40 C.F.R. § 122.45 (2026)
Calculating NPDES permit conditions (applicable to State NPDES programs, see § 123.25)
Edition and currency
Other sources
Courts have cited this section in 19 opinions since 1980, 1 of them in the last five years.
(a) Outfalls and discharge points. All permit effluent limitations, standards and prohibitions shall be established for each outfall or discharge point of the permitted facility, except as otherwise provided under § 122.44(k) (BMPs where limitations are infeasible) and paragraph (i) of this section (limitations on internal waste streams).
(b) Production-based limitations. (1) In the case of POTWs, permit effluent limitations, standards, or prohibitions shall be calculated based on design flow.
(2)(i) Except in the case of POTWs or as provided in paragraph (b)(2)(ii) of this section, calculation of any permit limitations, standards, or prohibitions which are based on production (or other measure of operation) shall be based not upon the designed production capacity but rather upon a reasonable measure of actual production of the facility. For new sources or new dischargers, actual production shall be estimated using projected production. The time period of the measure of production shall correspond to the time period of the calculated permit limitations; for example, monthly production shall be used to calculate average monthly discharge limitations.
(ii)(A)(1) The Director may include a condition establishing alternate permit limitations, standards, or prohibitions based upon anticipated increased (not to exceed maximum production capability) or decreased production levels.
(2) For the automotive manufacturing industry only, the Regional Administrator shall, and the State Director may establish a condition under paragraph (b)(2)(ii)(A)(1) of this section if the applicant satisfactorily demonstrates to the Director at the time the application is submitted that its actual production, as indicated in paragraph (b)(2)(i) of this section, is substantially below maximum production capability and that there is a reasonable potential for an increase above actual production during the duration of the permit.
(B) If the Director establishes permit conditions under paragraph (b)(2)(ii)(A) of this section:
(1) The permit shall require the permittee to notify the Director at least two business days prior to a month in which the permittee expects to operate at a level higher than the lowest production level identified in the permit. The notice shall specify the anticipated level and the period during which the permittee expects to operate at the alternate level. If the notice covers more than one month, the notice shall specify the reasons for the anticipated production level increase. New notice of discharge at alternate levels is required to cover a period or production level not covered by prior notice or, if during two consecutive months otherwise covered by a notice, the production level at the permitted facility does not in fact meet the higher level designated in the notice.
(2) The permittee shall comply with the limitations, standards, or prohibitions that correspond to the lowest level of production specified in the permit, unless the permittee has notified the Director under paragraph (b)(2)(ii)(B)(1) of this section, in which case the permittee shall comply with the lower of the actual level of production during each month or the level specified in the notice.
(3) The permittee shall submit with the DMR the level of production that actually occurred during each month and the limitations, standards, or prohibitions applicable to that level of production.
(c) Metals. All permit effluent limitations, standards, or prohibitions for a metal shall be expressed in terms of “total recoverable metal” as defined in 40 CFR part 136 unless:
(1) An applicable effluent standard or limitation has been promulgated under the CWA and specifies the limitation for the metal in the dissolved or valent or total form; or
(2) In establishing permit limitations on a case-by-case basis under § 125.3, it is necessary to express the limitation on the metal in the dissolved or valent or total form to carry out the provisions of the CWA; or
(3) All approved analytical methods for the metal inherently measure only its dissolved form (e.g., hexavalent chromium).
(d) Continuous discharges. For continuous discharges all permit effluent limitations, standards, and prohibitions, including those necessary to achieve water quality standards, shall unless impracticable be stated as:
(1) Maximum daily and average monthly discharge limitations for all dischargers other than publicly owned treatment works; and
(2) Average weekly and average monthly discharge limitations for POTWs.
(e) Non-continuous discharges. Discharges which are not continuous, as defined in § 122.2, shall be particularly described and limited, considering the following factors, as appropriate:
(1) Frequency (for example, a batch discharge shall not occur more than once every 3 weeks);
(2) Total mass (for example, not to exceed 100 kilograms of zinc and 200 kilograms of chromium per batch discharge);
(3) Maximum rate of discharge of pollutants during the discharge (for example, not to exceed 2 kilograms of zinc per minute); and
(4) Prohibition or limitation of specified pollutants by mass, concentration, or other appropriate measure (for example, shall not contain at any time more than 0.1 mg/1 zinc or more than 250 grams (
(f) Mass limitations. (1) All pollutants limited in permits shall have limitations, standards or prohibitions expressed in terms of mass except:
(i) For pH, temperature, radiation, or other pollutants which cannot appropriately be expressed by mass;
(ii) When applicable standards and limitations are expressed in terms of other units of measurement; or
(iii) If in establishing permit limitations on a case-by-case basis under § 125.3, limitations expressed in terms of mass are infeasible because the mass of the pollutant discharged cannot be related to a measure of operation (for example, discharges of TSS from certain mining operations), and permit conditions ensure that dilution will not be used as a substitute for treatment.
(2) Pollutants limited in terms of mass additionally may be limited in terms of other units of measurement, and the permit shall require the permittee to comply with both limitations.
(g) Pollutants in intake water. (1) Upon request of the discharger, technology-based effluent limitations or standards shall be adjusted to reflect credit for pollutants in the discharger's intake water if:
(i) The applicable effluent limitations and standards contained in 40 CFR subchapter N specifically provide that they shall be applied on a net basis; or
(ii) The discharger demonstrates that the control system it proposes or uses to meet applicable technology-based limitations and standards would, if properly installed and operated, meet the limitations and standards in the absence of pollutants in the intake waters.
(2) Credit for generic pollutants such as biochemical oxygen demand (BOD) or total suspended solids (TSS) should not be granted unless the permittee demonstrates that the constituents of the generic measure in the effluent are substantially similar to the constituents of the generic measure in the intake water or unless appropriate additional limits are placed on process water pollutants either at the outfall or elsewhere.
(3) Credit shall be granted only to the extent necessary to meet the applicable limitation or standard, up to a maximum value equal to the influent value. Additional monitoring may be necessary to determine eligibility for credits and compliance with permit limits.
(4) Credit shall be granted only if the discharger demonstrates that the intake water is drawn from the same body of water into which the discharge is made. The Director may waive this requirement if he finds that no environmental degradation will result.
(5) This section does not apply to the discharge of raw water clarifier sludge generated from the treatment of intake water.
(h) Internal waste streams. (1) When permit effluent limitations or standards imposed at the point of discharge are impractical or infeasible, effluent limitations or standards for discharges of pollutants may be imposed on internal waste streams before mixing with other waste streams or cooling water streams. In those instances, the monitoring required by § 122.48 shall also be applied to the internal waste streams.
(2) Limits on internal waste streams will be imposed only when the fact sheet under § 124.56 sets forth the exceptional circumstances which make such limitations necessary, such as when the final discharge point is inaccessible (for example, under 10 meters of water), the wastes at the point of discharge are so diluted as to make monitoring impracticable, or the interferences among pollutants at the point of discharge would make detection or analysis impracticable.
(i) Disposal of pollutants into wells, into POTWs or by land application. Permit limitations and standards shall be calculated as provided in § 122.50.
- Where it cites § 122.45
- “For example, 40 C.F.R. § 122.45 (g)(4) regulates intake credits.”
- The case’s holding
- An agency's reasonable interpretation of an ambiguous statute it administers is entitled to deference under the Chevron framework.
- Later courts cite it for
- “we evaluate challenges to an agency's interpretation of a statute that it administers within the two-step chevron deference framework.” · 4 citing courts
- Where it cites § 122.45
- “5 The EPA has interpreted this regime as “preclud[ing] [it] from imposing any particular technology on a discharger.”
- The case’s holding
- Agency actions are binding and subject to judicial review if they restrict the discretion of regulated entities or are applied in a manner that is controlling in practice.
- Later courts cite it for
- “need not establish that all of its members would have standing to sue individually so long as it can show that 'any one of them' would have standing.” · 8 citing courts
- Where it cites § 122.45
- “For example, 40 CFR § 122.45 (g)(4) (2003) allows an industrial water user to obtain "intake credit" for pollutants present in water that it withdraws from navigable waters.”
- The case’s holding
- A ditch or depression in a field that collects and channelizes pollutants constitutes a point source under the Clean Water Act.
- Later courts cite it for
- “generally speaking, the npdes requires dischargers to obtain permits that place limits on the type and quantity of pollutants that can be released into the nation's waters.” · 24 citing courts
- Where it cites § 122.45
- “44(d)(1) (2005), 5 the DNR must prepare a reasonable potential analysis to determine whether the Fort James' Broadway Mill's increase in phosphorous discharge will cause or contribute to a violation of water quality standards; 6 (2) pursuant to 40 C.F.R. § 122.45 (d) and (f),…”
- The case’s holding
- A state agency need not hold a public hearing on a petition challenging a state-issued discharge permit as violating federal Clean Water Act requirements, because federal remedies lie with the federal agency.
- Later courts cite it for
- “while we are not bound by an agency's conclusions of law, this court has articulated three levels of deference that we may accord an agency's statutory interpretation and application: great weight deference, due weight deference, and no deference.” · 2 citing courts
- Where it cites § 122.45
- “However, CLF has waived this argument by failing to present it either to the EPA Region during the permitting process or during the initial round of briefing before the EAR 40 C.”
- The case’s holding
- The EPA may not indefinitely delay issuing a Clean Water Act NPDES permit until better science is developed, and numerical effluent limits within a reasonable zone supported by the record are permissible.
- Later courts cite it for
- “raise all reasonably ascertainable issues and submit all reasonably available arguments supporting their position by the close of the public comment period ....” · 2 citing courts
- Where it cites § 122.45
- “( 40 C.F.R. § 122.45 (h) (2002).) 4 Discharge monitoring reports are admissible in court as admissions of the discharger and thus play a critical evidentiary role in enforcement actions for violation of permit terms.”
- Later courts cite it for
- “ensure the reasonable protection of beneficial uses of waters of the state and the prevention of nuisance.” · 2 citing courts
- Where it cites § 122.45
- “Citing 40 C.F.R. § 122.45 (g), which provides that, "[u]pon request of the discharger, technology-based effluent limitations or standards shall be adjusted to reflect credit for pollutants in the discharger's intake water [emphasis added]," Upper Potomac River Commission asserts…”
- Summary
- No passage or summary on file for this case yet.
- Where it cites § 122.45
- “Moreover, EPA regulations provide that when pollutants are limited in terms of mass as well as terms other than mass, “the permit shall require the permittee to comply with both limitations.”
- The case’s holding
- Each express permit limitation violated may be treated as a separate violation for penalty purposes, so separate exceedances of weight and concentration limits can each constitute distinct violations.
- Later courts cite it for
- “the fact that the failure to solve the problem is manifested from time to time in different parameters should not preclude a citizen's suit di rected at the unresolved source of trouble.” · 2 citing courts
- Where it cites § 122.45
- “32,908 (June 7, 1979); 40 C.F.R. § 122.45 (d) (1985). . As discussed above, the daily maximum limitations in Gwaltney’s NPDES permit are roughly *315 twice as high as the monthly average limitations.”
- The case’s holding
- Citizen suits under the Clean Water Act may seek civil penalties for past violations as well as the abatement of ongoing violations.
- Later courts cite it for
- “can be read to comprehend unlawful conduct that occurred only prior to the filing of a lawsuit as well as unlawful conduct that continues into the present.” · 2 citing courts
- Where it cites § 122.45
- “However, the court believes the EPA should be allowed considerable discretion is attempting to rectify pollution problems. The court is hesitant to hold that a permit-tee may be subject to suit for violating its permit limitations when the EPA has set another limitation by…”
- Where it cites § 122.45
- “57 and 40 C.F.R. § 122.45 (f)(2) 7 *139 provided that an NPDES permit may contain concentration limits in addition to mass-based limits, Shenango maintained that the limits were not “necessary” and offered the expert testimony of Gary Am-endola, P.”
- Later courts cite it for
- “offering authority to support its prior argument.” · 2 citing courts
- Where it cites § 122.45
- “40 C.F.R. § 122.45 . This regulation was adopted in response to a federal district court ruling that the EPA could not totally exclude storm water runoff systems from the NPDES permit program.”
- Where it cites § 122.45
- “40 C.F.R. § 122.45 (h) (1990). The regulation provides for effluent limitations on internal waste streams when it would be “impractical or infeasible” to monitor the effluent at the point of discharge into the waters of the United States.”
- Where it cites § 122.45
- “” 40 C.F.R. § 122.45 (g). Its supporting reasoning seems internally contradictory.”
- Later courts cite it for
- “does not empower the agency to regulate point sources themselves; rather, epa's jurisdiction under the operative statute is limited to regulating the discharge of pollutants.” · 4 citing courts
- Later courts cite it for
- “forever the right to do so, even though that action might eventually result in the imposition of severe civil or criminal penalties.” · 2 citing courts
- Where it cites § 122.45
- “40 C.F.R. section 122.45, subdivision (d)(2) provides that for publicly owned treatment works like Camarillo, effluent limitations shall, unless “impracticable,” be stated as “[a]verage weekly and average monthly discharge limitations .”
- Where it cites § 122.45
- “For example, 40 C.F.R. § 122.45 (g)(4) regulates intake credits.”
- Where it cites § 122.45
- “See 40 C.F.R. § 122.45 (b)(1) ("POTW[] [publicly owned treatment work] effluent limitations .”
The flag is Syfertize’s treatment of the citing case itself, not of the statute. “Where it cites” is the passage in the opinion; the holding is a summary of the whole case and may concern another point. Annotations are extracted automatically from the opinions in the Syfert caselaw corpus.
One bar per year. Tallest: 2 cases in 1988. These are opinions in the Syfert collection, which holds more of some courts’ recent opinions than their older ones, so a rise can reflect what the collection holds and not more litigation.
The 8 courts with the most citing cases, of 16 courts in all.
Courts have not cited this section by subsection, so its cases are not split up here. The Leading cases tab lists the cases that cite it most heavily.
Syfert holds no separate history line for this section. Where this code prints a source or history note, it appears with the text, usually at the end.
Edition shown: eCFR text as of Sept. 29, 2026. Syfert holds no earlier or later version of this section.