“Amend a complaint to add a cause of action for a constructional defect” defined
Courts have cited this section in 5 opinions since 2015. The most litigated part is subsection (2) (5 cases).
1. Add to the pleadings a defective component that is not otherwise included in the pleadings and for which a notice was not previously given; or
2. Amend the pleadings in such a manner that the practical effect is the addition of a constructional defect that is not otherwise included in the pleadings.
Ê The term does not include amending a complaint to plead a different cause for a constructional defect which is included in the same action.
(Added to NRS by 2003, 2034)
The flag is Syfertize’s treatment of the citing case itself, not of the statute. “Where it cites” is the passage in the opinion; the holding is a summary of the whole case and may concern another point. Annotations are extracted automatically from the opinions in the Syfert caselaw corpus.
Syfert holds no separate history line for this section. Where this code prints a source or history note, it appears with the text, usually at the end.
Edition shown: laws through the 2025 session (checked Sept. 2026). Syfert holds no earlier or later version of this section.