Pennsylvania Consolidated Statutes homeSearch Pennsylvania
Pa. Cons. Stat.66 Pa. Cons. Stat. (Public Utilities)Chapter 28

66 Pa. Cons. Stat. § 2803 (2026)

 Definitions.

Edition and currency
laws through the 2026 session (checked Sept. 2026). The text is the edition Syfert holds; for a past event, check the version in force on that date.
Coverage note: this corpus holds the consolidated Pa.C.S. titles only. Unconsolidated P.S. statutes (UTPCPL 73 P.S. § 201-1, Liquor Code, wage payment laws) are not included; a miss here does not mean the statute does not exist. Check palegis.us.
Other sources
CURRENTlaws through the 2026 session (checked Sept. 2026) cited 1998–2026 36citing cases
At a glance

Courts have cited this section in 36 opinions since 1998, 10 of them in the last five years.

§ 2803.  Definitions.

The following words and phrases when used in this chapter shall have the meanings given to them in this section unless the context clearly indicates otherwise:

"Aggregator" or "market aggregator."  An entity, licensed by the commission, that purchases electric energy and takes title to electric energy as an intermediary for sale to retail customers.

"Bilateral contract."  An agreement, as approved by the commission, reached by two parties, each acting in its own independent self-interest, as a result of negotiations free of undue influence, duress or favoritism, in which the electric energy supplier agrees to sell and the electric distribution company agrees to buy a quantity of electric energy at a specified price for a specified period of time under terms agreed to by both parties, and which follows a standard industry template widely accepted in the industry or variations thereto accepted by the parties. Standard industry templates may include the EEI Master Agreement for physical energy purchases and sales and the ISDA Master Agreement for financial energy purchases and sales.

"Broker" or "marketer."  An entity, licensed by the commission, that acts as an agent or intermediary in the sale and purchase of electric energy but that does not take title to electric energy.

"Competitive transition charge."  A nonbypassable charge applied to the bill of every customer accessing the transmission or distribution network which (charge) is designed to recover an electric utility's transition or stranded costs as determined by the commission under sections 2804 (relating to standards for restructuring of electric industry) and 2808 (relating to competitive transition charge).

"Consumer."  A retail electric customer.

"Customer."  A retail electric customer.

"Default service provider."  An electric distribution company within its certified service territory or an alternative supplier approved by the commission that provides generation service to retail electric customers who:

(1)  contract for electric power, including energy and capacity, and the chosen electric generation supplier does not supply the service; or

(2)  do not choose an alternative electric generation supplier.

"Direct access."  The right of electric generation suppliers and end-use customers to utilize and interconnect with the electric transmission and distribution system on a nondiscriminatory basis at rates, terms and conditions of service comparable to the transmission and distribution companies' own use of the system to transport electricity from any generator of electricity to any end-use customer.

"Electric distribution company."  The public utility providing facilities for the jurisdictional transmission and distribution of electricity to retail customers, except building or facility owners/operators that manage the internal distribution system serving such building or facility and that supply electric power and other related electric power services to occupants of the building or facility.

"Electric generation supplier" or "electricity supplier." A person or corporation, including municipal corporations which choose to provide service outside their municipal limits except to the extent provided prior to the effective date of this chapter, brokers and marketers, aggregators or any other entities, that sells to end-use customers electricity or related services utilizing the jurisdictional transmission or distribution facilities of an electric distribution company or that purchases, brokers, arranges or markets electricity or related services for sale to end-use customers utilizing the jurisdictional transmission and distribution facilities of an electric distribution company. The term excludes building or facility owner/operators that manage the internal distribution system serving such building or facility and that supply electric power and other related power services to occupants of the building or facility. The term excludes electric cooperative corporations except as provided in 15 Pa.C.S. Ch. 74 (relating to generation choice for customers of electric cooperatives).

"End-use customer."  A retail electric customer.

"Reliability."  Includes adequacy and security. As used in this definition, "adequacy" means the provision of sufficient generation, transmission and distribution capacity so as to supply the aggregate electric power and energy requirements of consumers, taking into account scheduled and unscheduled outages of system facilities; and "security" means designing, maintaining and operating a system so that it can handle emergencies safely while continuing to operate.

"Renewable resource."  Includes technologies such as solar photovoltaic energy, solar thermal energy, wind power, low-head hydropower, geothermal energy, landfill and mine-based methane gas, energy from waste and sustainable biomass energy.

"Retail customer."  A retail electric customer.

"Retail electric customer."  A direct purchaser of electric power. The term excludes an occupant of a building or facility where the owners/operators manage the internal distribution system serving such building or facility and supply electric power and other related power services to occupants of the building or facility; where such owners/operators are direct purchasers of electric power; and where the occupants are not direct purchasers.

"Transition or stranded costs."  An electric utility's known and measurable net electric generation-related costs, determined on a net present value basis over the life of the asset or liability as part of its restructuring plan, which traditionally would be recoverable under a regulated environment but which may not be recoverable in a competitive electric generation market and which the commission determines will remain following mitigation by the electric utility. This term includes:

(1)  Regulatory assets and other deferred charges typically recoverable under current regulatory practice, the unfunded portion of the utility's projected nuclear generating plant decommissioning costs and cost obligations under contracts with nonutility generating projects which have received a commission order, the recoverability of which shall be determined under section 2808(c)(1) (relating to competitive transition charge).

(2)  Prudently incurred costs related to cancellation, buyout, buydown or renegotiation of nonutility generating projects consistent with section 527 (relating to cogeneration rules and regulations), the recoverability of which shall be determined pursuant to section 2808(c)(2).

(3)  The following costs, the recoverability of which shall be determined pursuant to section 2808(c)(3):

(i)  Net plant investments and costs attributable to the utility's existing generation plants and facilities.

(ii)  The utility's disposal of spent nuclear fuel.

(iii)  The utility's long-term purchase power commitments other than the costs defined in paragraphs (1) and (2).

(iv)  Retirement costs attributable to the utility's existing generating plants other than the costs defined in paragraph (1).

(v)  Other transition costs of the utility, including costs of employee severance, retraining, early retirement, outplacement and related expenses, at reasonable levels, for employees who are affected by changes that occur as a result of the restructuring of the electric industry occasioned by this chapter.

The term includes any costs attributable to physical plants no longer used and useful because of the transition to retail competition. The term excludes any amounts previously disallowed by the commission as imprudently incurred. To the extent that the recoverability of amounts that are sought to be included as transition or stranded costs are subject to appellate review as of the time of the commission determination, any determination to include such costs shall be reversed to the extent required by the results of that appellate review.

"Transmission and distribution costs."  All costs directly or indirectly incurred to provide transmission and distribution services to retail electric customers. This includes the return of and return on facilities and other capital investments necessary to provide transmission and distribution services and associated operating expenses, including applicable taxes.

"Universal service and energy conservation."  Policies, protections and services that help low-income customers to maintain electric service. The term includes customer assistance programs, termination of service protection and policies and services that help low-income customers to reduce or manage energy consumption in a cost-effective manner, such as the low-income usage reduction programs, application of renewable resources and consumer education.

(Oct. 15, 2008, P.L.1592, No.129, eff. 30 days)

 

2008 Amendment.  Act 129 added the defs. of "bilateral contract" and "default service provider." See the preamble to Act 129 of 2008 in the appendix to this title for special provisions relating to legislative findings and declarations.

References in Text.  Chapter 74 of Title 15, referred to in the def. of "electric generation supplier" or "electricity supplier," is expired.

The 20 cases that cite 66 Pa. Cons. Stat. § 2803 most heavily, weighted by court and treatment. RelevanceNewestTreatment
1
GREENMetro. Edison Co. v. Pennsylvania Pub. Util. Comm'n, 767 F.3d 335 (3d Cir. 2014).
cites § 2803 8×cited by 46 cases
Where it cites § 2803
“”5 66 Pa. Cons. Stat. Ann. § 2803 (defining “[t]ransition or stranded costs”).”
The case’s holding
Issue preclusion bars federal claims identical to issues squarely decided in a prior state proceeding where the party had a full and fair opportunity to litigate, applying the state's preclusion law.
2
GREENSunrise Energy, LLC v. FirstEnergy Corp., 148 A.3d 894 (Pa. Commw. Ct. 2016).
cites § 2803 6×cited by 20 cases
Where it cites § 2803
“66 Pa. C.S. §2803. 2 Amended Complaint, ¶30.”
Later courts cite it for
“an administrative agency has exclusive jurisdiction where the legislature has given it the power to adjudicate on a particular subject matter.” · 3 citing courts
3
GREENArippa v. Pennsylvania Pub. Util. Comm'n, 792 A.2d 636 (Pa. Commw. Ct. 2002).
cites § 2803 4×cited by 25 cases
Where it cites § 2803
“66 Pa.C.S. § 2803 defines the competitive transition cost as “[a] nonbypassable charge applied to the bill of every customer accessing the transmission or distribution network which (charge) is designed to recover an electric utility’s transition or stranded costs as determined…”
Later courts cite it for
“charge applied to the bill of every customer accessing the transmission or distribution network,” · 1 citing court
4
GREENBorough of Olyphant v. Pennsylvania Pub. Util. Comm'n, 861 A.2d 377 (Pa. Commw. Ct. 2004).
cites § 2803 6×cited by 6 cases
Where it cites § 2803
“” 66 Pa.C.S. § 2803 (emphasis added). To offset PUC-approved stranded costs, utilities may charge both Competitive Transition Charges (CTCs) and Intangible Transition Charges (ITCs).”
cites § 2803 3×cited by 16 cases
Where it cites § 2803
“See 66 Pa.C.S. §§ 2803 (defining “default service provider”), 2807(e).”
Later courts cite it for
“when substantial evidence supports the commission's decision on a matter within the commission's expertise.” · 2 citing courts
6
GREENRetail Energy Supply Ass'n v. Pa. Pub. Util. Comm'n, 185 A.3d 1206 (Pa. Commw. Ct. 2018).
cites § 2803 2×cited by 12 cases
Where it cites § 2803
“" Section 2803 of the Choice Act, 66 Pa. C.S. § 2803. The term USEC includes CAPs, id.”
Later courts cite it for
“when substantial evidence supports the commission's decision on a matter within the commission's expertise.” · 2 citing courts
7
cites § 2803 3×cited by 14 cases
Where it cites § 2803
“66 Pa.C.S. § 2803. Default service providers are also known as “providers of last resort.”
Later courts cite it for
“an administrative agency may revise and correct its prior interpretation of a statute; but 'it cannot expect that its later interpretation is entitled to very much deference.” · 2 citing courts
8
GREENEnergy Conservation Council v. Pub. Util. Comm'n, 995 A.2d 465 (Pa. Commw. Ct. 2010).
cites § 2803 2×cited by 24 cases
Where it cites § 2803
“66 Pa.C.S. § 2803 (emphasis added). Finally, Section 2805 recognizes the need for the PUC and Pennsylvania utilities to work with generators, transmission companies, and distribution companies in the surrounding region, as well as the Federal Government and its agents to ensure…”
Later courts cite it for
“interpretations of the code . . . and its own regulations are entitled to great deference and should not be reversed unless clearly erroneous.” · 2 citing courts
9
GREENMetro. Edison Co. v. Pennsylvania Pub. Util. Comm'n, 22 A.3d 353 (Pa. Commw. Ct. 2011).
cites § 2803 3×cited by 11 cases
Where it cites § 2803
“Citing Section 2803 of the Electricity Generation Customer Choice and Competition Act (Competition Act), 66 Pa.C.S. § 2803, which defines “transmission costs” as all costs “directly or indirectly incurred to provide transmission and distribution services to retail electric…”
10
GREENHIKO Energy, LLC v. Pennsylvania Pub. Util. Comm'n, 163 A.3d 1079 (Pa. Commw. Ct. 2017).
cites § 2803 2×cited by 9 cases
Where it cites § 2803
“In particular, (continued…) 66 Pa. C.S. §2803. Additionally, an “electric distribution company” or EDC, is: “The public utility providing facilities for the jurisdictional transmission and distribution of electricity to retail customers ….”
11
GREENIndianapolis Power & Light Co. v. Pennsylvania Pub. Util. Comm'n, 711 A.2d 1071 (Pa. Commw. Ct. 1998).
cites § 2803 3×cited by 16 cases
Where it cites § 2803
“” 66 Pa. C.S. §§ 2803, 2804(13). In sum, even if we looked no further than the stranded-cost provisions, we would find nothing to implicate the Commerce Clause.”
12
GREENAm. Elec. Power Serv. Corp. v. Commonwealth of PA, 160 A.3d 950 (Pa. Commw. Ct. 2017).
cites § 2803 2×cited by 6 cases
Where it cites § 2803
“” 66 Pa. C.S. § 2803; see also Delmarva Power & Light Company v.”
13
GREENLloyd v. Pennsylvania Pub. Util. Comm'n, 904 A.2d 1010 (Pa. Commw. Ct. 2006).
cites § 2803 2×cited by 13 cases
Where it cites § 2803
“" 66 Pa.C.S. § 2803. [6] "Rate" is defined in the Code as "[e]very individual, or joint fare, toll, charge, rental, or other compensation whatsoever of any public utility, or contract carrier by motor vehicle, made, demanded, or received for any service within this part,…”
The case’s holding
The principle of gradualism cannot override the fundamental requirement of cost-of-service allocation in utility ratemaking.
Later courts cite it for
“trumps all other ratemaking concerns - especially the polestar - cost of providing service.” · 2 citing courts
14
GREENMet-Ed Indus. Users Grp. v. Pennsylvania Pub. Util. Comm'n, 960 A.2d 189 (Pa. Commw. Ct. 2008).
cites § 2803 3×cited by 5 cases
Where it cites § 2803
“66 Pa.C.S. § 2803. Here, the cost of switching electric generators and the cost of upgrading transmission facilities are costs directly or indirectly incurred to provide transmission services to customers.”
15
GREENPennsylvania Power Co. v. Pub. Util. Comm'n, 932 A.2d 300 (Pa. Commw. Ct. 2007).
cites § 2803 2×cited by 9 cases
Where it cites § 2803
“66 Pa.C.S. § 2803. Section 2 of the Alternative Energy Portfolio Standards Act, Act of November 30, 2004, P.”
Later courts cite it for
“interpretation of the aeps act is entitled to great deference and will not be reversed unless clearly erroneous” · 1 citing court
16
GREENUnited States Steel Corp. v. Pennsylvania Pub. Util. Comm'n, 850 A.2d 783 (Pa. Commw. Ct. 2004).
cites § 2803 2×cited by 8 cases
Where it cites § 2803
“Steel is still paying Duquesne for its "transition or stranded costs" as defined in Section 2803 of the Competition Act, 66 Pa.C.S. § 2803, thus violating rate-cap protections in Section 2804(4)(ii) of the Competition Act.”
17
GREENIn re PP&L, Inc., 838 A.2d 1 (Pa. Commw. Ct. 2003).
cites § 2803 1×cited by 19 cases
Where it cites § 2803
“See Section 4 of the Competition Act, 66 Pa.C.S. § 2803. 18 . The process of securitization converts the utility’s entitlement to receive future transition charges from its customers into a current, fully vested property right that may be pledged or sold as security for the…”
Later courts cite it for
“based on the concept that an informed investor would not willingly pay more for the subject property than would be necessary to develop an alternative providing economically equivalent benefits.” · 2 citing courts
18
GREENDelmarva Power & Light Co. v. Commonwealth, 870 A.2d 901 (Pa. 2005).
cites § 2803 2×cited by 6 cases
Where it cites § 2803
“4 See 66 Pa.C.S. § 2803. In August 2000, the Fiscal Office sent both Conectiv and PPL three notices of assessment and invoices.”
19
NEUTRALAm. Elec. Power Serv. Corp. v. Commonwealth of PA, 184 A.3d 1031 (Pa. Commw. Ct. 2018).
cites § 2803 2×cited by 12 cases
Where it cites § 2803
“" 66 Pa. C.S. § 2803 (emphasis added). Taxpayer argues that it is not a "public utility.”
20
GREENPennsylvania State Univ. v. Pub. Util. Comm'n, 988 A.2d 771 (Pa. Commw. Ct. 2010).
cites § 2803 2×cited by 3 cases
Where it cites § 2803
“[6] Section 2803 of the Competition Act, 66 Pa.C.S. § 2803, defines stranded or transition costs as: An electric utility's known and measurable net electric generation related costs, determined as a net present value basis over the life of the asset or liability as part of its…”

Show all 36 citing cases (list view) →

The flag is Syfertize’s treatment of the citing case itself, not of the statute. “Where it cites” is the passage in the opinion; the holding is a summary of the whole case and may concern another point. Annotations are extracted automatically from the opinions in the Syfert caselaw corpus.

Citing cases by year
199820122026

One bar per year. Tallest: 4 cases in 2024. 2026 is a partial year. These are opinions in the Syfert collection, which holds more of some courts’ recent opinions than their older ones, so a rise can reflect what the collection holds and not more litigation.

By court
Pa. Commw. Ct.31Pa.2E.D. Pa.23rd Cir.1
By subsection

Courts have not cited this section by subsection, so its cases are not split up here. The Leading cases tab lists the cases that cite it most heavily.

Show all 36 citing cases (list view) →

Enactment and amendments

Syfert holds no separate history line for this section. Where this code prints a source or history note, it appears with the text, usually at the end.

Versions

Edition shown: laws through the 2026 session (checked Sept. 2026). Syfert holds no earlier or later version of this section.

Pennsylvania Consolidated Statutes Home  |  Search Pennsylvania  |  Search cases for this section  |  syfert.com