 Declaration of policy.

Edition and currency
laws through the 2026 session (checked Sept. 2026). The text is the edition Syfert holds; for a past event, check the version in force on that date.
Coverage note: this corpus holds the consolidated Pa.C.S. titles only. Unconsolidated P.S. statutes (UTPCPL 73 P.S. § 201-1, Liquor Code, wage payment laws) are not included; a miss here does not mean the statute does not exist. Check palegis.us.
Other sources
CURRENTlaws through the 2026 session (checked Sept. 2026) cited 1998–2025 30citing cases
At a glance

Courts have cited this section in 30 opinions since 1998, 2 of them in the last five years. The most litigated part is subsection (16) (10 cases).

§ 2802.  Declaration of policy.

The General Assembly finds and declares as follows:

(1)  Over the past 20 years, the Federal Government and State government have introduced competition in several industries that previously had been regulated as natural monopolies.

(2)  Many state governments are implementing or studying policies that would create a competitive market for the generation of electricity.

(3)  Because of advances in electric generation technology and Federal initiatives to encourage greater competition in the wholesale electric market, it is now in the public interest to permit retail customers to obtain direct access to a competitive generation market as long as safe and affordable transmission and distribution service is available at levels of reliability that are currently enjoyed by the citizens and businesses of this Commonwealth.

(4)  Rates for electricity in this Commonwealth are on average higher than the national average, and significant differences exist among the rates of Pennsylvania electric utilities.

(5)  Competitive market forces are more effective than economic regulation in controlling the cost of generating electricity.

(6)  The cost of electricity is an important factor in decisions made by businesses concerning locating, expanding and retaining facilities in this Commonwealth.

(7)  This Commonwealth must begin the transition from regulation to greater competition in the electricity generation market to benefit all classes of customers and to protect this Commonwealth's ability to compete in the national and international marketplace for industry and jobs.

(8)  In moving toward greater competition in the electricity generation market, the Commonwealth must resolve certain transitional issues in a manner that is fair to customers, electric utilities, investors, the employees of electric utilities, local communities, nonutility generators of electricity and other affected parties.

(9)  Electric service is essential to the health and well-being of residents, to public safety and to orderly economic development, and electric service should be available to all customers on reasonable terms and conditions.

(10)  The Commonwealth must, at a minimum, continue the protections, policies and services that now assist customers who are low-income to afford electric service.

(11)  In order to ensure the safety and reliability of the electric system, ensure the continued provision of high-quality customer service and avoid economic dislocation, utilities shall consider the experience and expertise of their work force in moving towards competition.

(12)  The purpose of this chapter is to modify existing legislation and regulations and to establish standards and procedures in order to create direct access by retail customers to the competitive market for the generation of electricity while maintaining the safety and reliability of the electric system for all parties. Reliable electric service is of the utmost importance to the health, safety and welfare of the citizens of the Commonwealth. Electric industry restructuring should ensure the reliability of the interconnected electric system by maintaining the efficiency of the transmission and distribution system.

(13)  Under current law and regulation there exists some competition in the wholesale market for the generation of electricity, but the generation, transmission, distribution and retail sale of electricity is provided generally by public utilities under bundled rates regulated by the commission. The procedures established under this chapter provide for a fair and orderly transition from the current regulated structure to a structure under which retail customers will have direct access to a competitive market for the generation and sale or purchase of electricity.

(14)  This chapter requires electric utilities to unbundle their rates and services and to provide open access over their transmission and distribution systems to allow competitive suppliers to generate and sell electricity directly to consumers in this Commonwealth. The generation of electricity will no longer be regulated as a public utility function except as otherwise provided for in this chapter. Electric generation suppliers will be required to obtain licenses, demonstrate financial responsibility and comply with such other requirements concerning service as the commission deems necessary for the protection of the public.

(15)  In establishing the standards for the transition to and creation of a competitive electric market, heretofore, public utilities generally have had an obligation to serve customers within their defined service territories; consistent with that obligation, have undertaken long-term investments in generation, transmission and distribution facilities in order to meet the needs of their customers; and have entered into long-term power supply agreements as required by Federal law. In many instances, these investments and agreements have created costs which may not be recoverable in a competitive market. The commission is empowered under this chapter to determine the level of transition or stranded costs for each electric utility and to provide a mechanism, the competitive transition charge, for recovery of an appropriate amount of such costs in accordance with the standards established in this chapter.

(16)  It is in the public interest for the transmission and distribution of electricity to continue to be regulated as a natural monopoly subject to the jurisdiction and active supervision of the commission. Electric distribution companies should continue to be the provider of last resort in order to ensure the availability of universal electric service in this Commonwealth unless another provider of last resort is approved by the commission.

(17)  There are certain public purpose costs, including programs for low-income assistance, energy conservation and others, which have been implemented and supported by public utilities' bundled rates. The public purpose is to be promoted by continuing universal service and energy conservation policies, protections and services, and full recovery of such costs is to be permitted through a nonbypassable rate mechanism.

(18)  There are certain changes to a utility which will create transition costs to accomplish the move to a competitive market. These changes may entail the closure of facilities or reduction in employee levels. If such actions are to be undertaken, the utility must fully inform the commission of the impact of such decisions on local communities and on social services and of any tax implications of the actions. The utility is expected to discuss the transition to competition with its employees or their certified representatives and may provide severance, retraining, early retirement and outplacement services. Such transition costs may be recoverable under the competitive transition charge in section 2808 (relating to competitive transition charge).

(19)  All participants in the restructured electric industry are encouraged to coordinate their plans and transactions through an independent system operator or its functional equivalent.

(20)  Since continuing and ensuring the reliability of electric service depends on adequate generation and on conscientious inspection and maintenance of transmission and distribution systems, the independent system operator or its functional equivalent should set, and the commission shall set through regulations, inspection, maintenance, repair and replacement standards and enforce those standards.

(21)  Under Federal and State clean air laws and regulations, electricity generators located in states to the west and south of this Commonwealth are not subject to requirements as stringent as those which apply to generators and other "persons" as defined in section 3 of the act of January 8, 1960 (1959 P.L.2119, No.787), known as the Air Pollution Control Act, operating in this Commonwealth and that different regions within this Commonwealth are subject to varying air emission requirements. Under some scenarios, competition among electricity generators located in different states and different regions within this Commonwealth could make it more difficult for areas in this Commonwealth to demonstrate attainment with Federal and State air quality standards. Since this result may be caused by the disparate requirements imposed by Federal and State law on generators and other "persons" as defined in section 3 of the Air Pollution Control Act in this Commonwealth and generators located in other states, the General Assembly supports changes to Federal clean air laws and regulations that will protect Pennsylvania's environment and ensure that electricity generators and other "persons" as defined in section 3 of the Air Pollution Control Act located in this Commonwealth are not placed at an undue competitive disadvantage. The commission will consult with the Department of Environmental Protection regarding this issue during the transition to retail competition.

 

Cross References.  Section 2802 is referred to in section 2806 of this title.

The 20 cases that cite 66 Pa. Cons. Stat. § 2802 most heavily, weighted by court and treatment. RelevanceNewestTreatment
1
GREENMetro. Edison Co. v. Pennsylvania Pub. Util. Comm'n, 767 F.3d 335 (3d Cir. 2014).
cites § 2802 8×subsections: (4) 2× (13) 2× (14) 2× (16) 2×cited by 46 cases
Where it cites § 2802
“2004); see also 66 Pa. Cons. Stat. Ann. § 2802(13) (stating that the same was the case in Pennsylvania).”
The case’s holding
Issue preclusion bars federal claims identical to issues squarely decided in a prior state proceeding where the party had a full and fair opportunity to litigate, applying the state's preclusion law.
2
GREENEnergy Conservation Council v. Pub. Util. Comm'n, 995 A.2d 465 (Pa. Commw. Ct. 2010).
cites § 2802 6×subsections: (12) 2× (20) 2×cited by 24 cases
Where it cites § 2802
“Chapter 28 of the Code is known as the Electricity Generation Customer Choice and Competition Act.”
Later courts cite it for
“interpretations of the code . . . and its own regulations are entitled to great deference and should not be reversed unless clearly erroneous.” · 2 citing courts
3
GREENIndianapolis Power & Light Co. v. Pennsylvania Pub. Util. Comm'n, 711 A.2d 1071 (Pa. Commw. Ct. 1998).
cites § 2802 8×subsections: (16) 2× (8) (10) (12)cited by 16 cases
Where it cites § 2802
“See generally 66 Pa.C.S. § 2802 (detailing impetus for, and objectives of, Competition Act).”
4
GREENArippa v. Pennsylvania Pub. Util. Comm'n, 792 A.2d 636 (Pa. Commw. Ct. 2002).
cites § 2802 4×subsections: (16) 3× (21)cited by 25 cases
Where it cites § 2802
“66 Pa.C.S. § 2802(16). 6 The switch from regulation to competition created “stranded costs,” costs alleged *643 not to be recoverable at market rates.”
Later courts cite it for
“charge applied to the bill of every customer accessing the transmission or distribution network,” · 1 citing court
cites § 2802 5×subsections: (10) 2× (5) (7)cited by 16 cases
Where it cites § 2802
“Section 2802 of the Choice Act, 66 Pa.C.S. § 2802 (emphasis added). CAUSE-PA/ TURN point specifically to subsection (14) *1096 as evidence of the General Assembly’s intent to preserve in the PUC the authority to regulate EGSs where necessary to protect the public: (14) This…”
Later courts cite it for
“when substantial evidence supports the commission's decision on a matter within the commission's expertise.” · 2 citing courts
6
GREENLloyd v. Pennsylvania Pub. Util. Comm'n, 904 A.2d 1010 (Pa. Commw. Ct. 2006).
cites § 2802 4×subsections: (10) 2×cited by 13 cases
Where it cites § 2802
“66 Pa.C.S. § 2802. Now we will turn to the specific appeals.”
The case’s holding
The principle of gradualism cannot override the fundamental requirement of cost-of-service allocation in utility ratemaking.
Later courts cite it for
“trumps all other ratemaking concerns - especially the polestar - cost of providing service.” · 2 citing courts
7
GREENGeorge v. Pennsylvania Pub. Util. Comm'n, 735 A.2d 1282 (Pa. Commw. Ct. 1999).
cites § 2802 4×subsections: (5) 2× (16) 2×cited by 21 cases
Where it cites § 2802
“66 Pa.C.S. § 2802(16). The PUC's final order establishes a competitive bidding process for PLR service to retail customers.”
8
GREENRetail Energy Supply Ass'n v. Pa. Pub. Util. Comm'n, 185 A.3d 1206 (Pa. Commw. Ct. 2018).
cites § 2802 2×subsections: (9) (10)cited by 12 cases
Where it cites § 2802
“" Section 2802(10) of the Choice Act, 66 Pa. C.S. § 2802(10). In furtherance of this policy, the Choice Act requires an EDC, such as PPL, to submit triennially for PUC approval a Universal Service and Energy Conservation Plan (USECP).”
Later courts cite it for
“when substantial evidence supports the commission's decision on a matter within the commission's expertise.” · 2 citing courts
9
GREENBorough of Lansdale v. PP & L, INC., 426 F. Supp. 2d 264 (E.D. Pa. 2006).
cites § 2802 3×subsections: (16) 3×cited by 7 cases
Where it cites § 2802
“66 Pa. Cons.Stat. §§ 2802(16) and 2807(e)(3) (“if a customer does not choose an alternative electric generation supplier, the electric distribution company .”
10
GREENPPL Elec. Utils. Corp. v. City of Lancaster & PA PUC, 125 A.3d 837 (Pa. Commw. Ct. 2015).
cites § 2802 2×subsections: (20) 2×cited by 9 cases
Where it cites § 2802
“” Section 2802(20) of the Code, 66 Pa.C.S. §2802(20). In this regard, the Code specifically empowers the PUC to: appoint inspectors to ensure “the proper conduct of the work of the [PUC],” and “for the purpose of enforcing the [Code’s] provisions, sections 305(c) and 307 of the…”
11
GREENMid-Atl. Power Supply Ass'n v. Pennsylvania Pub. Util. Comm'n, 746 A.2d 1196 (Pa. Commw. Ct. 2000).
cites § 2802 3×subsections: (12) (13)cited by 5 cases
Where it cites § 2802
“66 Pa.C.S. § 2802, § 2804(14). The PUC set up a framework for all interested parties to participate.”
12
GREENPECO Energy Co. v. Twp. of Upper Dublin, 922 A.2d 996 (Pa. Commw. Ct. 2007).
cites § 2802 1×subsections: (20)cited by 11 cases
Where it cites § 2802
“They cite, among other statutes, 66 Pa.C.S. § 2802(20), added as part of Chapter 28 of the Public Utility Code (Electricity Generation Customer Choice and Competition Act).”
Later courts cite it for
“the legislature intended the public utility code to preempt the field of public utility regulation.” · 3 citing courts
13
GREENGreen Mountain Energy Co. v. Pennsylvania Pub. Util. Comm'n, 812 A.2d 740 (Pa. Commw. Ct. 2002).
cites § 2802 2×subsections: (5) (12)cited by 4 cases
Where it cites § 2802
“” 66 Pa.C.S. § 2802(12). The Competition Act permits retail customers access to the competitive market for the generation of electricity because “[c]ompetitive market forces are more effective than economic regulation in controlling the cost of generating electricity.”
14
GREENSpectrum Arena Ltd. P'ship v. Commonwealth, 983 A.2d 641 (Pa. 2009).
cites § 2802 1×subsections: (16)cited by 9 cases
Where it cites § 2802
“66 Pa.C.S. § 2802(16); PP & L Indus. Consumer Alliance v.”
Later courts cite it for
“it is not within this court's power to alter this scheme and the impact of any inconsistency is more properly addressed directly to the legislature.” · 1 citing court
15
GREENHess v. Pennsylvania Pub. Util. Comm'n, 107 A.3d 246 (Pa. Commw. Ct. 2014).
cites § 2802 1×subsections: (20)cited by 8 cases
Where it cites § 2802
“Section 2802(20) of the Code, 66 Pa.C.S. § 2802(20), requires electric utilities to establish their own inspection, maintenance, repair and replacement standards based on the unique circumstances facing each utility.”
16
GREENBorough of Olyphant v. Pennsylvania Pub. Util. Comm'n, 861 A.2d 377 (Pa. Commw. Ct. 2004).
cites § 2802 1×subsections: (16)cited by 6 cases
Where it cites § 2802
“66 Pa.C.S. § 2802(16). This means that throughout the period of transition to electricity competition, PPL “shall continue to have the full obligation to serve, including the connection of customers, the delivery of electric energy and the production or acquisition of electric…”
17
GREENMet-Ed Indus. Users Grp. v. Pennsylvania Pub. Util. Comm'n, 960 A.2d 189 (Pa. Commw. Ct. 2008).
cites § 2802 1×subsections: (17)cited by 5 cases
Where it cites § 2802
“66 Pa.C.S. § 2802(17) (emphasis added). Section 2804(9) of the Competition Act provides, in pertinent part: The [PUC] shall ensure that universal service and energy conservation policies, activities and services are appropriately funded.”
18
GREENPPL Energyplus, LLC v. Commonwealth, 814 A.2d 861 (Pa. Commw. Ct. 2003).
cites § 2802 2×subsections: (12) (14)cited by 2 cases
Where it cites § 2802
“66 Pa.C.S. § 2802(12) (emphasis added). Thus, one purpose of the Competition Act is to establish standards for maintaining *864 safe and reliable electric service in a competitive market that involves EGS companies.”
19
GREENSpectrum Arena Ltd. P'ship v. Commonwealth, 921 A.2d 585 (Pa. Commw. Ct. 2007).
cites § 2802 1×subsections: (16)cited by 4 cases
Where it cites § 2802
“Section 2802(16) of the Competition Act, 66 Pa.C.S. § 2802(16). While customers would have to use the public utility to deliver electricity, they were free to purchase electricity from any supplier.”
20
GREENBorough of Lansdale v. PP & L, INC., 503 F. Supp. 2d 730 (E.D. Pa. 2007).
cites § 2802 1×cited by 3 cases
Where it cites § 2802
“Effective January 1, 1997, Pennsylvania adopted the Electric Generation Customer Choice and Competition Act, which effectively deregulated the business of generating electricity in the state.”

Show all 30 citing cases (list view) →

The flag is Syfertize’s treatment of the citing case itself, not of the statute. “Where it cites” is the passage in the opinion; the holding is a summary of the whole case and may concern another point. Annotations are extracted automatically from the opinions in the Syfert caselaw corpus.

Citing cases by year
199820112025

One bar per year. Tallest: 3 cases in 1998. These are opinions in the Syfert collection, which holds more of some courts’ recent opinions than their older ones, so a rise can reflect what the collection holds and not more litigation.

By court
Pa. Commw. Ct.22Pa.3E.D. Pa.33rd Cir.1W.D. Pa.1
By subsection
(4)1 case
Metro. Edison Co. v. Pennsylvania Pub. Util. Comm'n, 767 F.3d 335 (3d Cir. 2014).“2004); see also 66 Pa. Cons. Stat. Ann. § 2802(13) (stating that the same was the case in Pennsylvania).”
(5)3 cases
George v. Pennsylvania Pub. Util. Comm'n, 735 A.2d 1282 (Pa. Commw. Ct. 1999).“66 Pa.C.S. § 2802(16). The PUC's final order establishes a competitive bidding process for PLR service to retail customers.”
Coalition for Affordable Util. Servs. & Energy Efficiency v. Pennsylvania Pub. Util. Comm'n, 120 A.3d 1087 (Pa. Commw. Ct. 2015).“Section 2802 of the Choice Act, 66 Pa.C.S. § 2802 (emphasis added). CAUSE-PA/ TURN point specifically to subsection (14) *1096 as evidence of the General Assembly’s intent to preserve in the PUC the authority to regulate EGSs where necessary to protect the public: (14) This…”
Green Mountain Energy Co. v. Pennsylvania Pub. Util. Comm'n, 812 A.2d 740 (Pa. Commw. Ct. 2002).“” 66 Pa.C.S. § 2802(12). The Competition Act permits retail customers access to the competitive market for the generation of electricity because “[c]ompetitive market forces are more effective than economic regulation in controlling the cost of generating electricity.”
(7)1 case
(8)3 cases
Indianapolis Power & Light Co. v. Pennsylvania Pub. Util. Comm'n, 711 A.2d 1071 (Pa. Commw. Ct. 1998).“See generally 66 Pa.C.S. § 2802 (detailing impetus for, and objectives of, Competition Act).”
Grays Ferry Cogeneration P'ship v. PECO Energy Co., 998 F. Supp. 542 (E.D. Pa. 1998).
Duquesne Light Co. v. Pennsylvania Pub. Util. Comm'n, 715 A.2d 540 (Pa. Commw. Ct. 1998).
(9)2 cases
Retail Energy Supply Ass'n v. Pa. Pub. Util. Comm'n, 185 A.3d 1206 (Pa. Commw. Ct. 2018).“" Section 2802(10) of the Choice Act, 66 Pa. C.S. § 2802(10). In furtherance of this policy, the Choice Act requires an EDC, such as PPL, to submit triennially for PUC approval a Universal Service and Energy Conservation Plan (USECP).”
Blue Pilot Energy, LLC v. PA PUC, No. 1054 C.D. 2019 (Pa. Commw. Ct. Oct. 27, 2020).
(10)4 cases
Lloyd v. Pennsylvania Pub. Util. Comm'n, 904 A.2d 1010 (Pa. Commw. Ct. 2006).“66 Pa.C.S. § 2802. Now we will turn to the specific appeals.”
Retail Energy Supply Ass'n v. Pa. Pub. Util. Comm'n, 185 A.3d 1206 (Pa. Commw. Ct. 2018).
(12)5 cases
Energy Conservation Council v. Pub. Util. Comm'n, 995 A.2d 465 (Pa. Commw. Ct. 2010).“Chapter 28 of the Code is known as the Electricity Generation Customer Choice and Competition Act.”
Mid-Atl. Power Supply Ass'n v. Pennsylvania Pub. Util. Comm'n, 746 A.2d 1196 (Pa. Commw. Ct. 2000).“66 Pa.C.S. § 2802, § 2804(14). The PUC set up a framework for all interested parties to participate.”
PPL Energyplus, LLC v. Commonwealth, 814 A.2d 861 (Pa. Commw. Ct. 2003).“66 Pa.C.S. § 2802(12) (emphasis added). Thus, one purpose of the Competition Act is to establish standards for maintaining *864 safe and reliable electric service in a competitive market that involves EGS companies.”
(13)4 cases
NRG Energy, Inc. v. PA PUC, No. 58 C.D. 2019 (Pa. Commw. Ct. June 2, 2020).
(14)5 cases
PPL Energyplus, LLC v. Commonwealth, 814 A.2d 861 (Pa. Commw. Ct. 2003).
Spectrum Arena Ltd. P'ship v. Commonwealth, 951 A.2d 1226 (Pa. Commw. Ct. 2008).
NRG Energy, Inc. v. PA PUC, No. 58 C.D. 2019 (Pa. Commw. Ct. June 2, 2020).
(16)10 cases
Arippa v. Pennsylvania Pub. Util. Comm'n, 792 A.2d 636 (Pa. Commw. Ct. 2002).“66 Pa.C.S. § 2802(16). 6 The switch from regulation to competition created “stranded costs,” costs alleged *643 not to be recoverable at market rates.”
Borough of Lansdale v. PP & L, INC., 426 F. Supp. 2d 264 (E.D. Pa. 2006).“66 Pa. Cons.Stat. §§ 2802(16) and 2807(e)(3) (“if a customer does not choose an alternative electric generation supplier, the electric distribution company .”
George v. Pennsylvania Pub. Util. Comm'n, 735 A.2d 1282 (Pa. Commw. Ct. 1999).
Showing the top 5 of 10. More in the list view →
(17)1 case
Met-Ed Indus. Users Grp. v. Pennsylvania Pub. Util. Comm'n, 960 A.2d 189 (Pa. Commw. Ct. 2008).“66 Pa.C.S. § 2802(17) (emphasis added). Section 2804(9) of the Competition Act provides, in pertinent part: The [PUC] shall ensure that universal service and energy conservation policies, activities and services are appropriately funded.”
(20)5 cases
Energy Conservation Council v. Pub. Util. Comm'n, 995 A.2d 465 (Pa. Commw. Ct. 2010).
PPL Elec. Utils. Corp. v. City of Lancaster & PA PUC, 125 A.3d 837 (Pa. Commw. Ct. 2015).“” Section 2802(20) of the Code, 66 Pa.C.S. §2802(20). In this regard, the Code specifically empowers the PUC to: appoint inspectors to ensure “the proper conduct of the work of the [PUC],” and “for the purpose of enforcing the [Code’s] provisions, sections 305(c) and 307 of the…”
PECO Energy Co. v. Twp. of Upper Dublin, 922 A.2d 996 (Pa. Commw. Ct. 2007).“They cite, among other statutes, 66 Pa.C.S. § 2802(20), added as part of Chapter 28 of the Public Utility Code (Electricity Generation Customer Choice and Competition Act).”
Hess v. Pennsylvania Pub. Util. Comm'n, 107 A.3d 246 (Pa. Commw. Ct. 2014).“Section 2802(20) of the Code, 66 Pa.C.S. § 2802(20), requires electric utilities to establish their own inspection, maintenance, repair and replacement standards based on the unique circumstances facing each utility.”
PPL Elec. Utils. v. City of Lancaster, No. 55 MAP 2017 (Pa. Aug. 20, 2019).
(21)1 case
Arippa v. Pennsylvania Pub. Util. Comm'n, 792 A.2d 636 (Pa. Commw. Ct. 2002).

Show all 30 citing cases (list view) →

Enactment and amendments

Syfert holds no separate history line for this section. Where this code prints a source or history note, it appears with the text, usually at the end.

Versions

Edition shown: laws through the 2026 session (checked Sept. 2026). Syfert holds no earlier or later version of this section.

Pennsylvania Consolidated Statutes Home  |  Search Pennsylvania  |  Search cases for this section  |  syfert.com