49.108-2 Prime contractor's rights and obligations.

Edition and currency
eCFR text as of Sept. 29, 2026. The text is the edition Syfert holds; for a past event, check the version in force on that date.
Other sources
CURRENTeCFR text as of Sept. 29, 2026 cited 1999–2008 2citing cases
At a glance

Courts have cited this section in 2 opinions since 1999.

(a) Termination for convenience clauses provide that after receipt of a termination notice the prime contractor shall, unless directed otherwise by the TCO, terminate all subcontracts to the extent that they relate to the performance of prime work terminated. Therefore, prime contractors should include a termination clause in their subcontracts for their own protection. Suggestions regarding use of subcontract termination clauses are in subpart 49.5.

(b) The failure of a prime contractor to include an appropriate termination clause in any subcontract, or to exercise the clause rights, shall not—

(1) Affect the Government's right to require the termination of the subcontract; or

(2) Increase the obligation of the Government beyond what it would have been if the subcontract had contained an appropriate clause.

(c) In any case, the reasonableness of the prime contractor's settlement with the subcontractor should normally be measured by the aggregate amount due under paragraph (f) of the subcontract termination clause suggested in 49.502(e). The TCO shall allow reimbursement in excess of that amount only in unusual cases and then only to the extent that the terms of the subcontract did not unreasonably increase the rights of the subcontractor.

The 2 cases that cite 48 C.F.R. § 49.108-2 most heavily, weighted by court and treatment. RelevanceNewestTreatment
cites § 49.108-2 2×cited by 39 cases
Where it cites § 49.108-2
“See 48 C.F.R. § 49.108-2 (b)(2) (“The failure of a prime contractor to include an appropriate termination clause in any subcontract, or to exercise the clause rights, shall not .”
The case’s holding
A district court possesses discretion in awarding prejudgment interest, though such awards must comply with stipulations regarding the accrual of damages.
Later courts cite it for
“an award of prejudgment interest is within the district court's discretion.” · 4 citing courts
2
GREENMorrison Knudsen Corp. v. Fireman's Fund Ins., 175 F.3d 1221 (10th Cir. 1999).
cites § 49.108-2 1×cited by 104 cases
Where it cites § 49.108-2
“See 48 C.F.R. § 49.108-2 (c) (measuring reasonableness of prime’s settlement with sub by amount due to sub under standard termination-for-convenience clause, which includes profit); see also id.”
The case’s holding
An appellant's failure to provide a necessary transcript to demonstrate prejudice from an instructional error requires affirmance of the judgment below.
Later courts cite it for
“our concern is to ensure that our review does not leave us with substantial doubt whether the instructions, considered as a whole, properly guided the jury in its deliberations.” · 7 citing courts

The flag is Syfertize’s treatment of the citing case itself, not of the statute. “Where it cites” is the passage in the opinion; the holding is a summary of the whole case and may concern another point. Annotations are extracted automatically from the opinions in the Syfert caselaw corpus.

By subsection

Courts have not cited this section by subsection, so its cases are not split up here. The Leading cases tab lists the cases that cite it most heavily.

Enactment and amendments

Syfert holds no separate history line for this section. Where this code prints a source or history note, it appears with the text, usually at the end.