C.F.R.Title 40Chapter I—Environmental Protection AgencySubchapter C—Air ProgramsPart 60—Standards of Performance for New Stationary SourcesSubpart A—General Provisions

40 C.F.R. § 60.2 (2026)

Definitions

Edition and currency
eCFR text as of Sept. 29, 2026. The text is the edition Syfert holds; for a past event, check the version in force on that date.
Other sources
CURRENTeCFR text as of Sept. 29, 2026 cited 1973–2022 25citing cases
At a glance

Courts have cited this section in 25 opinions since 1973, 1 of them in the last five years. The most litigated part is subsection (h) (2 cases).

The terms used in this part are defined in the Act or in this section as follows:

Act means the Clean Air Act (42 U.S.C. 7401 et seq.)

Administrator means the Administrator of the Environmental Protection Agency or his authorized representative.

Affected facility means, with reference to a stationary source, any apparatus to which a standard is applicable.

Alternative method means any method of sampling and analyzing for an air pollutant which is not a reference or equivalent method but which has been demonstrated to the Administrator's satisfaction to, in specific cases, produce results adequate for his determination of compliance.

Approved permit program means a State permit program approved by the Administrator as meeting the requirements of part 70 of this chapter or a Federal permit program established in this chapter pursuant to Title V of the Act (42 U.S.C. 7661).

Capital expenditure means an expenditure for a physical or operational change to an existing facility which exceeds the product of the applicable “annual asset guideline repair allowance percentage” specified in the latest edition of Internal Revenue Service (IRS) Publication 534 and the existing facility's basis, as defined by section 1012 of the Internal Revenue Code. However, the total expenditure for a physical or operational change to an existing facility must not be reduced by any “excluded additions” as defined in IRS Publication 534, as would be done for tax purposes.

Clean coal technology demonstration project means a project using funds appropriated under the heading ‘Department of Energy-Clean Coal Technology’, up to a total amount of $2,500,000,000 for commercial demonstrations of clean coal technology, or similar projects funded through appropriations for the Environmental Protection Agency.

Commenced means, with respect to the definition of new source in section 111(a)(2) of the Act, that an owner or operator has undertaken a continuous program of construction or modification or that an owner or operator has entered into a contractual obligation to undertake and complete, within a reasonable time, a continuous program of construction or modification.

Construction means fabrication, erection, or installation of an affected facility.

Continuous monitoring system means the total equipment, required under the emission monitoring sections in applicable subparts, used to sample and condition (if applicable), to analyze, and to provide a permanent record of emissions or process parameters.

Electric utility steam generating unit means any steam electric generating unit that is constructed for the purpose of supplying more than one-third of its potential electric output capacity and more than 25 MW electrical output to any utility power distribution system for sale. Any steam supplied to a steam distribution system for the purpose of providing steam to a steam-electric generator that would produce electrical energy for sale is also considered in determining the electrical energy output capacity of the affected facility.

Equivalent method means any method of sampling and analyzing for an air pollutant which has been demonstrated to the Administrator's satisfaction to have a consistent and quantitatively known relationship to the reference method, under specified conditions.

Excess Emissions and Monitoring Systems Performance Report is a report that must be submitted periodically by a source in order to provide data on its compliance with stated emission limits and operating parameters, and on the performance of its monitoring systems.

Existing facility means, with reference to a stationary source, any apparatus of the type for which a standard is promulgated in this part, and the construction or modification of which was commenced before the date of proposal of that standard; or any apparatus which could be altered in such a way as to be of that type.

Force majeure means, for purposes of § 60.8, an event that will be or has been caused by circumstances beyond the control of the affected facility, its contractors, or any entity controlled by the affected facility that prevents the owner or operator from complying with the regulatory requirement to conduct performance tests within the specified timeframe despite the affected facility's best efforts to fulfill the obligation. Examples of such events are acts of nature, acts of war or terrorism, or equipment failure or safety hazard beyond the control of the affected facility.

Isokinetic sampling means sampling in which the linear velocity of the gas entering the sampling nozzle is equal to that of the undisturbed gas stream at the sample point.

Issuance of a part 70 permit will occur, if the State is the permitting authority, in accordance with the requirements of part 70 of this chapter and the applicable, approved State permit program. When the EPA is the permitting authority, issuance of a Title V permit occurs immediately after the EPA takes final action on the final permit.

Malfunction means any sudden, infrequent, and not reasonably preventable failure of air pollution control equipment, process equipment, or a process to operate in a normal or usual manner. Failures that are caused in part by poor maintenance or careless operation are not malfunctions.

Modification means any physical change in, or change in the method of operation of, an existing facility which increases the amount of any air pollutant (to which a standard applies) emitted into the atmosphere by that facility or which results in the emission of any air pollutant (to which a standard applies) into the atmosphere not previously emitted.

Monitoring device means the total equipment, required under the monitoring of operations sections in applicable subparts, used to measure and record (if applicable) process parameters.

Nitrogen oxides means all oxides of nitrogen except nitrous oxide, as measured by test methods set forth in this part.

One-hour period means any 60-minute period commencing on the hour.

Opacity means the degree to which emissions reduce the transmission of light and obscure the view of an object in the background.

Owner or operator means any person who owns, leases, operates, controls, or supervises an affected facility or a stationary source of which an affected facility is a part.

Part 70 permit means any permit issued, renewed, or revised pursuant to part 70 of this chapter.

Particulate matter means any finely divided solid or liquid material, other than uncombined water, as measured by the reference methods specified under each applicable subpart, or an equivalent or alternative method.

Permit program means a comprehensive State operating permit system established pursuant to title V of the Act (42 U.S.C. 7661) and regulations codified in part 70 of this chapter and applicable State regulations, or a comprehensive Federal operating permit system established pursuant to title V of the Act and regulations codified in this chapter.

Permitting authority means:

(1) The State air pollution control agency, local agency, other State agency, or other agency authorized by the Administrator to carry out a permit program under part 70 of this chapter; or

(2) The Administrator, in the case of EPA-implemented permit programs under title V of the Act (42 U.S.C. 7661).

Proportional sampling means sampling at a rate that produces a constant ratio of sampling rate to stack gas flow rate.

Reactivation of a very clean coal-fired electric utility steam generating unit means any physical change or change in the method of operation associated with the commencement of commercial operations by a coal-fired utility unit after a period of discontinued operation where the unit:

(1) Has not been in operation for the two-year period prior to the enactment of the Clean Air Act Amendments of 1990, and the emissions from such unit continue to be carried in the permitting authority's emissions inventory at the time of enactment;

(2) Was equipped prior to shut-down with a continuous system of emissions control that achieves a removal efficiency for sulfur dioxide of no less than 85 percent and a removal efficiency for particulates of no less than 98 percent;

(3) Is equipped with low-NOX burners prior to the time of commencement of operations following reactivation; and

(4) Is otherwise in compliance with the requirements of the Clean Air Act.

Reference method means any method of sampling and analyzing for an air pollutant as specified in the applicable subpart.

Repowering means replacement of an existing coal-fired boiler with one of the following clean coal technologies: atmospheric or pressurized fluidized bed combustion, integrated gasification combined cycle, magnetohydrodynamics, direct and indirect coal-fired turbines, integrated gasification fuel cells, or as determined by the Administrator, in consultation with the Secretary of Energy, a derivative of one or more of these technologies, and any other technology capable of controlling multiple combustion emissions simultaneously with improved boiler or generation efficiency and with significantly greater waste reduction relative to the performance of technology in widespread commercial use as of November 15, 1990. Repowering shall also include any oil and/or gas-fired unit which has been awarded clean coal technology demonstration funding as of January 1, 1991, by the Department of Energy.

Run means the net period of time during which an emission sample is collected. Unless otherwise specified, a run may be either intermittent or continuous within the limits of good engineering practice.

Shutdown means the cessation of operation of an affected facility for any purpose.

Six-minute period means any one of the 10 equal parts of a one-hour period.

Standard means a standard of performance proposed or promulgated under this part.

Standard conditions means a temperature of 293 K (68F) and a pressure of 101.3 kilopascals (29.92 in Hg).

Startup means the setting in operation of an affected facility for any purpose.

State means all non-Federal authorities, including local agencies, interstate associations, and State-wide programs, that have delegated authority to implement: (1) The provisions of this part; and/or (2) the permit program established under part 70 of this chapter. The term State shall have its conventional meaning where clear from the context.

Stationary source means any building, structure, facility, or installation which emits or may emit any air pollutant.

Title V permit means any permit issued, renewed, or revised pursuant to Federal or State regulations established to implement title V of the Act (42 U.S.C. 7661). A title V permit issued by a State permitting authority is called a part 70 permit in this part.

Volatile Organic Compound means any organic compound which participates in atmospheric photochemical reactions; or which is measured by a reference method, an equivalent method, an alternative method, or which is determined by procedures specified under any subpart.

[44 FR 55173, Sept. 25, 1979, as amended at 45 FR 5617, Jan. 23, 1980; 45 FR 85415, Dec. 24, 1980; 54 FR 6662, Feb. 14, 1989; 55 FR 51382, Dec. 13, 1990; 57 FR 32338, July 21, 1992; 59 FR 12427, Mar. 16, 1994; 72 FR 27442, May 16, 2007]
The 20 cases that cite 40 C.F.R. § 60.2 most heavily, weighted by court and treatment. RelevanceNewestTreatment
1
GREENUnited States v. City of Painesville, 644 F.2d 1186 (6th Cir. 1981).
cites § 60.2 7×cited by 24 cases
Summary
No passage or summary on file for this case yet.
cites § 60.2 8×cited by 15 cases
Where it cites § 60.2
“40 C.F.R. § 60.2 (g). The EPA interpreted its regulations to require either a contract or actual construction on the boiler unit itself, and therefore Sierra Pacific had not “commenced construction.”
3
GREENUnited States v. Duke Energy Corp., 278 F. Supp. 2d 619 (M.D.N.C. 2003).
cites § 60.2 4×subsections: (h)cited by 22 cases
Where it cites § 60.2
“” 40 C.F.R. § 60.2 (h)(1) (1971) (Duke Energy Ex.”
The case’s holding
A project constitutes a modification under the prevention of significant deterioration program only if it increases the hourly rate of emissions rather than merely increasing utilization.
Later courts cite it for
“increase in the hours of operation or in the production rate” · 1 citing court
4
GREENUtil. Air Regulatory Grp. v. EPA, 573 U.S. 302 (2014).
cites § 60.2 1×cited by 253 cases
Where it cites § 60.2
“24877 (1971), codified, as amended, 40 CFR §60.2 ; 40 Fed. Reg. 58419 (1975), codified, as amended, 40 CFR §60.”
The case’s holding
An agency may not rewrite unambiguous statutory terms or numerical thresholds to accommodate its own regulatory goals or to address practical administrative difficulties.
Later courts cite it for
“an agency may not rewrite clear statutory terms to suit its own sense of how the statute should operate.” · 19 citing courts
5
REDNew York v. U.S. Env't Prot. Agency, 413 F.3d 3 (D.C. Cir. 2005).
cites § 60.2 1×cited by 146 cases
Vacated by Environmental Defense v. Duke Energy Corporation (2007): the U.S. Supreme Court's own opinion in this case.
Where it cites § 60.2
“at 58,418 (previously codified at 40 C.F.R. § 60.2 (h) (1976)). But 40 C.F.”
The case’s holding
An agency's interpretation of an ambiguous statutory term is permissible if it represents a reasonable accommodation of conflicting policies committed to the agency's care.
Later courts cite it for
“congress could reasonably conclude, for example, that tradeoffs between pollutants are difficult to measure, and thus any significant increase in emissions of any pollutant should be subject to nsr.” · 3 citing courts
cites § 60.2 2×subsections: (j)cited by 66 cases
Where it cites § 60.2
“” 40 C.F.R. § 60.2 (j) (1979). See discussion infra, text preceding note 100.”
The case’s holding
An agency bears the burden of explaining how a performance standard is achievable by accounting for variables such as fuel type and feed materials.
Later courts cite it for
“burden of promulgating and explaining a non-arbitrary, non-capricious rule.” · 6 citing courts
7
GREENUnited States v. City of Painesville, 431 F. Supp. 496 (N.D. Ohio 1977).
cites § 60.2 6×cited by 7 cases
Where it cites § 60.2
“15704, so that if, as of August 17, 1971, “construction” or “modification” 4 of Municipal Electric had been “commenced,” Unit 5 would not be a new source and therefore sulphur dioxide emission standards promulgated under 42 U.”
Later courts cite it for
“if the only work made fruitless by the need to meet antipollution standards is in the design or planning of a new source, then operators are required to modify those designs or operating plans to meet new stationary source emission standards,” · 2 citing courts
8
REDUnited States v. Duke Energy Corp., 411 F.3d 539 (4th Cir. 2005).
cites § 60.2 2×cited by 19 cases
Vacated by Environmental Defense v. Duke Energy Corporation (2007): the U.S. Supreme Court's own opinion in this case.
The case’s holding
When Congress mandates that two statutory provisions define a term identically, the agency cannot interpret that term differently under each provision; the PSD and NSPS 'modification' definitions must be read consistently.
Later courts cite it for
“the language and various interpretations of the psd regulations . . . are largely irrelevant to the proper analysis of this case,” · 1 citing court
9
cites § 60.2 1×cited by 61 cases
Where it cites § 60.2
“The changes [TVA] made to Colbert Unit 5 in 1983 that are discussed above caused an increase in the maximum hourly emissions rate achievable by the unit and therefore constituted a “modification” as that term is de *1329 fined at 40 C.F.R. §§ 60.2 and 60.14(a). Accordingly,…”
The case’s holding
Violations of preconstruction permitting requirements occur at the time of construction and do not constitute continuing violations that toll the statute of limitations.
Later courts cite it for
“under the continuing violations doctrine, the statute of limitations is tolled for a claim that otherwise would be time-barred where the violation giving rise to the claim continues to occur within the limitations period.” · 8 citing courts
10
GREENASARCO Inc. v. Env't Prot. Agency, 578 F.2d 319 (D.C. Cir. 1978).
cites § 60.2 9×cited by 3 cases
Where it cites § 60.2
“24877 (1971), codified at 40 C.F.R. §§ 60.2 (d) & (h) (1975). EPA acknowledges in its brief that it originally “defined the term new source as ‘an affected facility’ which .”
The case’s holding
A plant consisting of a combination of facilities does not constitute a single stationary source under the Clean Air Act.
Later courts cite it for
“the bubble concept in the challenged regulations would undercut (the nsps program) by allowing operators to avoid installing the best pollution control technology on an altered facility as long as the emissions from the entire plant do not increase.” · 2 citing courts
cites § 60.2 1×cited by 25 cases
Where it cites § 60.2
“See 40 C.F.R. § 60.2 (c) (1975) (new stationary sources); id.”
Later courts cite it for
“objective evidentiary standard(s) (which) would have to be met by the citizen who brings an action under the (citizen suit provision).” · 3 citing courts
cites § 60.2 1×cited by 15 cases
Where it cites § 60.2
“” 40 C.F.R. § 60.2 (1980). Opacity is measured in percentages, with 0 percent indicating no visible emissions and 100 percent indicating emissions that completely obscure the background.”
13
GREENSierra Club v. Pub. Serv. Co. of Colorado, 894 F. Supp. 1455 (D. Colo. 1995).
cites § 60.2 1×cited by 13 cases
Where it cites § 60.2
“” 40 C.F.R. § 60.2 . PSC submits quarterly reports to the CDH which document at six minute intervals the opacity readings from the CEMs.”
14
GREENEssex Chem. Corp. v. Ruckelshaus, 486 F.2d 427 (D.C. Cir. 1973).
cites § 60.2 1×cited by 35 cases
Where it cites § 60.2
“” 40 C.F.R. § 60.2 (j). A 10 percent opacity standard was established for the portland cement stationary sources of pollution and the Port-land Cement court, impressed both by the arbitrariness of the test — it is essentially a subjective test on the part of trained inspectors…”
The case’s holding
An agency must demonstrate that its emission standards result from reasoned decisionmaking and are achievable through the established system.
Later courts cite it for
“(i)t is the system which must be adequately demonstrated and the standard which must be achievable.” · 2 citing courts
15
GREENUnited States v. Alabama Power Co., 372 F. Supp. 2d 1283 (N.D. Ala. 2005).
cites § 60.2 1×subsections: (h)cited by 6 cases
Where it cites § 60.2
“, to new capacity to *1311 emit pollution, while “automatically allowing] increases in operating hours as intended by one of the existing exemptions under 40 CFR 60.2(h).” 39 Fed. Reg. 36,946 , 36,947 (Oct.”
16
GREENAnderson v. Farmland Indus., Inc., 70 F. Supp. 2d 1218 (D. Kan. 1999).
cites § 60.2 1×cited by 11 cases
Where it cites § 60.2
“On a renewed motion, made at the close of discovery, the Court would anticipate a much more fully developed exposition of the facts underlying Farmland’s contention that excess emissions were caused by malfunctions and specifically correlating them to the definition of…”
17
GREENPotomac Elec. Power Co. v. Env't Prot. Agency, 650 F.2d 509 (4th Cir. 1981).
cites § 60.2 9×cited by 2 cases
Where it cites § 60.2
“The reasons given for the EPA’s preliminary determination were that construction of Unit # 4 had been neither continuous nor of reasonable length, as required by 40 C.F.R. § 60.2 (i). PEPCO supplied the requested information and urged that the EPA make its decision “just as…”
cites § 60.2 1×cited by 5 cases
Where it cites § 60.2
“40 C.F.R. § 60.2 defines stationary source as “any building, structure, facility, or installation which emits or may emit any air pollutant and which contains any one or combination of the following: (1) Affected facilities.”
Later courts cite it for
“unless such control or prohibition is identical with the federally promulgated standards.” · 2 citing courts
cites § 60.2 5×cited by 1 case
Where it cites § 60.2
“40 CFR § 60.2 (1980). The Council makes two arguments as to the application of the 1978 NSPS regulations to Colstrip Units Nos.”
Later courts cite it for
“no manifest congressional intent” · 2 citing courts
cites § 60.2 1×cited by 4 cases
Where it cites § 60.2
“emitted into the atmosphere____” 40 C.F.R. § 60.2 . See also 40 C.F.R. § 60.14 (a) (any change “which results in an increase in the emission rate to the atmosphere ” constitutes a modification (emphasis added)).”

Show all 25 citing cases (list view) →

The flag is Syfertize’s treatment of the citing case itself, not of the statute. “Where it cites” is the passage in the opinion; the holding is a summary of the whole case and may concern another point. Annotations are extracted automatically from the opinions in the Syfert caselaw corpus.

Citing cases by year
197319972022

One bar per year. Tallest: 5 cases in 1981. These are opinions in the Syfert collection, which holds more of some courts’ recent opinions than their older ones, so a rise can reflect what the collection holds and not more litigation.

By court
D.C. Cir.74th Cir.26th Cir.29th Cir.2D. Kan.2N.D. Ala.111th Cir.12d Cir.1

The 8 courts with the most citing cases, of 15 courts in all.

By subsection
(h)2 cases
United States v. Duke Energy Corp., 278 F. Supp. 2d 619 (M.D.N.C. 2003).“” 40 C.F.R. § 60.2 (h)(1) (1971) (Duke Energy Ex.”
United States v. Alabama Power Co., 372 F. Supp. 2d 1283 (N.D. Ala. 2005).“, to new capacity to *1311 emit pollution, while “automatically allowing] increases in operating hours as intended by one of the existing exemptions under 40 CFR 60.2(h).” 39 Fed. Reg. 36,946 , 36,947 (Oct.”
(j)1 case
Nat'l Lime Ass'n v. Env't Prot. Agency & Douglas M. Costle, 627 F.2d 416 (D.C. Cir. 1980).“” 40 C.F.R. § 60.2 (j) (1979). See discussion infra, text preceding note 100.”

Show all 25 citing cases (list view) →

Enactment and amendments

Syfert holds no separate history line for this section. Where this code prints a source or history note, it appears with the text, usually at the end.