Wis. Stat.Chapter 779 — Liens

Wis. Stat. § 779.02 (2026)

Notice required to preserve lien rights; exceptions; saving clause; obligations of contractors

Edition and currency
laws through the 2025-26 session (checked Sept. 2026). The text is the edition Syfert holds; for a past event, check the version in force on that date.
Other sources
CURRENTlaws through the 2025-26 session (checked Sept. 2026) cited 1982–2026 75citing cases
At a glance

Courts have cited this section in 75 opinions since 1982, 19 of them in the last five years. The most litigated part is subsection (5) (49 cases).

779.02779.02 Notice required to preserve lien rights; exceptions; saving clause; obligations of contractors.
779.02(1)(1) Exceptions to notice requirement. The notice required to be given by lien claimants under sub. (2) shall not be required to be given in the following cases only:
779.02(1)(a)(a) By any laborer or mechanic employed by any prime contractor or subcontractor.
779.02(1)(b)(b) By any lien claimant who has contracted directly with the owner for the labor, services, materials, plans, or specifications performed, furnished, or procured, unless the claimant is a prime contractor subject to the notice requirement of sub. (2) (a).
779.02(1)(c)(c) By any lien claimant performing, furnishing, or procuring labor, services, materials, plans, or specifications for an improvement in any case where more than 4 family living units are to be provided or added by such work of improvement, if the improvement is wholly residential in character, or in any case where the improvement is partly or wholly nonresidential in character.
779.02(1)(d)(d) By any prime contractor who is personally an owner of the land to be improved, by any corporate prime contractor of which an owner of the land is an officer or controlling shareholder, by any prime contractor who is an officer or controlling shareholder of a corporation which is an owner of the land or by any corporate prime contractor managed or controlled by substantially the same persons who manage or control a corporation which is an owner of the land.
779.02(1)(e)(e) By any lien claimant, other than a prime contractor, who performs, furnishes, or procures labor, services, materials, plans, or specifications for an improvement on a project on which the prime contractor is not required to give notice under this section.
779.02(2)(2) Notice to owner, lender, and supplier.
779.02(2)(a)(a) Every prime contractor who enters into a contract with the owner for a work of improvement on the owner’s land and who has contracted or will contract with any subcontractors, suppliers, or service providers to perform, furnish, or procure labor, services, materials, plans, or specifications for the work of improvement shall include in any written contract with the owner the notice required by this paragraph, and shall provide the owner with a copy of the written contract. If no written contract for the work of improvement is entered into, the notice shall be prepared separately and served on the owner or authorized agent within 10 days after the first labor, services, materials, plans, or specifications are performed, furnished, or procured for the improvement by or pursuant to the authority of the prime contractor. The notice, whether included in a written contract or separately given, shall be in at least 8-point bold type, if printed, or in capital letters, if typewritten. It shall be in substantially the following language: “As required by the Wisconsin construction lien law, claimant hereby notifies owner that persons or companies performing, furnishing, or procuring labor, services, materials, plans, or specifications for the construction on owner’s land may have lien rights on owner’s land and buildings if not paid. Those entitled to lien rights, in addition to the undersigned claimant, are those who contract directly with the owner or those who give the owner notice within 60 days after they first perform, furnish, or procure labor, services, materials, plans or specifications for the construction. Accordingly, owner probably will receive notices from those who perform, furnish, or procure labor, services, materials, plans, or specifications for the construction, and should give a copy of each notice received to the mortgage lender, if any. Claimant agrees to cooperate with the owner and the owner’s lender, if any, to see that all potential lien claimants are duly paid”.
779.02(2)(b)(b) Every person other than a prime contractor who performs, furnishes, or procures labor, materials, plans, or specifications for an improvement shall have the lien and remedy under this subchapter only if within 60 days after performing, furnishing, or procuring the first labor, services, materials, plans, or specifications the person serves a written notice, in 2 signed copies, on the owner or authorized agent at the last-known post-office address. The owner or agent shall provide a copy of the notice received, within 10 days after receipt, to any mortgage lender who is furnishing or is to furnish funds for construction of the improvement to which the notice relates. The notice to the owner shall be in substantially the following language, with blanks accurately filled in: “As a part of your construction contract, your prime contractor or claimant has already advised you that those who perform, furnish, or procure labor, services, materials, plans, or specifications for the work will be notifying you. The undersigned first performed, furnished, or procured labor, services, materials, plans, or specifications on .... (give date) for the improvement now under construction on your real estate at .... (give legal description, street address or other clear description). Please give your mortgage lender the extra copy of this notice within 10 days after you receive this, so your lender, too, will know that the undersigned is included in the job”.
779.02(2)(c)(c) If any prime contractor required to give the notice prescribed in par. (a) fails to give notice as required, the prime contractor does not have the lien and remedy provided by this subchapter unless the prime contractor pays all of the prime contractor’s obligations to its subcontractors, suppliers, and service providers in respect to the work of improvement within the time periods under s. 779.06 and until the time for notice under par. (b) has elapsed and either none of its subcontractors, suppliers, or service providers gives notice as a lien claimant under par. (b) or all of its subcontractors, suppliers, and service providers have waived all lien rights in full under s. 779.05.
779.02(2)(d)(d) Every mortgage lender making an improvement or construction loan shall make reasonable inquiry of the owner as to whether any notices required by this subsection have been given. A lender is not required to pay out any loan proceeds unless or until the prime contractor has given any notice required of the prime contractor by this subsection.
779.02(2)(e)(e) If the owner or lender complains of any insufficiency of any notice, the burden of proof is upon the owner or lender to show that he or she has been misled or deceived by the insufficiency. If there is more than one owner, giving the notice required to any one owner or authorized agent is sufficient. In addition, every prime contractor and subcontractor, at the time of purchasing or contracting for any materials to be used in any of the cases enumerated in s. 779.01, shall upon request deliver to the supplier a description of the real estate upon which the materials are to be used and the name and post-office address of the owner and authorized agent, if any. Failure to receive such description and name and address does not relieve a supplier who asserts a lien from the requirement of giving timely notice.
779.02(3)(3) Failure to give notice; saving clause. Any lien claimant, other than the prime contractor, who fails to give a notice as required by sub. (2) (b) shall have no lien on the land or improvement to which the failure relates. Any claimant who serves a late but otherwise proper notice on the owner or authorized agent shall have the lien provided by s. 779.01 for any labor, services, materials, plans, or specifications performed, furnished, or procured after the late notice is actually received by the owner. The burden of proving that labor, services, materials, plans, or specifications for which a lien is claimed were furnished after that date is on the lien claimant.
779.02(4)(4) Notice and filing requirements in s. 779.06 unaffected. Nothing in this section shall be construed to relieve any lien claimant of the notice and filing requirements under s. 779.06.
779.02(5)(5) Theft by contractors. The proceeds of any mortgage on land paid to any prime contractor or any subcontractor for improvements upon the mortgaged premises, and all moneys paid to any prime contractor or subcontractor by any owner for improvements, constitute a trust fund only in the hands of the prime contractor or subcontractor to the amount of all claims due or to become due or owing from the prime contractor or subcontractor for labor, services, materials, plans, and specifications used for the improvements, until all the claims have been paid, and shall not be a trust fund in the hands of any other person. The use of any such moneys by any prime contractor or subcontractor for any other purpose until all claims, except those which are the subject of a bona fide dispute and then only to the extent of the amount actually in dispute, have been paid in full or proportionally in cases of a deficiency, is theft by the prime contractor or subcontractor of moneys so misappropriated and is punishable under s. 943.20. If the prime contractor or subcontractor is a corporation, limited liability company, or other legal entity other than a sole proprietorship, such misappropriation also shall be deemed theft by any officers, directors, members, partners, or agents responsible for the misappropriation. Any of such misappropriated moneys which have been received as salary, dividend, loan repayment, capital distribution or otherwise by any shareholder, member, or partner not responsible for the misappropriation shall be a civil liability of that person and may be recovered and restored to the trust fund specified in this subsection by action brought by any interested party for that purpose. Except as provided in this subsection, this section does not create a civil cause of action against any person other than the prime contractor or subcontractor to whom such moneys are paid. Until all claims are paid in full, have matured by notice and filing or have expired, such proceeds and moneys shall not be subject to garnishment, execution, levy or attachment.
779.02(6)(6) Prime contractors to defend lien actions. Where a lien is filed under this subchapter by any person other than the prime contractor, the prime contractor shall defend any action thereon at personal expense, and during the pendency of the action the owner may withhold from the prime contractor the amount for which the lien was filed and sufficient to defray the costs of the action. In case of judgment against the owner, the owner may deduct from any amount due to the prime contractor the amount of the judgment and if the judgment exceeds the amount due, the owner may recover the difference from the prime contractor. This subsection does not apply if the lien is the result of the failure of the owner to pay the prime contractor.
779.02(7)(7) Wrongful use of materials. Any prime contractor or any subcontractor furnishing materials who purchases materials on credit and represents at the time of making the purchase that the materials are to be used in a designated building or other improvement and thereafter uses or causes them to be used in the construction of any improvement other than that designated, without the written consent of the seller, may be fined not more than $300 or imprisoned not more than 3 months.
779.02(8)(8) Wage payments to laborer apply to earlier work. In any situation where a laborer or mechanic employed by any prime contractor or subcontractor has wage payments due and has worked on more than one improvement for the employer during the period for which the wages are due, and a payment of less than all wages due is made, the payment is deemed to apply to the unpaid work in chronological sequence starting with the earliest unpaid time, unless the laborer agrees in writing that the payment shall be applied in a different way.
779.02 AnnotationIt is not necessary to show that the defendant received benefits from a misappropriation of trust funds in order for the plaintiff to recover. A showing of wrongful intent is not required to establish civil liability under sub. (5). Burmeister Woodwork Co. v. Friedel, 65 Wis. 2d 293, 222 N.W.2d 647 (1974).
779.02 AnnotationWhen the lessor had not paid the lessee for improvements to the lessor’s property by the lessee’s contractor, the contractor had a claim for unjust enrichment against the lessor even though the contractor lost its lien rights against the lessor by failing to give the notice required under sub. (2) (a). S&M Rotogravure Service, Inc. v. Baer, 77 Wis. 2d 454, 252 N.W.2d 913 (1977).
779.02 AnnotationIntent to defraud must be proved when criminal sanctions are sought under sub. (5). State v. Blaisdell, 85 Wis. 2d 172, 270 N.W.2d 69 (1978).
779.02 AnnotationBecause an entire project was covered by one contract, three buildings on three adjoining lots constituted a single improvement under sub. (1) (c). Cline-Hanson, Inc. v. Esselman, 107 Wis. 2d 381, 319 N.W.2d 829 (1982).
779.02 AnnotationSub. (5) does not require that payments be made directly from the owner to the subcontractors for a trust to be created. Money deposited into a bank did not lose its trust fund status. Kraemer Bros. v. Pulaski State Bank, 138 Wis. 2d 395, 406 N.W.2d 379 (1987).
779.02 AnnotationA trust fund under sub. (5) is created when an owner constructively pays an insolvent contractor by delivering money to the clerk of court seeking a declaratory judgment as to distribution. A subcontractor need not preserve lien rights. Wisconsin Dairies Cooperative v. Citizens Bank & Trust, 160 Wis. 2d 758, 467 N.W.2d 124 (1991).
779.02 AnnotationA violation of sub. (5) may be found without showing that the prime contractor intended to permanently deprive laborers and suppliers of compensation. The intent required is to use the moneys subject to a trust inconsistent with the purpose of the trust. State v. Sobkowiak, 173 Wis. 2d 327, 496 N.W.2d 620 (Ct. App. 1992).
779.02 AnnotationUnder sub. (5), a corporate officer who had the power and authority to ensure that corporate affairs were properly managed and who did not receive a personal benefit may be personally responsible for a misappropriation. Capen Wholesale, Inc. v. Probst, 180 Wis. 2d 354, 509 N.W.2d 120 (Ct. App. 1993).
779.02 AnnotationThe prime contractor’s duty under sub. (6) to defend the property owners against subcontractors’ lien claims is not altered because the prime contractor is also owed money. Torke/Wirth/Pujara, Ltd. v. Lakeshore Towers of Racine, 192 Wis. 2d 481, 531 N.W.2d 419 (Ct. App. 1995).
779.02 AnnotationThe exemption under sub. (1) (c) to the notice requirement for improvements when more than four residential units are provided is not restricted to the actual provision of the dwellings, but also applies to improvements that facilitate providing the dwellings when the improvements are not provided to each living unit separately but are provided to a project as a whole. Riverwood Park, Inc. v. Central Ready-Mixed Concrete, Inc., 195 Wis. 2d 821, 536 N.W.2d 722 (Ct. App. 1995), 94-2413.
779.02 AnnotationThe test for a violation of sub. (5) is whether all the money received by the contractor was paid for labor and materials used for contracted improvements. It is not whether an individual subcontractor received its full billed amount. Capital City Sheet Metal, Inc. v. Voytovich, 217 Wis. 2d 683, 578 N.W.2d 643 (Ct. App. 1998), 97-1588.
779.02 AnnotationWhen a lien claimant’s work was essential to allow an improvement to be used for its intended purpose and the improved area exceeded 10,000 square feet, the work “provided” 10,000 square feet of space to the facility under former sub. (1) (c), 1995 stats., and the claimant was exempt from the sub. (2) lien notice requirement. United States Fire Protection, Wisconsin, Inc. v. St. Michael’s Hospital of Franciscan Sisters, Milwaukee, Inc., 221 Wis. 2d 410, 585 N.W.2d 659 (Ct. App. 1998), 97-3426.
779.02 AnnotationUnder sub. (5), a misuse of contractor trust funds can form the basis of a prosecution for criminal theft by contractor under s. 943.20. Because s. 943.20 qualifies for treble damages under s. 895.80, treble damages are available for theft by contractor under sub. (5), provided that the elements of both the civil and the criminal statutes, including the specific criminal intent element required by s. 943.20, are proven to the civil preponderance burden of proof. Tri-Tech Corp. of America v. Americomp Services, Inc., 2002 WI 88, 254 Wis. 2d 418, 646 N.W.2d 822, 00-3195.
779.02 AnnotationWhile money cannot be used for purposes outside of the project, that does not end contractors’ responsibilities under the statute. Using the money to pay themselves in full while other subcontractors have not been paid proportionally constitutes using money for a non-statutory purpose. State v. Keyes, 2008 WI 54, 309 Wis. 2d 516, 750 N.W.2d 30, 04-1104.
779.02 AnnotationMonies paid to the trustee in bankruptcy of an insolvent contractor are not trust funds. Wisconsin Furnace Supply Corp. v. Kroog, 322 F. Supp. 1161 (1971).
779.02 AnnotationWisconsin’s Construction Trust Fund Statute: Protecting Against Theft by Contractor. Hinkston. Wis. Law. May 2005.
The 20 cases that cite Wis. Stat. § 779.02 most heavily, weighted by court and treatment. RelevanceNewestTreatment
1
GREENTri-Tech Corp. of Am. v. Americomp Servs., Inc., 2002 WI 88, 646 N.W.2d 822.
cites § 779.02 74×subsections: (5) 2×cited by 35 cases
Where it cites § 779.02
“80 (1999-2000) [1] is available for civil theft by contractor under Wis. Stat. § 779.02 (5), and if so, whether it requires proof of the elements of the criminal offense under Wis.”
The case’s holding
The issue of intent is generally not readily susceptible of determination on summary judgment because it requires an assessment of subjective credibility.
Later courts cite it for
“the issue of intent is generally not readily susceptible of determination on summary judgment.” · 2 citing courts
2
GREENState v. Keyes, 2007 WI App 163, 736 N.W.2d 904.
cites § 779.02 184×subsections: (5) 95× (2) 7×cited by 3 cases
Where it cites § 779.02
“02(2) is apparently a typographical error; the theft by contractor provision of § 779.02 is subsection (5), not (2). It is clear that this reference is a typographical error, rather than an intentional reference to subsection § 779.02(2), because the information contains the "theft by contractor" heading, which can only describe § 779.02(5), not § 779.02(2).”
3
GREENHellenbrand Glass, LLC v. Pulvermacher (In re Pulvermacher), 567 B.R. 881 (Bankr. W.D. Wis. 2017).
cites § 779.02 33×subsections: (5) 13×cited by 11 cases
Where it cites § 779.02
“Hellenbrand filed suit in Dane County Circuit Court alleging a claim for theft by contractor under Wis. Stat. § 779.02 (5) (the “Circuit Court Case”).”
Later courts cite it for
“res judicata does not apply in nondischargeability proceedings.” · 2 citing courts
4
GREENState v. Keyes, 2008 WI 54, 750 N.W.2d 30.
cites § 779.02 43×subsections: (5) 23×cited by 6 cases
Where it cites § 779.02
“1 The Keyes were each charged with felony theft by contractor, party to a crime, in violation of Wis. Stat. §§ 779.02 (5) and 943.20(l)(b) (1999-2000).”
5
GREENGanther Constr., Inc. v. Ward (In re Ward), 417 B.R. 582 (Bankr. E.D. Wis. 2009).
cites § 779.02 32×subsections: (5) 8×cited by 8 cases
Where it cites § 779.02
“Specifically, the plaintiff alleged that the defendant incurred the debt through the commission of “theft by contractor,” in violation of Wis. Stat. § 779.02 (5). The parties have tried the case, and based on the evidence presented at that trial, the Court concludes that the…”
6
GREENCapen Wholesale, Inc. v. Probst, 509 N.W.2d 120 (Wis. Ct. App. 1993).
cites § 779.02 34×subsections: (5) 34×cited by 10 cases
Where it cites § 779.02
“Probst (Probst Senior) appeals from a judgment following a bench trial in *357 which he was found liable for civil theft by contractor, in violation of sec. 779.02(5), Stats. He argues that although he was a corporate officer and director, he was not "responsible for the…”
7
GREENRiverwood Park, Inc. v. Cent. Ready-Mixed Concrete, Inc., 536 N.W.2d 722 (Wis. Ct. App. 1995).
cites § 779.02 28×subsections: (1)(c) 18× (2) 4× (2)(b) 3× (1)cited by 12 cases
Where it cites § 779.02
“[Section 779.02, STATS.,] eliminates any notice requirement.”
The case’s holding
A subdivision project qualifies for the lien notice exemption if it adds more than four family units, regardless of whether the supplied materials themselves create living units.
Later courts cite it for
“if the language is clear and unambiguous on its face, we must construe the statute in accordance with its ordinary meaning and may not resort to extrinsic aids.” · 1 citing court
8
GREENLevine v. Ward (In re Ward), 425 B.R. 507 (Bankr. E.D. Wis. 2010).
cites § 779.02 24×subsections: (5) 10×cited by 7 cases
Where it cites § 779.02
“Wis. Stat. § 779.02 (5) — one digit off from the section the plaintiffs cited — is the portion of Wisconsin’s theft-by-contractor statute that prohibits theft by contractors involved in private work, as op *520 posed to § 779.16’s prohibition against theft by contractors involved in public improvement work.”
9
GREENWisconsin Dairies Coop. v. Citizens Bank & Trust, 467 N.W.2d 124 (Wis. 1991).
cites § 779.02 27×subsections: (5) 26× (2)cited by 10 cases
Where it cites § 779.02
“The Bank asserts that this language was intended to restrict a claimant's protection to a limited time period, beginning when the claimant contributes supplies or labor and ending at the earliest of three occurrences: (1) when the claimant achieves status as a perfected…”
10
GREENMurphy v. Droessler, 525 N.W.2d 117 (Wis. Ct. App. 1994).
cites § 779.02 43×subsections: (2)(b) 25× (2) 6× (2)(e) 4× (3) 3×cited by 4 cases
Where it cites § 779.02
“, gives persons who supply labor or materials for an improvement to real estate a lien on the land, provided they comply with § 779.02, Stats. With certain exceptions not applicable here, § 779.02 requires that the furnisher of labor or materials give notice within sixty days after furnishing the first labor or materials.”
11
GREENFischer Constr., LLC v. Ecker (In re Ecker), 400 B.R. 669 (Bankr. E.D. Wis. 2009).
cites § 779.02 19×subsections: (5) 5×cited by 6 cases
Where it cites § 779.02
“” See Wis. Stat. § 779.02 (5) (2003-04). For improvements that visibly commenced on or after April 11, 2006, the statute provided that moneys paid to a contractor constituted a trust fund to the amount of all claims due or to become due or owing from the prime contractor or…”
Later courts cite it for
“for fraud or defalcation while acting in a fiduciary capacity, embezzlement, or larceny.” · 2 citing courts
12
GREENHoida, Inc. v. M & I Midstate Bank, 2006 WI 69, 717 N.W.2d 17.
cites § 779.02 4×cited by 118 cases
Where it cites § 779.02
“On March 5, 1997, as a result of not being paid, Hoida wrote to Villager and explained that pursuant to Wis. Stat. § 779.02 , it possessed lien rights on the project property.”
The case’s holding
A lender and its agent do not owe a duty of ordinary care to subcontractors to identify them, verify work progress, or collect lien waivers unless such obligations are contractually assumed.
Later courts cite it for
“ordinary care involves the concept of foreseeability, in that a reasonable person exercising ordinary care would have foreseen injury as a consequence of his or her act.” · 4 citing courts
13
GREENW.H. Major & Sons, Inc. v. Krueger, 369 N.W.2d 400 (Wis. Ct. App. 1985).
cites § 779.02 17×subsections: (5) 17×cited by 9 cases
Where it cites § 779.02
“00 together with costs and interest against the defendant Ronald Krueger, an officer and shareholder of T-K Incorporated, under sec. 779.02(5), Stats., the theft by contractor statute.”
14
GREENRomes Design, Inc. v. Dinkins (In re Dinkins ), 327 B.R. 918 (Bankr. E.D. Wis. 2005).
cites § 779.02 12×subsections: (5) 6×cited by 6 cases
Where it cites § 779.02
“The proceeds of any mortgage on land paid to any prime contractor or any subcontractor for improvements upon the mortgaged premises, and all moneys paid to any prime contractor or subcontractor by any owner for improvements, constitute a trust fund only in the hands of the prime…”
Later courts cite it for
“if the prime contractor or subcontractor is a corporation, such misappropriation also shall be deemed theft by any officers, directors or agents of the corporation responsible for the misappropriation.” · 2 citing courts
15
GREENDavid Skindzelewski v. Joseph Smith, Jr., 2020 WI 57, 944 N.W.2d 575.
cites § 779.02 4×cited by 13 cases
Where it cites § 779.02
“BACKGROUND ¶3 In March 2014, the State charged Skindzelewski with theft by contractor in violation of Wis. Stat. § 779.02 (5) (2009- 10) after Skindzelewski failed to perform work for which he was 1 Skindzelewski v.”
The case’s holding
A criminal defendant suing his defense attorney for legal malpractice must prove actual innocence of the crime of conviction; a missed statute-of-limitations defense does not excuse that requirement.
Later courts cite it for
“to prove causation and injury, a plaintiff must show that 'but for the negligence of the attorney, the client would have been successful in the prosecution or defense of an action.” · 2 citing courts
16
GREENState v. Sobkowiak, 496 N.W.2d 620 (Wis. Ct. App. 1992).
cites § 779.02 10×subsections: (5) 10×cited by 9 cases
Where it cites § 779.02
“Even if relevant, Sobkowiak does not show how the credit arrangement with Northwest Wholesale Lumber and its waiver of its lien rights would have legit *333 imated his use of the trust fund created under sec. 779.02(5), Stats., for his personal purposes.”
The case’s holding
A prime contractor commits theft by intentionally using construction loan trust funds for purposes other than paying lien claims before all such claims are paid; intent to use trust funds inconsistently suffices.
Later courts cite it for
“the defendant intentionally used a part of the money for a purpose other than the payment of claims due or to become due from him for labor or materials used in the improvements before all claims were paid in full.” · 1 citing court
17
GREENCapital City Sheet Metal, Inc. v. Voytovich, 578 N.W.2d 643 (Wis. Ct. App. 1998).
cites § 779.02 11×subsections: (5) 11×cited by 6 cases
Where it cites § 779.02
“1 Capital City *686 sought to hold Timm Fehrman personally liable for that amount under § 779.02(5), Stats., which provides in pertinent part: (5) Theft BY CONTRACTORS.”
Later courts cite it for
“using the funds for some other purpose - whether personal or corporate - violates the theft by contractor statute, and the officers of the corporation may be held personally liable to the subcontractors and suppliers.” · 2 citing courts
18
GREENJames Cape & Sons Co. v. Bowles (In re Bowles), 318 B.R. 129 (Bankr. E.D. Wis. 2004).
cites § 779.02 5×subsections: (5)cited by 10 cases
Where it cites § 779.02
“Wis. Stat. § 779.02 (5) states in pertinent part: The proceeds of any mortgage on land paid to any prime contractor or any subcontractor for improvements upon the mortgaged premises, and all moneys paid to any prime contractor or subcontractor by any owner for improvements,…”
19
GREENState v. Longmire, 2004 WI App 90, 681 N.W.2d 534.
cites § 779.02 3×subsections: (5)cited by 20 cases
Where it cites § 779.02
“The La Crosse County District Attorney charged Longmire with one count of felony theft by contractor, Wis. Stat. §§ 779.02 (5) and 943.20(l)(b), 2 and two counts of misdemeanor home improvement *770 fraud.”
The case’s holding
A trial court may only order restitution if the defendant's criminal activity was a substantial factor in causing pecuniary injury to the victim.
Later courts cite it for
“first, before a trial court may order restitution 'there must be a showing that the defendant's criminal activity was a substantial factor in causing' pecuniary injury to the victim.” · 2 citing courts
20
GREENChase Lumber & Fuel Co. v. Koch (In re Koch), 197 B.R. 654 (Bankr. W.D. Wis. 1996).
cites § 779.02 4×subsections: (5) 4×cited by 26 cases
Where it cites § 779.02
“Wisconsin’s “theft-by-contractor” statute, Wis.Stat. § 779.02(5), is part of Wisconsin’s construction lien law, Wis.”
The case’s holding
A contractor's failure to pay trust funds under Wisconsin's theft-by-contractor statute is nondischargeable defalcation only if the creditor proves more than negligence, and the contractor's knowledge is material.
Later courts cite it for
“suggesting only that something akin to 'reckless' may be the appropriate standard.” · 3 citing courts

Show all 75 citing cases (list view) →

The flag is Syfertize’s treatment of the citing case itself, not of the statute. “Where it cites” is the passage in the opinion; the holding is a summary of the whole case and may concern another point. Annotations are extracted automatically from the opinions in the Syfert caselaw corpus.

Citing cases by year
198220042026

One bar per year. Tallest: 7 cases in 2023. 2026 is a partial year. These are opinions in the Syfert collection, which holds more of some courts’ recent opinions than their older ones, so a rise can reflect what the collection holds and not more litigation.

By court
Wis. Ct. App.33Bankr. E.D. Wis.15Bankr. W.D. Wis.9E.D. Wis.6Wis.67th Cir.2W.D. Wis.2Bankr. D. Del.1

The 8 courts with the most citing cases, of 9 courts in all.

By subsection
(1)3 cases
Sullivan Bros. v. State Bank of Union Grove, 321 N.W.2d 545 (Wis. Ct. App. 1982).
Riverwood Park, Inc. v. Cent. Ready-Mixed Concrete, Inc., 536 N.W.2d 722 (Wis. Ct. App. 1995).“[Section 779.02, STATS.,] eliminates any notice requirement.”
(1)(a)1 case
CTW Flooring, Inc. v. Brandon Dittberner, 11 N.W.3d 451 (Wis. Ct. App. 2024).
(1)(b)1 case
CTW Flooring, Inc. v. Brandon Dittberner, 11 N.W.3d 451 (Wis. Ct. App. 2024).
(1)(c)3 cases
Riverwood Park, Inc. v. Cent. Ready-Mixed Concrete, Inc., 536 N.W.2d 722 (Wis. Ct. App. 1995).
McQuay-Perfex, Inc. v. Wisconsin Tel. Co., 381 N.W.2d 586 (Wis. Ct. App. 1985).
(2)5 cases
State v. Keyes, 2007 WI App 163, 736 N.W.2d 904.“02(2) is apparently a typographical error; the theft by contractor provision of § 779.02 is subsection (5), not (2). It is clear that this reference is a typographical error, rather than an intentional reference to subsection § 779.02(2), because the information contains the "theft by contractor" heading, which can only describe § 779.02(5), not § 779.02(2).”
Riverwood Park, Inc. v. Cent. Ready-Mixed Concrete, Inc., 536 N.W.2d 722 (Wis. Ct. App. 1995).
Murphy v. Droessler, 525 N.W.2d 117 (Wis. Ct. App. 1994).“, gives persons who supply labor or materials for an improvement to real estate a lien on the land, provided they comply with § 779.02, Stats. With certain exceptions not applicable here, § 779.02 requires that the furnisher of labor or materials give notice within sixty days after furnishing the first labor or materials.”
Troutman v. FMC Corp., 340 N.W.2d 581 (Wis. Ct. App. 1983).
Wisconsin Dairies Coop. v. Citizens Bank & Trust, 467 N.W.2d 124 (Wis. 1991).“The Bank asserts that this language was intended to restrict a claimant's protection to a limited time period, beginning when the claimant contributes supplies or labor and ending at the earliest of three occurrences: (1) when the claimant achieves status as a perfected…”
(2)(a)1 case
CTW Flooring, Inc. v. Brandon Dittberner, 11 N.W.3d 451 (Wis. Ct. App. 2024).
(2)(b)5 cases
Murphy v. Droessler, 525 N.W.2d 117 (Wis. Ct. App. 1994).
Riverwood Park, Inc. v. Cent. Ready-Mixed Concrete, Inc., 536 N.W.2d 722 (Wis. Ct. App. 1995).
McQuay-Perfex, Inc. v. Wisconsin Tel. Co., 381 N.W.2d 586 (Wis. Ct. App. 1985).
CTW Flooring, Inc. v. Brandon Dittberner, 11 N.W.3d 451 (Wis. Ct. App. 2024).
(2)(e)1 case
Murphy v. Droessler, 525 N.W.2d 117 (Wis. Ct. App. 1994).
(3)1 case
Murphy v. Droessler, 525 N.W.2d 117 (Wis. Ct. App. 1994).
(5)49 cases
State v. Keyes, 2007 WI App 163, 736 N.W.2d 904.
Hellenbrand Glass, LLC v. Pulvermacher (In re Pulvermacher), 567 B.R. 881 (Bankr. W.D. Wis. 2017).“Hellenbrand filed suit in Dane County Circuit Court alleging a claim for theft by contractor under Wis. Stat. § 779.02 (5) (the “Circuit Court Case”).”
Capen Wholesale, Inc. v. Probst, 509 N.W.2d 120 (Wis. Ct. App. 1993).“Probst (Probst Senior) appeals from a judgment following a bench trial in *357 which he was found liable for civil theft by contractor, in violation of sec. 779.02(5), Stats. He argues that although he was a corporate officer and director, he was not "responsible for the…”
State v. Keyes, 2008 WI 54, 750 N.W.2d 30.“1 The Keyes were each charged with felony theft by contractor, party to a crime, in violation of Wis. Stat. §§ 779.02 (5) and 943.20(l)(b) (1999-2000).”
Showing the top 5 of 49. More in the list view →
(6)1 case
Torke/Wirth/Pujara, Ltd. v. Lakeshore Towers of Racine, 531 N.W.2d 419 (Wis. Ct. App. 1995).

Show all 75 citing cases (list view) →

Enactment and amendments

Syfert holds no separate history line for this section. Where this code prints a source or history note, it appears with the text, usually at the end.

Versions

Edition shown: laws through the 2025-26 session (checked Sept. 2026). Syfert holds no earlier or later version of this section.