Wis. Stat. § 779.01 (2026)
Construction liens
Edition and currency
Other sources
Courts have cited this section in 30 opinions since 1981, 1 of them in the last five years. The most litigated part is subsection (2)(a) (6 cases).
- Where it cites § 779.01
- “We also conclude that the claim Hoida seeks to establish against M & I is barred by the legislative determination of priority as between a lender and a subcontractor set out in Wis. Stat. § 779.01 (4) (2003-04) [1] and Wis.”
- The case’s holding
- A lender and its agent do not owe a duty of ordinary care to subcontractors to identify them, verify work progress, or collect lien waivers unless such obligations are contractually assumed.
- Later courts cite it for
- “ordinary care involves the concept of foreseeability, in that a reasonable person exercising ordinary care would have foreseen injury as a consequence of his or her act.” · 4 citing courts
- Where it cites § 779.01
- “The court of appeals also held as a matter of law that computer network cabling constituted an improvement providing a permanent benefit to property within the meaning of Wis. Stat. §§ 779.01 (2)(a) and 779.02(5).”
- The case’s holding
- The issue of intent is generally not readily susceptible of determination on summary judgment because it requires an assessment of subjective credibility.
- Later courts cite it for
- “the issue of intent is generally not readily susceptible of determination on summary judgment.” · 2 citing courts
- Where it cites § 779.01
- “Wis. Stat. § 779.01 (3) (2015-16). 1 Construction liens are statutory creatures, and if a lien is properly perfected, it becomes an encumbrance against the real estate in the same manner as a mortgage or a judgment lien.”
- Where it cites § 779.01
- “Assignment of a claim or right to a lien or any part thereof by a prime contractor, or garnishment by the creditor of a prime contractor, subcontractor, supplier, service provider, laborer or mechanic, shall not operate to compel the owner, prime contractor, subcontractor,…”
- Where it cites § 779.01
- “However, evaluating the work of those doing the improvements, described in Wis. Stat. § 779.01 (2)(a) as “building, structure, erection, fixture, demolition, alteration, excavation, filling, grading, tiling, planting, clearing, or landscaping,” is qualitatively different from…”
- Later courts cite it for
- “if the prime contractor or subcontractor is a corporation, such misappropriation also shall be deemed theft by any officers, directors or agents of the corporation responsible for the misappropriation.” · 2 citing courts
- Where it cites § 779.01
- “02(5), is part of Wisconsin’s construction lien law, Wis.Stat. § 779.01 et. seq. (1993-94), and purports to create a fiduciary relationship, to wit: [A]ll moneys paid to any prime contractor or subcontractor by any owner for improvements, constitute a trust fund only in the…”
- The case’s holding
- A contractor's failure to pay trust funds under Wisconsin's theft-by-contractor statute is nondischargeable defalcation only if the creditor proves more than negligence, and the contractor's knowledge is material.
- Later courts cite it for
- “suggesting only that something akin to 'reckless' may be the appropriate standard.” · 3 citing courts
- Where it cites § 779.01
- “” Wis. Stat. § 779.01 (2)(a) (2003-04). By adding “repairing or remodeling .”
- Later courts cite it for
- “for fraud or defalcation while acting in a fiduciary capacity, embezzlement, or larceny.” · 2 citing courts
- Where it cites § 779.01
- “We agree with Central that the definition of "improvement" in § 779.01(2)(a), Stats., clearly suggests that the legislature intended liens to be available for work besides the physical improvement of a residential building.”
- The case’s holding
- A subdivision project qualifies for the lien notice exemption if it adds more than four family units, regardless of whether the supplied materials themselves create living units.
- Later courts cite it for
- “if the language is clear and unambiguous on its face, we must construe the statute in accordance with its ordinary meaning and may not resort to extrinsic aids.” · 1 citing court
- Where it cites § 779.01
- “§ 779.01, and "mechanic's lien" to describe liens arising from work on personal property.”
- Where it cites § 779.01
- “See Wis. Stat. § 779.01 . " 'A construction lien is a remedy created by statute to insure payment to contractors, subcontractors, tradesmen, laborers, and materialmen who have furnished labor or materials in good faith for improvement of another's property.”
- Later courts cite it for
- “the judiciary is limited to applying the policy the legislature has chosen to enact, and may not impose its own policy choices.” · 1 citing court
- Where it cites § 779.01
- “" Section 779.01(2)(b), STATS. Siesel and Dentinger qualify as lien claimants under this definition.”
- Where it cites § 779.01
- “2 Section 779.01(3), Stats., provides in part: Every person who performs any work or procures its performance or furnishes any labor or materials or plans or specifications for the improvement of land, and who complies with s.”
- Where it cites § 779.01
- “1 Section 779.01 (2) (d), Stats., provides: "Prime contractor" means: 1.”
- The case’s holding
- A prime contractor commits theft by intentionally using construction loan trust funds for purposes other than paying lien claims before all such claims are paid; intent to use trust funds inconsistently suffices.
- Later courts cite it for
- “the defendant intentionally used a part of the money for a purpose other than the payment of claims due or to become due from him for labor or materials used in the improvements before all claims were paid in full.” · 1 citing court
- Where it cites § 779.01
- “Section 779.01 (4), Stats., declares: When new construction is the principal improvement involved, commencement is deemed to occur no earlier than the beginning of substantial excavation for the foundations, footings or base of the new construction, except where the new…”
- Where it cites § 779.01
- “In Sullivan, the court determined that the word "alteration" in the definition of improvement found in sec. 779.01(2), Stats., 2 "indicates that the term .”
- Later courts cite it for
- “statutes providing lien remedies to laborers and materialmen . . . liberally . . . in favor of the lien claimants.” · 2 citing courts
- Where it cites § 779.01
- “Since § 779.01(3), Stats., makes compliance with § 779.02(2) a prerequisite for a valid lien, neither subcontractor has á valid lien.”
- Where it cites § 779.01
- “Accordingly, although we use different reasoning than the circuit court, we agree with its conclusion that the term "construction hen" in the contract unambiguously excludes La Quinta's mortgage interest. Conclusion ¶ 70. Although we reject each of MPC's arguments and would,…”
- Where it cites § 779.01
- “See Wis. Stat. § 779.01 . "A construction lien is a remedy created by statute to insure payment to contractors, subcontractors, [tradesper-sons], laborers and [material suppliers] who have furnished labor or materials in good faith for the improvement of another's property.”
- Later courts cite it for
- “a general purpose of the construction lien laws is to ensure the payment of construction project subcontractors and material suppliers.” · 2 citing courts
- Summary
- No passage or summary on file for this case yet.
- Where it cites § 779.01
- “However, Home Depot offers no authority supporting this contention, and Wisconsin’s construction lien law expressly provides that prime contractors who contract to improve land “shall have a lien therefor on all interests in the land belonging to its owners.”
Show all 30 citing cases (list view) →
The flag is Syfertize’s treatment of the citing case itself, not of the statute. “Where it cites” is the passage in the opinion; the holding is a summary of the whole case and may concern another point. Annotations are extracted automatically from the opinions in the Syfert caselaw corpus.
One bar per year. Tallest: 3 cases in 2002. These are opinions in the Syfert collection, which holds more of some courts’ recent opinions than their older ones, so a rise can reflect what the collection holds and not more litigation.
(2)1 case
(2)(a)6 cases
(2)(b)1 case
(2)(c)3 cases
(2)(d)3 cases
(3)5 cases
(4)4 cases
(5)1 case
Syfert holds no separate history line for this section. Where this code prints a source or history note, it appears with the text, usually at the end.
Edition shown: laws through the 2025-26 session (checked Sept. 2026). Syfert holds no earlier or later version of this section.