Notes of Decisions
Cited in 7 cases, 1983–2018 · leading case: In re Petition of Stowe Cady Hill Solar, LLC, 182 A.3d 53 (Vt. 2018).
Sort: Relevance Newest Treatment
In re Petition of Stowe Cady Hill Solar, LLC, 182 A.3d 53 (Vt. 2018). · cites it 2× “30 V.S.A. § 231(a) (stating Commission has authority to grant CPG); id .”
In Re Proposed Sale of Vermont Yankee Nuclear Power Station, 2003 VT 53 (Vt. 2003). · cites it 4× “§ 248, and that ENVY is eligible for a CPG under 30 V.S.A. § 231. We affirm. *370 ¶ 2. Vermont Yankee Nuclear Power Station began operating in 1972 after receiving a CPG from the Public Service Board (PSB) in 1966 under 30 V.”
Entergy Nuclear Vermont Yankee, LLC v. United States, 95 Fed. Cl. 160 (Fed. Cl. 2010). · cites it 2× “See 30 V.S.A. § 231(a); Thayer, Tr. 91-92. The Public Service Board is a three-member panel with quasi-judicial authority that supervises “the rates, quality of service, and overall financial management of Vermont’s public utilities.”
In Re Vermont Elec. Power Producers, Inc., 683 A.2d 716 (Vt. 1996). · cites it 2× “§ 231, which establishes the requirements for issuance and revocation of a certificate of public good to operate a business over which the PSB has jurisdiction; and that the PSB did not issue the 1987 designation order following public notice and public hearings conducted to…”
In re Petition of LK Holdings, LLC, 201 A.3d 373 (Vt. 2018). “Finally, applicant maintains that the Commission erred in dismissing the application because the new net-metering program had not yet been adopted through formal rulemaking.”
Petition of Telesystems, Corp., 469 A.2d 1169 (Vt. 1983). “As required by 30 V.S.A. § 231, hearings were convened in Shelburne, where all three parties participated, and in Vergennes, from which Green Mountain was absent.”
Petition of Quechee Serv. Co., Inc., 690 A.2d 354 (Vt. 1996). “Moreover, § 126 predates 30 V.S.A. § 231, which establishes the CPG requirement.”
— Vt. Stat. Ann. tit. 30, § 231(a) — 5 cases
In re Petition of Stowe Cady Hill Solar, LLC, 182 A.3d 53 (Vt. 2018). “30 V.S.A. § 231(a) (stating Commission has authority to grant CPG); id .”
Entergy Nuclear Vermont Yankee, LLC v. United States, 95 Fed. Cl. 160 (Fed. Cl. 2010). “See 30 V.S.A. § 231(a); Thayer, Tr. 91-92. The Public Service Board is a three-member panel with quasi-judicial authority that supervises “the rates, quality of service, and overall financial management of Vermont’s public utilities.”
In Re Proposed Sale of Vermont Yankee Nuclear Power Station, 2003 VT 53 (Vt. 2003). “§ 248, and that ENVY is eligible for a CPG under 30 V.S.A. § 231. We affirm. *370 ¶ 2. Vermont Yankee Nuclear Power Station began operating in 1972 after receiving a CPG from the Public Service Board (PSB) in 1966 under 30 V.”
In re Petition of LK Holdings, LLC, 201 A.3d 373 (Vt. 2018). “Finally, applicant maintains that the Commission erred in dismissing the application because the new net-metering program had not yet been adopted through formal rulemaking.”
In Re Vermont Elec. Power Producers, Inc., 683 A.2d 716 (Vt. 1996). “§ 231, which establishes the requirements for issuance and revocation of a certificate of public good to operate a business over which the PSB has jurisdiction; and that the PSB did not issue the 1987 designation order following public notice and public hearings conducted to…”