42 U.S.C. § 7503

Permit requirements

Read at: OLRCuscode.house.gov CornellLII GovInfogovinfo.gov JustiaTitle 42 CasesGoogle Scholar
(a) In generalThe permit program required by section 7502(b)(6) 11 See References in Text note below. of this title shall provide that permits to construct and operate may be issued if—(1) in accordance with regulations issued by the Administrator for the determination of baseline emissions in a manner consistent with the assumptions underlying the applicable implementation plan approved under section 7410 of this title and this part, the permitting agency determines that—(A) by the time the source is to commence operation, sufficient offsetting emissions reductions have been obtained, such that total allowable emissions from existing sources in the region, from new or modified sources which are not major emitting facilities, and from the proposed source will be sufficiently less than total emissions from existing sources (as determined in accordance with the regulations under this paragraph) prior to the application for such permit to construct or modify so as to represent (when considered together with the plan provisions required under section 7502 of this title) reasonable further progress (as defined in section 7501 of this title); or(B) in the case of a new or modified major stationary source which is located in a zone (within the nonattainment area) identified by the Administrator, in consultation with the Secretary of Housing and Urban Development, as a zone to which economic development should be targeted, that emissions of such pollutant resulting from the proposed new or modified major stationary source will not cause or contribute to emissions levels which exceed the allowance permitted for such pollutant for such area from new or modified major stationary sources under section 7502(c) of this title;(2) the proposed source is required to comply with the lowest achievable emission rate;(3) the owner or operator of the proposed new or modified source has demonstrated that all major stationary sources owned or operated by such person (or by any entity controlling, controlled by, or under common control with such person) in such State are subject to emission limitations and are in compliance, or on a schedule for compliance, with all applicable emission limitations and standards under this chapter; and 22 So in original. The word “and” probably should not appear.(4) the Administrator has not determined that the applicable implementation plan is not being adequately implemented for the nonattainment area in which the proposed source is to be constructed or modified in accordance with the requirements of this part; and(5) an analysis of alternative sites, sizes, production processes, and environmental control techniques for such proposed source demonstrates that benefits of the proposed source significantly outweigh the environmental and social costs imposed as a result of its location, construction, or modification.Any emission reductions required as a precondition of the issuance of a permit under paragraph (1) shall be federally enforceable before such permit may be issued.(b) Prohibition on use of old growth allowances

Any growth allowance included in an applicable implementation plan to meet the requirements of section 7502(b)(5) of this title (as in effect immediately before November 15, 1990) shall not be valid for use in any area that received or receives a notice under section 7410(a)(2)(H)(ii) of this title (as in effect immediately before November 15, 1990) or under section 7410(k)(1) of this title that its applicable implementation plan containing such allowance is substantially inadequate.

(c) Offsets(1) The owner or operator of a new or modified major stationary source may comply with any offset requirement in effect under this part for increased emissions of any air pollutant only by obtaining emission reductions of such air pollutant from the same source or other sources in the same nonattainment area, except that the State may allow the owner or operator of a source to obtain such emission reductions in another nonattainment area if (A) the other area has an equal or higher nonattainment classification than the area in which the source is located and (B) emissions from such other area contribute to a violation of the national ambient air quality standard in the nonattainment area in which the source is located. Such emission reductions shall be, by the time a new or modified source commences operation, in effect and enforceable and shall assure that the total tonnage of increased emissions of the air pollutant from the new or modified source shall be offset by an equal or greater reduction, as applicable, in the actual emissions of such air pollutant from the same or other sources in the area.(2) Emission reductions otherwise required by this chapter shall not be creditable as emissions reductions for purposes of any such offset requirement. Incidental emission reductions which are not otherwise required by this chapter shall be creditable as emission reductions for such purposes if such emission reductions meet the requirements of paragraph (1).(d) Control technology information

The State shall provide that control technology information from permits issued under this section will be promptly submitted to the Administrator for purposes of making such information available through the RACT/BACT/LAER clearinghouse to other States and to the general public.

(e) Rocket engines or motorsThe permitting authority of a State shall allow a source to offset by alternative or innovative means emission increases from rocket engine and motor firing, and cleaning related to such firing, at an existing or modified major source that tests rocket engines or motors under the following conditions:(1) Any modification proposed is solely for the purpose of expanding the testing of rocket engines or motors at an existing source that is permitted to test such engines on November 15, 1990.(2) The source demonstrates to the satisfaction of the permitting authority of the State that it has used all reasonable means to obtain and utilize offsets, as determined on an annual basis, for the emissions increases beyond allowable levels, that all available offsets are being used, and that sufficient offsets are not available to the source.(3) The source has obtained a written finding from the Department of Defense, Department of Transportation, National Aeronautics and Space Administration or other appropriate Federal agency, that the testing of rocket motors or engines at the facility is required for a program essential to the national security.(4) The source will comply with an alternative measure, imposed by the permitting authority, designed to offset any emission increases beyond permitted levels not directly offset by the source. In lieu of imposing any alternative offset measures, the permitting authority may impose an emissions fee to be paid to such authority of a State which shall be an amount no greater than 1.5 times the average cost of stationary source control measures adopted in that area during the previous 3 years. The permitting authority shall utilize the fees in a manner that maximizes the emissions reductions in that area.(July 14, 1955, ch. 360, title I, § 173, as added Pub. L. 95–95, title I, § 129(b), Aug. 7, 1977, 91 Stat. 748; amended Pub. L. 95–190, § 14(a)(57), (58), Nov. 16, 1977, 91 Stat. 1403; Pub. L. 101–549, title I, § 102(c), Nov. 15, 1990, 104 Stat. 2415.)Editorial NotesReferences in Text

Section 7502(b) of this title, referred to in subsec. (a), was amended generally by Pub. L. 101–549, title I, § 102(b), Nov. 15, 1990, 104 Stat. 2412, and, as so amended, does not contain a par. (6). See section 7502(c)(5) of this title.

Amendments

1990—Pub. L. 101–549, § 102(c)(1), made technical amendment to section catchline.

Pub. L. 101–549, § 102(c)(2), (8), designated existing provisions as subsec. (a), inserted heading, and substituted “(1) shall be federally enforceable” for “(1)(A) shall be legally binding” in last sentence.

Subsec. (a)(1). Pub. L. 101–549, § 102(c)(3), inserted at beginning “in accordance with regulations issued by the Administrator for the determination of baseline emissions in a manner consistent with the assumptions underlying the applicable implementation plan approved under section 7410 of this title and this part,”.

Subsec. (a)(1)(A). Pub. L. 101–549, § 102(c)(4), inserted “sufficient offsetting emissions reductions have been obtained, such that” after “to commence operation,” and substituted “(as determined in accordance with the regulations under this paragraph)” for “allowed under the applicable implementation plan”.

Subsec. (a)(1)(B). Pub. L. 101–549, § 102(c)(5), inserted at beginning “in the case of a new or modified major stationary source which is located in a zone (within the nonattainment area) identified by the Administrator, in consultation with the Secretary of Housing and Urban Development, as a zone to which economic development should be targeted,” and substituted “7502(c)” for “7502(b)”.

Subsec. (a)(4). Pub. L. 101–549, § 102(c)(6), inserted at beginning “the Administrator has not determined that”, substituted “not being adequately implemented” for “being carried out”, and substituted “; and” for period at end.

Subsec. (a)(5). Pub. L. 101–549, § 102(c)(7), added par. (5).

Subsec. (b). Pub. L. 101–549, § 102(c)(9), added subsec. (b).

Subsecs. (c) to (e). Pub. L. 101–549, § 102(c)(10), added subsecs. (c) to (e).

1977—Par. (1)(A). Pub. L. 95–190, § 14(a)(57), inserted “or modified” after “from new” and “applicable” before “implementation plan”, and substituted “source” for “facility” wherever appearing.

Par. (4). Pub. L. 95–190, § 14(a)(58), added par. (4).

Statutory Notes and Related SubsidiariesFailure To Attain National Primary Ambient Air Quality Standards Under Clean Air Act

Pub. L. 100–202, § 101(f) [title II], Dec. 22, 1987, 101 Stat. 1329–187, 1329–199, provided that: “No restriction or prohibition on construction, permitting, or funding under sections 110(a)(2)(I), 173(4), 176(a), 176(b), or 316 of the Clean Air Act [sections 7410(a)(2)(I), 7503(4), 7506(a), (b), 7616 of this title] shall be imposed or take effect during the period prior to August 31, 1988, by reason of (1) the failure of any nonattainment area to attain the national primary ambient air quality standard under the Clean Air Act [this chapter] for photochemical oxidants (ozone) or carbon monoxide (or both) by December 31, 1987, (2) the failure of any State to adopt and submit to the Administrator of the Environmental Protection Agency an implementation plan that meets the requirements of part D of title I of such Act [this part] and provides for attainment of such standards by December 31, 1987, (3) the failure of any State or designated local government to implement the applicable implementation plan, or (4) any combination of the foregoing. During such period and consistent with the preceding sentence, the issuance of a permit (including required offsets) under section 173 of such Act [this section] for the construction or modification of a source in a nonattainment area shall not be denied solely or partially by reason of the reference contained in section 171(l) of such Act [section 7501(1) of this title] to the applicable date established in section 172(a) [section 7502(a) of this title]. This subsection [probably means the first 3 sentences of this note] shall not apply to any restriction or prohibition in effect under sections 110(a)(2)(I), 173(4), 176(a), 176(b), or 316 of such Act prior to the enactment of this section [Dec. 22, 1987]. Prior to August 31, 1988, the Administrator of the Environmental Protection Agency shall evaluate air quality data and make determinations with respect to which areas throughout the nation have attained, or failed to attain, either or both of the national primary ambient air quality standards referred to in subsection (a) [probably means the first 3 sentences of this note] and shall take appropriate steps to designate those areas failing to attain either or both of such standards as nonattainment areas within the meaning of part D of title I of the Clean Air Act.”

Notes of Decisions
Cited in 48 cases (4 in the last 5 years), 1979–2024 · leading case: Nat. Resources Def. Council v. Env't Prot. Agency, 571 F.3d 1245 (D.C. Cir. 2009).
Nat. Resources Def. Council v. Env't Prot. Agency, 571 F.3d 1245 (D.C. Cir. 2009). · cites it 26× “42 U.S.C. § 7503 (a)(1)(A) (1989). The EPA concluded that the "essence of [this] provision is that a new source may be *1267 allowed in a nonattainment area only where its presence would be consistent with RFP toward attainment of the NAAQS" and that this policy is satisfied if…”
Romoland Sch. Dist. v. Inland Empire Energy Ctr., LLC, 548 F.3d 738 (9th Cir. 2008). · cites it 6× “42 U.S.C. § 7503 (a)(1)-(2). SCAQMD implements its NSR program, now part of the California SIP, through Rule 1303, [2] which provides that the air district "shall deny the Permit to Construct for any new or modified source which results in a net emission increase in a…”
Sierra Club v. Douglas M. Costle, Adm'r of the Env't Prot. Agency, Nat'l Coal Ass'n, Alabama Power Co., Intervenors, 657 F.2d 298 (D.C. Cir. 1981). · cites it 4× “§§ 7470-79 ; Part D — Plan Requirements for Nonattainment Areas, sections 173(2), 42 U.S.C. §§ 7503 (2), 7501(3). 63 . I. e.”
Communities for a Better Env't v. Cenco Refining Co., 180 F. Supp. 2d 1062 (C.D. Cal. 2001). · cites it 4× “42 U.S.C. § 7503 (a)(2). Prior to issuing a permit to a new source of air pollutant emissions, the state must require an analysis of alternative sites, sizes, production processes and environmental control techniques for the proposed source that demonstrates that the benefits of…”
Sierra Club v. Moser, 310 P.3d 360 (Kan. 2013). · cites it 2× “2006) (citing 42 U.S.C. § 7503 ). If a permitting authority determines an owner has met these burdens and issues a PSD permit, the permitting authority must include limitations or conditions to ensure that emissions from the permitted facility: (1) will not cause or contribute…”
Texas v. Env't Prot. Agency, 726 F.3d 180 (D.C. Cir. 2013). · cites it 2× “” CAA § 173(a)(1), 42 U.S.C. § 7503 (a)(1) (emphasis added).”
New York v. U.S. Env't Prot. Agency, 413 F.3d 3 (D.C. Cir. 2005). “While states are responsible for writing SIPs, the Act gives EPA responsibility for developing basic rules for the NSR program, see 42 U.S.C. § 7503 (a)(1), a responsibility that clearly includes choosing a methodology for calculating baseline emissions.”
Sharon Steel Corp. v. Env't Prot. Agency, Bethlehem Steel Corp. v. Env't Prot. Agency, 597 F.2d 377 (3rd Cir. 1979). · cites it 2× “42 U.S.C.A. § 7503 (1)(A) (West Supp.1977) (emission offsets).”
Sierra Club v. United States Env't Prot. Agency, 774 F.3d 383 (7th Cir. 2014). · cites it 2× “Moderate nonattainment areas, Sierra Club points out, are subject to “non-attainment new source review” provisions pursuant to 42 U.S.C. § 7503 . Those provisions demand that new and modified sources of ozone-forming pollutants meet the “Lowest Achievable Emissions Rate” and…”
The Sierra Club v. U.S. EPA, 368 F.3d 1300 (11th Cir. 2004). · cites it 3× “42 U.S.C. § 7503 . We refer to this type of permit as a “preconstruction” permit.”
California Unions for Reliable Energy v. Mojave Desert Air Quality Mgmt. Dist., 178 Cal. App. 4th 1225 (Cal. Ct. App. 2009). · cites it 2× “( 42 U.S.C. § 7503 (a)(1)(A), (c).) The District “is the local agency with the primary responsibility for the development, implementation, monitoring, and enforcement of air pollution control strategies” for most of the Mojave Desert Air Basin.”
City of Seabrook, Texas v. United States Env't Prot. Agency, 659 F.2d 1349 (5th Cir. 1981). · cites it 2× “CAA § 173(1)(A), 42 U.S.C. § 7503 (1)(A) (emphasis added); see id.”
— 42 U.S.C. § 7503(c)(1) — 1 case