Nebraska Revised Statutes homeSearch Nebraska
Neb. Rev. Stat.Chapter 52

Neb. Rev. Stat. § 52-125 (2026)

Act, how cited

Edition and currency
text as last checked Oct. 2026 (this copy records no edition or section history). The text is the edition Syfert holds; for a past event, check the version in force on that date.
Other sources
CURRENTtext as last checked Oct. 2026 (this copy records no edition or section history) cited 1984–2026 27citing cases
At a glance

Courts have cited this section in 27 opinions since 1984, 3 of them in the last five years.

Sections 52-125 to 52-159 shall be known and may be cited as the Nebraska Construction Lien Act.

The 20 cases that cite Neb. Rev. Stat. § 52-125 most heavily, weighted by court and treatment. RelevanceNewestTreatment
1
GREENTilt-Up Concrete, Inc. v. Star City/Fed., Inc., 621 N.W.2d 502 (Neb. 2001).
cites § 52-125 3×cited by 105 cases
Where it cites § 52-125
“*68 Effect of Nebraska Construction Lien Act Tilt-Up’s construction lien was brought under the Nebraska Construction Lien Act (NCLA), Neb. Rev. Stat. §§ 52-125 through 52-159 (Reissue 1998).”
The case’s holding
The Nebraska Construction Lien Act does not preclude a concurrent breach of contract action, nor does a supersedeas bond toll the statute of limitations.
Later courts cite it for
“the amount unpaid for the services and materials furnished.” · 2 citing courts
2
GREENLincoln Lumber Co. v. Lancaster, 618 N.W.2d 676 (Neb. 2000).
cites § 52-125 3×cited by 24 cases
Where it cites § 52-125
“This is an appeal from a foreclosure action on construction liens filed under the Nebraska Construction Lien Act, Neb. Rev. Stat. §§ 52-125 through 52-159 (Reissue 1998).”
3
GREENChicago Lumber Co. v. Sch. Dist. No. 71, 417 N.W.2d 757 (Neb. 1988).
cites § 52-125 2×cited by 56 cases
Where it cites § 52-125
“The Nebraska Construction Lien Act, Neb. Rev. Stat. §§ 52-125 et seq. (Reissue 1984), does not apply to real estate owned by a governmental agency or political subdivision, and, hence, did not apply to the district’s real estate which was the subject of the renovation project.”
The case’s holding
Substantial compliance with statutory notice requirements provides sufficient notice under the Political Subdivisions Tort Claims Act if the lack of compliance causes no prejudice to the political subdivision.
Later courts cite it for
“therefore, substantial compliance with the statutory provisions pertaining to a claim's content supplies the requisite and sufficient notice to a political subdivision in accordance with 13-905, when the lack of compliance has caused no prejudice to the political subdivision ....” · 4 citing courts
4
GREENEcho Grp. v. Tradesmen Internat., 980 N.W.2d 869 (Neb. 2022).
cites § 52-125 2×cited by 8 cases
Where it cites § 52-125
“Stat. §§ 52-125 to 52-159 (Reissue 2021). - 733 - Nebraska Supreme Court Advance Sheets 312 Nebraska Reports ECHO GROUP V.”
The case’s holding
Under the Nebraska Construction Lien Act, substituting a lien release surety bond for a construction lien does not cap recovery, and prejudgment interest may be awarded in lien foreclosure actions.
Later courts cite it for
“a formal legal document entailing rights and obligations, such as a contract, deed, legislative act, etc.; any document formally drawn up so as to have legal effect.” · 2 citing courts
5
GREENTilt-Up Concrete, Inc. v. Star City/Fed., Inc., 582 N.W.2d 604 (Neb. 1998).
cites § 52-125 2×cited by 42 cases
Where it cites § 52-125
“Such a rule is not consistent with the purpose of the Nebraska Construction Lien Act (NCLA), see Neb. Rev. Stat. §§ 52-125 through 52-159 (Reissue 1993).”
The case’s holding
A person who furnishes services or materials pursuant to a real estate improvement contract has a construction lien.
Later courts cite it for
“who furnishes services or materials pursuant to a real estate improvement contract has a construction lien,” · 2 citing courts
6
GREENFranksen v. Crossroads Jt. Venture, 515 N.W.2d 794 (Neb. 1994).
cites § 52-125 2×cited by 38 cases
Where it cites § 52-125
“A person who furnishes services or materials pursuant to a real estate improvement contract has a construction lien, to the extent provided in the act, to secure the payment of his or her contract price.”
The case’s holding
A person placed on inquiry regarding an agent's authority with reasonable means of inquiry is charged with knowledge of the facts that such inquiry would reveal.
Later courts cite it for
“one who is placed on inquiry as to an agent's or employee's authority, and who has reasonable means of making inquiry, occupies the same position in law as if he had actual knowledge of the employee's lack of authority, because he is charged with knowledge of the facts which the inquiry would have developed.” · 2 citing courts
7
GREENBlue Tee Corp. v. CDI Contractors, Inc., 529 N.W.2d 16 (Neb. 1995).
cites § 52-125 2×cited by 35 cases
Where it cites § 52-125
“CDI claimed that Blue Tee was not entitled to protection under the Nebraska Construction Lien Act, Neb. Rev. Stat. § 52-125 et seq. (Reissue 1993).”
The case’s holding
A fabricator that custom-manufactures unique building materials to a prime contractor's specifications, performing substantial labor, is a subcontractor, so its supplier may claim a construction lien.
8
GREENSorenson v. Dager, 601 N.W.2d 564 (Neb. Ct. App. 1999).
cites § 52-125 2×cited by 31 cases
Where it cites § 52-125
“BACKGROUND On April 9, 1996, Sorenson filed a petition for foreclosure of a construction lien under the Nebraska Construction Lien Act, Neb. Rev. Stat. §§ 52-125 to 52-159 (Reissue 1998).”
9
GREENOmaha Constr. Indus. Pension Plan v. Child.'s Hosp., 642 N.W.2d 849 (Neb. Ct. App. 2002).
cites § 52-125 3×cited by 6 cases
Where it cites § 52-125
“The Nebraska Construction Lien Act, Neb. Rev. Stat. §§ 52-125 through 52-159 (Reissue 1998), is an almost verbatim version of article 5 of the Uniform Simplification of Land Transfers Act (Uniform Act).”
10
GREENPayless Bldg. Ctr., Inc. v. Wilmoth, 581 N.W.2d 420 (Neb. 1998).
cites § 52-125 2×cited by 22 cases
Where it cites § 52-125
“The district court dismissed the action, concluding that being titled in the names of protected parties under the Nebraska Construction Lien Act, Neb. Rev. Stat. § 52-125 et seq. (Reissue 1993), the property was exempt from foreclosure.”
11
GREENPreston Refrigeration v. Omaha Cold Storage, 742 N.W.2d 782 (Neb. Ct. App. 2007).
cites § 52-125 3×cited by 5 cases
Where it cites § 52-125
“From this authority and reasoning, Cold Storage argues that a construction lien foreclosure is a statutory action under Neb.Rev.Stat. § 52-125 et seq. (Reissue 2004) and that thus, a common law action for breach of contract cannot be combined therewith.”
Later courts cite it for
“the unpaid cost of materials and labor actually expended,” · 2 citing courts
12
GREENBorrenpohl v. DaBeers Props., LLC, 755 N.W.2d 39 (Neb. 2008).
cites § 52-125 2×cited by 8 cases
Where it cites § 52-125
“Also on October 19, 2005, DaBeers executed a notice of commencement in accordance with the Nebraska Construction Lien Act (NCLA), Neb.Rev.Stat. § 52-125 et seq. (Reissue 2004).”
13
cites § 52-125 2×cited by 8 cases
Where it cites § 52-125
“81 had been filed against garnishees’ real estate; that garnishees were protected party contracting owners within the meaning of the Nebraska Construction Lien Act, Neb. Rev. Stat. §§ 52-125 to 52-159 (Reissue 1984); and that garnishees hold the $9,600 for the benefit of the…”
14
GREENHulinsky v. Parriott, 441 N.W.2d 883 (Neb. 1989).
cites § 52-125 2×cited by 6 cases
Where it cites § 52-125
“Under the Nebraska Construction Lien Act, Neb. Rev. Stat. §§ 52-125 to 52-159 (Reissue 1988), adopted in 1981, a person who furnishes services or materials pursuant to a real estate construction improvement contract has a lien to secure the payment of his contract price.”
15
GREENIn re WorldCom, Inc., 362 B.R. 96 (Bankr. S.D.N.Y. 2007).
cites § 52-125 1×cited by 8 cases
Where it cites § 52-125
“On or about October 29, 2001, Waldinger filed a claim of lien (the “Lien”) on the Omaha Property pursuant to the Nebraska Construction Lien Act, Neb. Rev. Stat § 52-125, et seq (the “Nebraska Statute”).”
Later courts cite it for
“an act to maintain or continue perfection of a lien” · 2 citing courts
16
GREENTuttle & Assocs., Inc. v. Gendler, 467 N.W.2d 881 (Neb. 1991).
cites § 52-125 2×cited by 5 cases
Where it cites § 52-125
“The Nebraska Construction Lien Act, Neb. Rev. Stat. §§ 52-125 et seq. (Reissue 1988), under which Tuttle’s cause of action is premised, provides for the attachment and enforceability of a lien against real estate in favor of a person furnishing services or materials under a real…”
17
GREENIn re Worldcom, Inc., 382 B.R. 610 (Bankr. S.D.N.Y. 2008).
cites § 52-125 1×cited by 6 cases
Where it cites § 52-125
“) Waldinger filed a lien (the “Lien”) on the Omaha property with the Register of Deeds in Nebraska on or about October 29, 2001 pursuant to the Nebraska Construction Lien Act, Neb. Rev. Stat § 52-125, et seq. The Lien was in the amount of $463,862 for the cost of the…”
Later courts cite it for
“article 10.01 of the plan stated that 'all property of the estates of the debtors shall vest in the reorganized debtors free and clear of all claims, liens . . . .' that section encompasses the data center, the property subject to the lien.” · 2 citing courts
18
GREENQuality Equip. Co. v. Transamerica Ins., 502 N.W.2d 488 (Neb. 1993).
cites § 52-125 2×cited by 3 cases
Where it cites § 52-125
“creates a presumption that they were used in the course of construction or were incorporated into the improvement.” However, we are examining quite a different statute, § 52-118, which by its unambiguous language governs a surety bond for a public highway contractor.”
19
GREENTaylor v. Taylor, 764 N.W.2d 101 (Neb. 2009).
cites § 52-125 2×cited by 1 case
Where it cites § 52-125
“[5] When an attorney fee is authorized, the fee is left to the trial court's discretion, and we will not disturb its ruling on appeal absent an abuse of discretion.”
20
GREENNore Elec. v. S & H Holdings, 3 N.W.3d 895 (Neb. 2024).
cites § 52-125 5×cited by 0 cases
Where it cites § 52-125
“§§ 52-125 to 52-159 (Reissue 2021), the real estate subject to construction liens is ultimately determined by the contracting owner’s contract for the improvement of the real estate.”

Show all 27 citing cases (list view) →

The flag is Syfertize’s treatment of the citing case itself, not of the statute. “Where it cites” is the passage in the opinion; the holding is a summary of the whole case and may concern another point. Annotations are extracted automatically from the opinions in the Syfert caselaw corpus.

Citing cases by year
198420052026

One bar per year. Tallest: 4 cases in 2000. 2026 is a partial year. These are opinions in the Syfert collection, which holds more of some courts’ recent opinions than their older ones, so a rise can reflect what the collection holds and not more litigation.

By court
Neb.18Neb. Ct. App.4Bankr. D. Neb.3Bankr. S.D.N.Y.2
By subsection

Courts have not cited this section by subsection, so its cases are not split up here. The Leading cases tab lists the cases that cite it most heavily.

Show all 27 citing cases (list view) →

Enactment and amendments

Syfert holds no separate history line for this section. Where this code prints a source or history note, it appears with the text, usually at the end.