Nebraska Revised Statutes homeSearch Nebraska
Neb. Rev. Stat.Chapter 52

Neb. Rev. Stat. § 52-126 (2026)

Sections, purpose

Edition and currency
text as last checked Oct. 2026 (this copy records no edition or section history). The text is the edition Syfert holds; for a past event, check the version in force on that date.
Other sources
CURRENTtext as last checked Oct. 2026 (this copy records no edition or section history) cited 1988–2024 7citing cases
At a glance

Courts have cited this section in 7 opinions since 1988, 1 of them in the last five years.

Sections 52-125 to 52-159 creates, and provides for the attachment and enforceability of, a lien against real estate in favor of a person furnishing services or materials under a real estate improvement contract. Except as provided in sections 52-125 to 52-159, no nonconsensual lien arises against real estate by reason of improvements made thereon.

The 7 cases that cite Neb. Rev. Stat. § 52-126 most heavily, weighted by court and treatment. RelevanceNewestTreatment
1
GREENTilt-Up Concrete, Inc. v. Star City/Fed., Inc., 582 N.W.2d 604 (Neb. 1998).
cites § 52-126 1×cited by 42 cases
Where it cites § 52-126
“First, according to § 52-126, the purpose behind the NCLA is to “create .”
The case’s holding
A person who furnishes services or materials pursuant to a real estate improvement contract has a construction lien.
Later courts cite it for
“who furnishes services or materials pursuant to a real estate improvement contract has a construction lien,” · 2 citing courts
2
GREENPayless Bldg. Ctr., Inc. v. Wilmoth, 581 N.W.2d 420 (Neb. 1998).
cites § 52-126 1×cited by 22 cases
Where it cites § 52-126
“§§ 52-126, 52-131, 52-133, 52-134, and 52-135.”
cites § 52-126 2×cited by 6 cases
Where it cites § 52-126
“§ 52-134 (l)(b)(iv) (Reissue 1993). The amount of a lien arising from the supplying of tools, appliances, or machinery is limited as follows: (a) If they are rented, the lien is for the reasonable rental value for the period of actual use and any reasonable periods of nonuse…”
cites § 52-126 1×cited by 8 cases
Where it cites § 52-126
“§ 52-126. The provisions of § 52-136 make it clear that a prime contractor is not entitled to payment from the owner until the liens of the subcontractors are satisfied.”
5
GREENHulinsky v. Parriott, 441 N.W.2d 883 (Neb. 1989).
cites § 52-126 1×cited by 6 cases
Where it cites § 52-126
“The act further provides that if no price is agreed upon by the contracting parties, the contract price means the reasonable value of all services and materials covered.”
6
GREENTuttle & Assocs., Inc. v. Gendler, 467 N.W.2d 881 (Neb. 1991).
cites § 52-126 1×cited by 5 cases
Where it cites § 52-126
“§ 52-126. A real estate improvement *831 contract includes an agreement to perform services such as the preparation of plans, surveys, and engineering plans for any change in the physical condition of the land whether or not used incident to producing a change in physical…”
7
GREENNore Elec. v. S & H Holdings, 3 N.W.3d 895 (Neb. 2024).
cites § 52-126 1×cited by 0 cases
Where it cites § 52-126
“In this manner, the NCLA did not change the fact that any nonprotected party purchasing property within the time a contractor is allowed to perfect the lien under the act takes title subject to any future construction lien.”

The flag is Syfertize’s treatment of the citing case itself, not of the statute. “Where it cites” is the passage in the opinion; the holding is a summary of the whole case and may concern another point. Annotations are extracted automatically from the opinions in the Syfert caselaw corpus.

Citing cases by year
198820062024

One bar per year. Tallest: 2 cases in 1998. These are opinions in the Syfert collection, which holds more of some courts’ recent opinions than their older ones, so a rise can reflect what the collection holds and not more litigation.

By subsection

Courts have not cited this section by subsection, so its cases are not split up here. The Leading cases tab lists the cases that cite it most heavily.

Enactment and amendments

Syfert holds no separate history line for this section. Where this code prints a source or history note, it appears with the text, usually at the end.

Versions

Edition shown: text as last checked Oct. 2026 (this copy records no edition or section history). Syfert holds no earlier or later version of this section.