33 C.F.R. § 330.2 (2026)
Definitions
Edition and currency
Other sources
Courts have cited this section in 23 opinions since 1986, 1 of them in the last five years.
(a) The definitions found in 33 CFR parts 320-329 are applicable to the terms used in this part.
(b) Nationwide permit refers to a type of general permit which authorizes activities on a nationwide basis unless specifically limited. (Another type of general permit is a “regional permit” which is issued by division or district engineers on a regional basis in accordance with 33 CFR part 325). (See 33 CFR 322.2(f) and 323.2(h) for the definition of a general permit.)
(c) Authorization means that specific activities that qualify for an NWP may proceed, provided that the terms and conditions of the NWP are met. After determining that the activity complies with all applicable terms and conditions, the prospective permittee may assume an authorization under an NWP. This assumption is subject to the DE's authority to determine if an activity complies with the terms and conditions of an NWP. If requested by the permittee in writing, the DE will verify in writing that the permittee's proposed activity complies with the terms and conditions of the NWP. A written verification may contain activity-specific conditions and regional conditions which a permittee must satisfy for the authorization to be valid.
(d) Headwaters means non-tidal rivers, streams, and their lakes and impoundments, including adjacent wetlands, that are part of a surface tributary system to an interstate or navigable water of the United States upstream of the point on the river or stream at which the average annual flow is less than five cubic feet per second. The DE may estimate this point from available data by using the mean annual area precipitation, area drainage basin maps, and the average runoff coefficient, or by similar means. For streams that are dry for long periods of the year, DEs may establish the point where headwaters begin as that point on the stream where a flow of five cubic feet per second is equaled or exceeded 50 percent of the time.
(e) Isolated waters means those non-tidal waters of the United States that are:
(1) Not part of a surface tributary system to interstate or navigable waters of the United States; and
(2) Not adjacent to such tributary waterbodies.
(f) Filled area means the area within jurisdictional waters which is eliminated or covered as a direct result of the discharge (i.e., the area actually covered by the discharged material). It does not include areas excavated nor areas impacted as an indirect effect of the fill.
(g) Discretionary authority means the authority described in §§ 330.1(d) and 330.4(e) which the Chief of Engineers delegates to division or district engineers to modify an NWP authorization by adding conditions, to suspend an NWP authorization, or to revoke an NWP authorization and thus require individual permit authorization.
(h) Terms and conditions. The “terms” of an NWP are the limitations and provisions included in the description of the NWP itself. The “conditions” of NWPs are additional provisions which place restrictions or limitations on all of the NWPs. These are published with the NWPs. Other conditions may be imposed by district or division engineers on a geographic, category-of-activity, or activity-specific basis (See 33 CFR 330.4(e)).
(i) Single and complete project means the total project proposed or accomplished by one owner/developer or partnership or other association of owners/developers. For example, if construction of a residential development affects several different areas of a headwater or isolated water, or several different headwaters or isolated waters, the cumulative total of all filled areas should be the basis for deciding whether or not the project will be covered by an NWP. For linear projects, the “single and complete project” (i.e., single and complete crossing) will apply to each crossing of a separate water of the United States (i.e., single waterbody) at that location; except that for linear projects crossing a single waterbody several times at separate and distant locations, each crossing is considered a single and complete project. However, individual channels in a braided stream or river, or individual arms of a large, irregularly-shaped wetland or lake, etc., are not separate waterbodies.
(j) Special aquatic sites means wetlands, mudflats, vegetated shallows, coral reefs, riffle and pool complexes, sanctuaries, and refuges as defined at 40 CFR 230.40 through 230.45.
- Where it cites § 330.2
- “” 33 C.F.R. § 330.2 (i) (2012). For linear projects like utility lines, the Corps considers each crossing of a waterway to be a “single and complete project” as long as these crossings are “separate and distant.”
- Later courts cite it for
- “the council on environmental quality (ceq) is tasked with interpreting nepa and establishing regulations governing agencies' responsibilities under the statute.” · 2 citing courts
- Where it cites § 330.2
- “" 33 C.F.R. § 330.2 (c) (emphases added). Put differently, "[a]n activity is authorized under an NWP only if that activity and the permittee satisfy all of the NWP's terms and conditions .”
- The case’s holding
- A federal agency lacks authority to substitute its own conditions for state-imposed Clean Water Act certification requirements and a state cannot waive such conditions without notice and comment.
- Later courts cite it for
- “if the statute is ambiguous, courts then 'move to chevron's second step and defer to the agency's interpretation so long as it is based on a permissible construction of the statute.” · 3 citing courts
- Where it cites § 330.2
- “" 33 C.F.R. § 330.2 (i). Nationwide Permit 14 authorizes "[a]ctivities required for the construction, expansion, modification, or improvement of linear transportation projects (e.”
- Later courts cite it for
- “equitable tolling allows for an extension of the prescribed limitations period 'when the plaintiff, despite all due diligence, is unable to obtain vital information bearing on the existence of his or her claim.” · 2 citing courts
- Where it cites § 330.2
- “As defined at 33 C.F.R. § 330.2 (g), “[discretionary authority means the authority described in §§ 330.1(d) and 330.4(e) which the Chief of Engineers delegates to division or district engineers to modify an NWP authorization by adding conditions, to suspend an NWP authorization, or to revoke an NWP authorization and thus require individual permit authorization.””
- The case’s holding
- Corps may switch from individual permitting to nationwide permits without notifying interested parties, since no regulation mandates such notice, so the switch is not arbitrary or capricious.
- Later courts cite it for
- “no precise regulation mandates that the corps must notify interested parties of a decision to switch from the individual permitting mode to the nwp mode.” · 2 citing courts
- Where it cites § 330.2
- “See 33 C.F.R. § 330.2 (1997). Thus, even assuming the federal definition of “isolated wetland” encompasses the Program’s definition, there is no evidence the Wetland had met the relevant criteria at the time of the consistency application.”
- Later courts cite it for
- “the requirements of due process include notice, an opportunity to be heard in a meaningful way, and judicial review.” · 3 citing courts
- Where it cites § 330.2
- “See 33 C.F.R. § 330.2 (c). Under the NWP program, upon receiving a verification request, the ACE simply determines whether the activity complies with the terms and conditions of the NWP.”
- Where it cites § 330.2
- “” 33 C.F.R. § 330.2 (b). They note the regulation contains Nationwide Permit 26, which exempts the “discharge of dredged or fill materials” into wetlands above the headwaters from the individual permit requirement provided the discharger meets certain conditions.”
- The case’s holding
- The unpermitted discharge of fill material into wetlands adjacent to navigable waters constitutes a violation of the Clean Water Act subject to strict liability.
- Later courts cite it for
- “civil contempt is remedial in nature, serving to coerce compliance with a court order or to compensate the other party for losses sustained due to noncompliance.” · 3 citing courts
- Where it cites § 330.2
- “A part of that test requires the Corps to make a reasoned conclusion whether the County and THG constituted “an association of owners/developers” within the meaning of 33 C.F.R. § 330.2 (i). The Corps neither discussed nor decided that crucial aspect of the regulatory…”
- Where it cites § 330.2
- “” 33 C.F.R. § 330.2 (f). For linear projects crossing a single waterbody several times at separate and distant locations, each crossing is considered a single and complete project.”
- Where it cites § 330.2
- “5 (c)(1); 33 C.F.R. § 330.2 (c). Here, the Corps proposed SAJ-86, a regional general permit (“RGP”), upon provisionally determining that the proposed activities satisfied the statutory requirements for issuance of a general permit ( 33 U.”
- Where it cites § 330.2
- “” 33 C.F.R. § 330.2 (e); Reichelt v. U.S. Army Corps of Engineers, 923 F.”
- Later courts cite it for
- “the case law is abundantly clear that a minimal showing of detriment is all that is required to establish an injury in fact.” · 2 citing courts
- Where it cites § 330.2
- “33 C.F.R. § 330.2 (a) (1985). “Structure” and “work” are defined in the Corps regulations.”
- Later courts cite it for
- “contextual review of its total activities” · 2 citing courts
- Where it cites § 330.2
- “” 33 C.F.R. § 330.2 (b). 5 . Appellants argue that the district engineer had "more than ample" reason to think Glimcher’s plan would be of importance to the EPA, the U.”
- Where it cites § 330.2
- “"Headwater wetlands,” 33 C.F.R. §§ 330.2 (b), 330.5(26), are "adjacent waters” and the issue of a nexus to interstate or foreign commerce is irrelevant.”
- Where it cites § 330.2
- “Similarly, when, on May 21, 2002, the Army Corps confirmed the designation of the region in which the site was located as a “Critical Resource Waters” area, the only “change” that occurred was that the project was removed from the coverage of a nationwide general permit for the…”
- Where it cites § 330.2
- “” 33 C.F.R. § 330.2 (f) (2003). The test governing this inquiry is whether the project has “independent utility” — or in other words, whether it “would be constructed absent the construction of other projects in the project area.”
- Later courts cite it for
- “requires a resource-intensive review that entails submission of voluminous application materials, extensive site-specific research and documentation, promulgation of public notice, opportunity for public comment, consultation with other federal agencies, and a formal analysis justifying the ultimate decision to issue or refuse the permit.” · 4 citing courts
- Where it cites § 330.2
- “” 33 C.F.R. § 330.2 (b) (1992). 4 . However, the Donnells were informed that such removal "will occur simultaneously with the construction of the abutter’s pier, ramp, and float.”
- Where it cites § 330.2
- “” 33 C.F.R. § 330.2 (b). The average annual flow on Pacheco Creek in the area of Casa de Fruta is well in excess of that figure.”
- Later courts cite it for
- “is limited to 'maintenance' of certain 'structures,” · 2 citing courts
- Where it cites § 330.2
- “33 C.F.R. § 330.2 (b). “Isolated waters” are non-tidal waters which are not part of a surface tributary system to interstate or navigable waters of the United States.”
- Where it cites § 330.2
- “6 (a)(2); see also 33 C.F.R. § 330.2 (c). The Corps has implicitly interpreted this regulation as allowing the instant denial of RSLC’s application for NWP authorization to be made by persons other than the District Engineer.”
- Later courts cite it for
- “res judicata does not apply to claims that did not exist when the first suit was filed.” · 5 citing courts
Show all 23 citing cases (list view) →
The flag is Syfertize’s treatment of the citing case itself, not of the statute. “Where it cites” is the passage in the opinion; the holding is a summary of the whole case and may concern another point. Annotations are extracted automatically from the opinions in the Syfert caselaw corpus.
One bar per year. Tallest: 3 cases in 1993. 2026 is a partial year. These are opinions in the Syfert collection, which holds more of some courts’ recent opinions than their older ones, so a rise can reflect what the collection holds and not more litigation.
The 8 courts with the most citing cases, of 18 courts in all.
Courts have not cited this section by subsection, so its cases are not split up here. The Leading cases tab lists the cases that cite it most heavily.
Syfert holds no separate history line for this section. Where this code prints a source or history note, it appears with the text, usually at the end.
Edition shown: eCFR text as of Sept. 29, 2026. Syfert holds no earlier or later version of this section.