C.F.R.Title 33Chapter II—Corps of Engineers, Department of the Army, Department of DefensePart 330—Nationwide Permit Program

33 C.F.R. § 330.1 (2026)

Purpose and policy

Edition and currency
eCFR text as of Sept. 29, 2026. The text is the edition Syfert holds; for a past event, check the version in force on that date.
Other sources
CURRENTeCFR text as of Sept. 29, 2026 cited 1986–2026 64citing cases
At a glance

Courts have cited this section in 64 opinions since 1986, 6 of them in the last five years. The most litigated part is subsection (c) (1 case).

(a) Purpose. This part describes the policy and procedures used in the Department of the Army's nationwide permit program to issue, modify, suspend, or revoke nationwide permits; to identify conditions, limitations, and restrictions on the nationwide permits; and, to identify any procedures, whether required or optional, for authorization by nationwide permits.

(b) Nationwide permits. Nationwide permits (NWPs) are a type of general permit issued by the Chief of Engineers and are designed to regulate with little, if any, delay or paperwork certain activities having minimal impacts. The NWPs are proposed, issued, modified, reissued (extended), and revoked from time to time after an opportunity for public notice and comment. Proposed NWPs or modifications to or reissuance of existing NWPs will be adopted only after the Corps gives notice and allows the public an opportunity to comment on and request a public hearing regarding the proposals. The Corps will give full consideration to all comments received prior to reaching a final decision.

(c) Terms and conditions. An activity is authorized under an NWP only if that activity and the permittee satisfy all of the NWP's terms and conditions. Activities that do not qualify for authorization under an NWP still may be authorized by an individual or regional general permit. The Corps will consider unauthorized any activity requiring Corps authorization if that activity is under construction or completed and does not comply with all of the terms and conditions of an NWP, regional general permit, or an individual permit. The Corps will evaluate unauthorized activities for enforcement action under 33 CFR part 326. The district engineer (DE) may elect to suspend enforcement proceedings if the permittee modifies his project to comply with an NWP or a regional general permit. After considering whether a violation was knowing or intentional, and other indications of the need for a penalty, the DE can elect to terminate an enforcement proceeding with an after-the-fact authorization under an NWP, if all terms and conditions of the NWP have been satisfied, either before or after the activity has been accomplished.

(d) Discretionary authority. District and division engineers have been delegated a discretionary authority to suspend, modify, or revoke authorizations under an NWP. This discretionary authority may be used by district and division engineers only to further condition or restrict the applicability of an NWP for cases where they have concerns for the aquatic environment under the Clean Water Act section 404(b)(1) Guidelines or for any factor of the public interest. Because of the nature of most activities authorized by NWP, district and division engineers will not have to review every such activity to decide whether to exercise discretionary authority. The terms and conditions of certain NWPs require the DE to review the proposed activity before the NWP authorizes its construction. However, the DE has the discretionary authority to review any activity authorized by NWP to determine whether the activity complies with the NWP. If the DE finds that the proposed activity would have more than minimal individual or cumulative net adverse effects on the environment or otherwise may be contrary to the public interest, he shall modify the NWP authorization to reduce or eliminate those adverse effects, or he shall instruct the prospective permittee to apply for a regional general permit or an individual permit. Discretionary authority is also discussed at 33 CFR 330.4(e) and 330.5.

(e) Notifications. (1) In most cases, permittees may proceed with activities authorized by NWPs without notifying the DE. However, the prospective permittee should carefully review the language of the NWP to ascertain whether he must notify the DE prior to commencing the authorized activity. For NWPs requiring advance notification, such notification must be made in writing as early as possible prior to commencing the proposed activity. The permittee may presume that his project qualifies for the NWP unless he is otherwise notified by the DE within a 45-day period. The 45-day period starts on the date of receipt of the notification in the Corps district office and ends 45 calendar days later regardless of weekends or holidays. If the DE notifies the prospective permittee that the notification is incomplete, a new 45-day period will commence upon receipt of the revised notification. The prospective permittee may not proceed with the proposed activity before expiration of the 45-day period unless otherwise notified by the DE. If the DE fails to act within the 45-day period, he must use the procedures of 33 CFR 330.5 in order to modify, suspend, or revoke the NWP authorization.

(2) The DE will review the notification and may add activity-specific conditions to ensure that the activity complies with the terms and conditions of the NWP and that the adverse impacts on the aquatic environment and other aspects of the public interest are individually and cumulatively minimal.

(3) For some NWPs involving discharges into wetlands, the notification must include a wetland delineation. The DE will review the notification and determine if the individual and cumulative adverse environmental effects are more than minimal. If the adverse effects are more than minimal the DE will notify the prospective permittee that an individual permit is required or that the prospective permittee may propose measures to mitigate the loss of special aquatic sites, including wetlands, to reduce the adverse impacts to minimal. The prospective permittee may elect to propose mitigation with the original notification. The DE will consider that proposed mitigation when deciding if the impacts are minimal. The DE shall add activity-specific conditions to ensure that the mitigation will be accomplished. If sufficient mitigation cannot be developed to reduce the adverse environmental effects to the minimal level, the DE will not allow authorization under the NWP and will instruct the prospective permittee on procedures to seek authorization under an individual permit.

(f) Individual Applications. DEs should review all incoming applications for individual permits for possible eligibility under regional general permits or NWPs. If the activity complies with the terms and conditions of one or more NWP, he should verify the authorization and so notify the applicant. If the DE determines that the activity could comply after reasonable project modifications and/or activity-specific conditions, he should notify the applicant of such modifications and conditions. If such modifications and conditions are accepted by the applicant, verbally or in writing, the DE will verify the authorization with the modifications and conditions in accordance with 33 CFR 330.6(a). However, the DE will proceed with processing the application as an individual permit and take the appropriate action within 15 calendar days of receipt, in accordance with 33 CFR 325.2(a)(2), unless the applicant indicates that he will accept the modifications or conditions.

(g) Authority. NWPs can be issued to satisfy the permit requirements of section 10 of the Rivers and Harbors Act of 1899, section 404 of the Clean Water Act, section 103 of the Marine Protection, Research, and Sanctuaries Act, or some combination thereof. The applicable authority will be indicated at the end of each NWP. NWPs and their conditions previously published at 33 CFR 330.5 and 330.6 will remain in effect until they expire or are modified or revoked in accordance with the procedures of this part.

[56 FR 59134, Nov. 22, 1991, as amended at 78 FR 5733, Jan. 28, 2013]
The 20 cases that cite 33 C.F.R. § 330.1 most heavily, weighted by court and treatment. RelevanceNewestTreatment
1
GREENSierra Club v. United States Army Corps of Engineers, 803 F.3d 31 (D.C. Cir. 2015).
cites § 330.1 6×cited by 52 cases
Where it cites § 330.1
“33 C.F.R. §§ 330.1 (e)(2), 330.6(a)(3)(i).”
The case’s holding
Federal agencies are not required to conduct a NEPA analysis of an entire project when their regulatory actions only authorize discrete segments of that project.
Later courts cite it for
“requires federal agencies to take a 'hard look' at their proposed actions' environmental consequences in advance of deciding whether and how to proceed.” · 6 citing courts
2
GREENSierra Club v. U.S. Army Corps of Engineers, 909 F.3d 635 (4th Cir. 2018).
cites § 330.1 4×cited by 30 cases
Where it cites § 330.1
“The Reinstatement primarily cites to 33 C.F.R. §§ 330.1 (d) and 330.1(e)(2) as the relevant authority for the Corps' replacement of Special Condition C, although the Reinstatement does not explain in any depth how the Act authorizes such an interpretation or application of those…”
The case’s holding
A federal agency lacks authority to substitute its own conditions for state-imposed Clean Water Act certification requirements and a state cannot waive such conditions without notice and comment.
Later courts cite it for
“if the statute is ambiguous, courts then 'move to chevron's second step and defer to the agency's interpretation so long as it is based on a permissible construction of the statute.” · 3 citing courts
3
GREENSierra Club v. United States Army Corps of Engineers, 990 F. Supp. 2d 9 (D.D.C. 2013).
cites § 330.1 4×cited by 49 cases
Where it cites § 330.1
“See 33 C.F.R. § 330.1 (b); Proposal to Reissue and Modify Nationwide Permits, 76 Fed.”
The case’s holding
Federal agency actions involving only a small portion of a pipeline do not constitute a major federal action requiring a comprehensive environmental impact statement for the entire project.
Later courts cite it for
“although allowing challenged conduct to persist certainly may be harmful to a plaintiff and the public, harm can also flow from enjoining an activity, and the public may benefit most from permitting it to continue.” · 14 citing courts
4
GREENOhio Valley Env't Coalition v. Hurst, 604 F. Supp. 2d 860 (S.D. W. Va. 2009).
cites § 330.1 5×cited by 18 cases
Where it cites § 330.1
“OVEC’s NWP 21 (2007) Claims Are Not Barred By The Statute of Limitations Finally, the Corps argues that OVEC, by challenging the Corps’ reliance on compensatory mitigation in making its NWP 21 (2007) minimal impacts determination, is actually challenging 33 C.F.R. § 330.1…”
Later courts cite it for
“a court conducting judicial review under the apa does not resolve factual questions, but instead determines whether or not as a matter of law the evidence in the administrative record permitted the agency to make the decision it did.” · 7 citing courts
cites § 330.1 2×cited by 128 cases
Where it cites § 330.1
“See 33 C.F.R. § 330.1 (e)(1) (“In most cases, permittees may proceed with activities authorized by [nationwide general permits] without notifying the [district engineer].”
The case’s holding
The issuance of nationwide permits constitutes final agency action, and purely legal facial challenges to such permits are presumptively ripe for judicial review.
Later courts cite it for
“observed that a purely legal claim in the context of a facial challenge ... is 'presumptively renewable.” · 9 citing courts
6
GREENCrutchfield v. United States Army Corps of Engineers, 214 F. Supp. 2d 593 (E.D. Va. 2002).
cites § 330.1 9×cited by 6 cases
Where it cites § 330.1
“” *641 33 C.F.R. § 330.1 (d) expands on that definition.”
The case’s holding
Corps may switch from individual permitting to nationwide permits without notifying interested parties, since no regulation mandates such notice, so the switch is not arbitrary or capricious.
Later courts cite it for
“no precise regulation mandates that the corps must notify interested parties of a decision to switch from the individual permitting mode to the nwp mode.” · 2 citing courts
7
GREENSierra Club, Inc. v. Bostick, 539 F. App'x 885 (10th Cir. 2013).
cites § 330.1 2×cited by 63 casesunpublished
Where it cites § 330.1
“See 33 C.F.R. § 330.1 (c) (“An activity is authorized under an NWP only if that activity and the permittee satisfy all of the NWP’s terms and conditions.”
The case’s holding
A party seeking a preliminary injunction must prove that all four equitable factors weigh in its favor.
Later courts cite it for
“a party seeking a preliminary injunction must prove that all four of the equitable factors weigh in its favor.” · 9 citing courts
8
GREENSierra Club v. State Water Control Bd., 898 F.3d 383 (4th Cir. 2018).
cites § 330.1 2×cited by 19 cases
Where it cites § 330.1
“2003) (citing 33 C.F.R. § 330.1 (e) ). "In cases where preconstruction notification is required, the Corps will verify the applicability of the [nationwide permit] to the proposed activity.”
Later courts cite it for
“a likelihood of ultimate relief” · 2 citing courts
9
GREENCrutchfield v. Cnty. of Hanover, 325 F.3d 211 (4th Cir. 2003).
cites § 330.1 7×cited by 19 cases
Where it cites § 330.1
“33 C.F.R. § 330.1 (e) (2003). In cases where precon-struction notification is required, the *215 Corps will verify the applicability of the NWP to the proposed activity.”
Later courts cite it for
“requires a resource-intensive review that entails submission of voluminous application materials, extensive site-specific research and documentation, promulgation of public notice, opportunity for public comment, consultation with other federal agencies, and a formal analysis justifying the ultimate decision to issue or refuse the permit.” · 4 citing courts
10
GREENSierra Club, Inc. v. Bostick, 787 F.3d 1043 (10th Cir. 2015).
cites § 330.1 2×subsections: (d)cited by 26 cases
Where it cites § 330.1
“See 33 C.F.R. § 330.1 (d) (2012) (stating that Corps officials may instruct permittees whose projects do not qualify for nationwide permits to "apply for a regional general permit or an individual permit”).”
Later courts cite it for
“the council on environmental quality (ceq) is tasked with interpreting nepa and establishing regulations governing agencies' responsibilities under the statute.” · 2 citing courts
cites § 330.1 2×cited by 67 cases
Where it cites § 330.1
“Consequently, 33 C.F.R. § 330.1 notes that some of its chapter’s nationwide permits require notification to the district engineer prior to commencement of the activity in question.”
The case’s holding
A private plaintiff lacks a cause of action to enjoin nonfederal entities for alleged violations of the National Historic Preservation Act.
Later courts cite it for
“it is implicit in rule 19(a) itself that before a party ... will be joined as a defendant the plaintiff must have a cause of action against it.” · 6 citing courts
12
GREENMohlen v. United States, 74 Fed. Cl. 656 (Fed. Cl. 2006).
cites § 330.1 4×cited by 7 cases
Where it cites § 330.1
“33 C.F.R. § 330.1 (b) (2004). The rules direct that when citizens in a geographic area propose building or maintenance activities that are “substantially similar in nature and cause only minimal individual and cumulative environmental impacts,” the Corps may issue a general…”
Later courts cite it for
“the court decides if the governmental action at issue constituted a taking of that property.” · 2 citing courts
13
GREENCrutchfield v. United States Army Corps of Engineers, 154 F. Supp. 2d 878 (E.D. Va. 2001).
cites § 330.1 3×cited by 9 cases
Where it cites § 330.1
“” 33 C.F.R. § 330.1 (b). At the risk of oversimplification, NWPs are issued to allow conduct of a class of activities that the Corps has studied that, either because of the nature of the activity or the small reach of its impact, have sufficiently minimal impact as to justify…”
Later courts cite it for
“remarkably illogical conclusion” · 3 citing courts
cites § 330.1 1×cited by 17 cases
Where it cites § 330.1
“" 33 C.F.R. § 330.1 (b). Nationwide permits are subject to certain requirements.”
Later courts cite it for
“equitable tolling allows for an extension of the prescribed limitations period 'when the plaintiff, despite all due diligence, is unable to obtain vital information bearing on the existence of his or her claim.” · 2 citing courts
15
GREENPermapost Prods., Inc. v. McHugh, 55 F. Supp. 3d 14 (D.D.C. 2014).
cites § 330.1 2×cited by 10 cases
Where it cites § 330.1
“33 C.F.R. § 330.1 (d). On February 16, 2011, the Corps proposed to re-issue forty-eight existing nationwide permits and two new nationwide permits for the five-year period from 2012 through 2017.”
16
GREENUnited States v. Cumberland Farms of Connecticut, Inc., 647 F. Supp. 1166 (D. Mass. 1986).
cites § 330.1 2×cited by 16 cases
Where it cites § 330.1
“See 33 C.F.R. § 330.1 (1985). Nationwide permits under both the Clean Waters Act and the Rivers and Harbors Act were created administratively by the Corps in a rulemaking in 1977.”
Later courts cite it for
“contextual review of its total activities” · 2 citing courts
cites § 330.1 1×cited by 64 cases
Where it cites § 330.1
“If the district engineer determines that such historic properties may be adversely affected, he will provide the Advisory Council on Historic Preservation an opportunity to comment on the effects on such historic properties or he will consider modification, suspension, or…”
The case’s holding
Federal agencies must comply with historic preservation review requirements for licensed projects if the agency retains authority to mandate changes to mitigate adverse historic impacts.
Later courts cite it for
“a suit is moot only when it can be shown that a court cannot even 'theoretically grant' relief.” · 6 citing courts
18
GREENUtah Council v. United States Army Corp. of Engineers, 187 F. Supp. 2d 1334 (D. Utah 2002).
cites § 330.1 3×cited by 4 cases
Where it cites § 330.1
“” 33 C.F.R. § 330.1 (b). Because the projects at issue here were authorized by the ACE under the NWP program, explanation of the procedures governing NWP is necessary.”
19
GREENOuachita Riverkeeper, Inc. v. Bostick, 938 F. Supp. 2d 32 (D.D.C. 2013).
cites § 330.1 3×cited by 4 cases
Summary
No passage or summary on file for this case yet.
20
GREENNat'l Wildlife Fed'n v. U.S. Army Corps of Engineers, 170 F. Supp. 3d 6 (D.D.C. 2016).
cites § 330.1 1×cited by 9 cases
Where it cites § 330.1
“The general permit at issue in this lawsuit, nationwide permit 13 (“NWP 13”), authorizes bank stabilization activities like those in the Ogeechee River and Savannah River basins. It was issued on February 21, 2012, along with 50 other nationwide general permits.”
Later courts cite it for
“redressability focuses on the requested relief.” · 2 citing courts

Show all 64 citing cases (list view) →

The flag is Syfertize’s treatment of the citing case itself, not of the statute. “Where it cites” is the passage in the opinion; the holding is a summary of the whole case and may concern another point. Annotations are extracted automatically from the opinions in the Syfert caselaw corpus.

Citing cases by year
198620062026

One bar per year. Tallest: 4 cases in 2000. 2026 is a partial year. These are opinions in the Syfert collection, which holds more of some courts’ recent opinions than their older ones, so a rise can reflect what the collection holds and not more litigation.

By court
D.D.C.94th Cir.4Ct. Cl.3Ohio Ct. App.3D. Utah3W.D. Wash.3S.D.W. Va310th Cir.2

The 8 courts with the most citing cases, of 33 courts in all.

By subsection
(c)1 case
United States v. Irizarry, 98 F. Supp. 2d 160 (D.P.R. 2000).
(d)1 case
Sierra Club, Inc. v. Bostick, 787 F.3d 1043 (10th Cir. 2015).“See 33 C.F.R. § 330.1 (d) (2012) (stating that Corps officials may instruct permittees whose projects do not qualify for nationwide permits to "apply for a regional general permit or an individual permit”).”
(e)(1)1 case

Show all 64 citing cases (list view) →

Enactment and amendments

Syfert holds no separate history line for this section. Where this code prints a source or history note, it appears with the text, usually at the end.