42 U.S.C. § 7419 (2026)
Primary nonferrous smelter orders
Edition and currency
Other sources
Courts have cited this section in 12 opinions since 1980.
At any time during which an order under this section applies, the Administrator may enter upon a public hearing respecting the availability of technology. Any order under this section shall be terminated if the Administrator determines on the record, after notice and public hearing, that the conditions upon which the order was based no longer exist. If the owner or operator of the smelter to which the order is issued demonstrates that prompt termination of such order would result in undue hardship, the termination shall become effective at the earliest practicable date on which such undue hardship would not result, but in no event later than the date required under subsection (c).
Section 7413(d) of this title, referred to in subsec. (a)(2)(A), was amended generally by Pub. L. 101–549, title VII, § 701,
A prior section 119 of act July 14, 1955, ch. 360, title I, as added
1977—Subsec. (a)(3). Pub. L. 95–190, § 14(a)(25), added par. (3).
Subsec. (d)(3). Pub. L. 95–190, § 14(a)(26), substituted “7621” for “7619”.
Subsec. (e). Pub. L. 95–190, § 14(a)(27), substituted “an order under this section” for “such order”.
Section effective
All rules, regulations, orders, determinations, contracts, certifications, authorizations, delegations, or other actions duly issued, made, or taken by or pursuant to act
- Where it cites § 7419
- “II); and § 119, 42 U. S. C. § 7419 (1976 ed., Supp. II). EPA maintains that these additions make no substantive changes because the "any other final action" phrase already included actions under these sections, and under the Court's interpretation of that phrase this would…”
- The case’s holding
- The phrase any other final action in the Clean Air Act includes any final action of the Administrator as understood under the Administrative Procedure Act.
- Later courts cite it for
- “it would be a strange canon of statutory construction that would require congress to state in committee reports or elsewhere in its deliberations that which is obvious on the face of a statute.” · 16 citing courts
- Where it cites § 7419
- “42 U.S.C. § 7419 (d)(2) (requirement to use continuous emission reduction technology can be waived “upon a showing by the owner or operator of the smelter that such requirement would be so costly as to necessitate permanent or prolonged temporary cessation of operations of the…”
- Later courts cite it for
- “the apa requires courts to consider agency action in conformity with the agency's statutory grant of power, and agency action is unlawful if it is 'in excess of statutory jurisdiction, authority, or limitations, or short of statutory right.” · 2 citing courts
- Where it cites § 7419
- “712 , 42 U.S.C. § 7419 (Supp. I 1977). Moreover, with respect to the nondeterioration program, the actual emissions from tall stacks of major operating facilities on which construction commenced prior to January 6, 1975, are grandfathered into the baseline.”
- The case’s holding
- Courts should be reluctant to interpret statutory terms in a manner that mandates pointless expenditures of effort.
- Later courts cite it for
- “inherent in most statutory schemes, to overlook circumstances that in context may fairly be considered de minimis.” · 10 citing courts
- Where it cites § 7419
- “Section 119, 42 U.S.C. § 7419 . That section provides that the deadline for compliance with limitations necessary to meet the air quality standards for sulphur dioxide may, under certain conditions, be extended for up to 10 years.”
- The case’s holding
- The Administrator must set ambient air quality standards to protect public health and welfare without being required to consider economic or technological feasibility.
- Later courts cite it for
- “that the evidence in the record may also support other conclusions, even those that are inconsistent with the administrator's, does not prevent us from concluding that her decisions were rational and supported by the record.” · 9 citing courts
- Where it cites § 7419
- “] (relating to nonattainment)!,] section 119 [42 USCS § 7419] (relating to primary nonferrous smelter orders), any condition or requirement under an applicable implementation plan relating to transportation control measures, air quality maintenance plans, vehicle inspection and…”
- Later courts cite it for
- “it is inappropriate to consider arguments raised for the first time in a reply brief.” · 9 citing courts
- Where it cites § 7419
- “A petition for review of the Administrator’s action in approving or promulgating any implementation plan under section 110 or section 111(d) [42 USCS § 7410 or 7411(d)], any order under section Ilia) [42 USCS § 741 l(j)], under section 112(c) [42 USCS § 7412(c)], under section…”
- Later courts cite it for
- “once a plan is adopted by the state and it withstands any subsequent procedural challenge , then 307(b)(1) provides that invalidation may occur only in the federal appellate courts.” · 3 citing courts
- Where it cites § 7419
- “under section 112(c) [42 USCS § 7412(c)], under section 113(d) [42 USCS § 7413(d) ], under section 119 [42 USCS § 7419], or under section 120 [42 USCS § 7420], or his action under section 119(c)(2)(A), (B), or (C) (as in effect before the date of enactment of the Clean Air Act…”
- Summary
- No passage or summary on file for this case yet.
- Where it cites § 7419
- “42 U.S.C. § 7419 (d)(2) (requirement to use continuous emission reduction technology can be waived “upon a showing by the owner or operator of the smelter that such requirement would be so costly as to necessitate permanent' or prolonged temporary cessation of operations of the…”
- Where it cites § 7419
- “To avoid being assessed a penalty for their noncompliance, the smelters must obtain a nonferrous smelter order under § 119 of the Act, 42 U.S.C. § 7419 . A prerequisite to such an order is that the smelter adopt a combination of emission limitations and dispersion techniques…”
- Later courts cite it for
- “dropped its proposed conditional approval in favor of combining full, unconditional approval of the implementation plan with a requirement that arizona promulgate fugitive emission regulations.” · 1 citing court
- Where it cites § 7419
- “(Asarco) and Magma Copper Company (Magma) seek review of the final regulations of the Environmental Protection Agency (EPA) promulgated under Section 119 of the Clean Air Act (Act) as amended 42 U.S.C. § 7419 , and governing issuance of primary nonferrous smelter orders (NSO’s).”
- Where it cites § 7419
- “42 U.S.C. § 7419 (b)(3) (1982). Petitioners gave no indication that such adjustments would not be forthcoming.”
- Later courts cite it for
- “with engineering and work practices and only very limited use of respirators,” · 2 citing courts
The flag is Syfertize’s treatment of the citing case itself, not of the statute. “Where it cites” is the passage in the opinion; the holding is a summary of the whole case and may concern another point. Annotations are extracted automatically from the opinions in the Syfert caselaw corpus.
One bar per year. Tallest: 3 cases in 1980. These are opinions in the Syfert collection, which holds more of some courts’ recent opinions than their older ones, so a rise can reflect what the collection holds and not more litigation.
Courts have not cited this section by subsection, so its cases are not split up here. The Leading cases tab lists the cases that cite it most heavily.
Amendment years (notes): 1977