18 Nevada opinions name it 1 courts 1914–2020 0 in the last five years
The cases below were cited by Nevada courts in a sentence that names this issue. Sides come from how each citing opinion treated the case (Syfertize flag on that citation), so a case can appear on both: that is where the law is contested. A red or yellow chip is the case's own overall treatment.
| Case | Followed | Cited |
|---|---|---|
Wm. R. Clarke Corp. v. Safeco Insurance of Americagreen2 sentences2008Co., 15 Cal.4th 882 , 64 Cal.Rptr.2d 578 , 938 P.2d 372, 376 (1997) (discussing statutory forms for lien waiver provisions that do not violate public policy if the waiver is "in conjunction with payment, or a promise of payment"). [32] Although the district court concluded that all lien waiver provisions violate public policy and are thus unenforceable, whether a lien waiver provision is enforceable, as set forth above, depends on a case-by-case analysis of whether it violates public policy, for example, by waiving the lien right regardless of whether the contractor receives payment. 2008Co., 15 Cal.4th 882 , 64 Cal.Rptr.2d 578 , 938 P.2d 372, 376 (1997) (discussing statutory forms for lien waiver provisions that do not violate public policy if the waiver is "in conjunction with payment, or a promise of payment"). [32] Although the district court concluded that all lien waiver provisions violate public policy and are thus unenforceable, whether a lien waiver provision is enforceable, as set forth above, depends on a case-by-case analysis of whether it violates public policy, for example, by waiving the lien right regardless of whether the contractor receives payment. | 2 | 2 |
Lehrer McGovern Bovis, Inc. v. Bullock Insulation, Inc.green2 sentences2020See generally Simmons Self-Storage v. Rib Roof, Inc., 130 Nev. 540 , 545, 331 P.3d 850 , 853 (2014) (steel manufacturer and supplier brought a lien foreclosure action against six properties it had supplied steel to, despite execution of lien release forms and the posting of surety bonds); Lehrer McGovern Bovis, Inc. v. Bullock Insulation, Inc., 124 Nev. 1102, 1115-17 , 197 P.3d 1032, 1040-42 (2008) (unpaid subcontractor prevailed in a lien foreclosure action, despite the existence of a lien waiver provision in the subcontract, where the lien waiver provision violated Nevada's public policy fav 2020See generally Simmons Self-Storage v. Rib Roof, Inc., 130 Nev. 540 , 545, 331 P.3d 850 , 853 (2014) (steel manufacturer and supplier brought a lien foreclosure action against six properties it had supplied steel to, despite execution of lien release forms and the posting of surety bonds); Lehrer McGovern Bovis, Inc. v. Bullock Insulation, Inc., 124 Nev. 1102, 1115-17 , 197 P.3d 1032, 1040-42 (2008) (unpaid subcontractor prevailed in a lien foreclosure action, despite the existence of a lien waiver provision in the subcontract, where the lien waiver provision violated Nevada's public policy fav | 1 | 1 |
Barney v. Mt. Rose Heating & Air Conditioninggreen2 sentences2012Rose Heating & Air, 124 Nev. 821, 827 , 192 P.3d 730, 734 (2008) (district court has discretion pursuant to NRS 108.237). 2012Rose Heating & Air, 124 Nev. 821, 827 , 192 P.3d 730, 734 (2008) (district court has discretion pursuant to NRS 108.237). | 1 | 1 |
SD Deacon Corp. v. Gastongreen1 sentence2010Deacon Corp. v. Gaston, 206 P.3d 689, 691 (Wash. Ct. App. 2009). | 1 | 1 |
American Standard Homes Corp. v. Reineckegreen1 sentence2007Ct. 2004) (concluding that the doctrine of substantial compliance does not apply when the timeliness of serving notice is at issue, and thus, the trial court properly struck a mechanics’ lien claim since notice of the claim was not served until one month after the statutory time period allowed for service); American Standard Homes Corp. v. Reinecke, 425 S.E.2d 515, 518 (Va. 1993) (indicating that, unless a lien is perfected within the time outlined by statute, it is lost); Marsh-McLennan Bldg., Inc. v. Clapp, 980 P.2d 311 , 313 n.1 (Wash. Ct. App. 1999) (explaining that an unlawful detainer st | 1 | 1 |
Browning v. Dixongreen2 sentences2007Ct. 2004) (concluding that the doctrine of substantial compliance does not apply when the timeliness of serving notice is at issue, and thus, the trial court properly struck a mechanics’ lien claim since notice of the claim was not served until one month after the statutory time period allowed for service); American Standard Homes Corp. v. Reinecke, 425 S.E.2d 515, 518 (Va. 1993) (indicating that, unless a lien is perfected within the time outlined by statute, it is lost); Marsh-McLennan Bldg., Inc. v. Clapp, 980 P.2d 311 , 313 n.1 (Wash. Ct. App. 1999) (explaining that an unlawful detainer st 2007Ct. 2004) (concluding that the doctrine of substantial compliance does not apply when the timeliness of serving notice is at issue, and thus, the trial court properly struck a mechanics’ lien claim since notice of the claim was not served until one month after the statutory time period allowed for service); American Standard Homes Corp. v. Reinecke, 425 S.E.2d 515, 518 (Va. 1993) (indicating that, unless a lien is perfected within the time outlined by statute, it is lost); Marsh-McLennan Bldg., Inc. v. Clapp, 980 P.2d 311 , 313 n.1 (Wash. Ct. App. 1999) (explaining that an unlawful detainer st | 1 | 1 |
Swanson v. Flynngreen1 sentence2007Ct. 2004) (concluding that the doctrine of substantial compliance does not apply when the timeliness of serving notice is at issue, and thus, the trial court properly struck a mechanics’ lien claim since notice of the claim was not served until one month after the statutory time period allowed for service); American Standard Homes Corp. v. Reinecke, 425 S.E.2d 515, 518 (Va. 1993) (indicating that, unless a lien is perfected within the time outlined by statute, it is lost); Marsh-McLennan Bldg., Inc. v. Clapp, 980 P.2d 311 , 313 n.1 (Wash. Ct. App. 1999) (explaining that an unlawful detainer st | 1 | 1 |
Landvatter Ready Mix, Inc. v. Buckeygreen1 sentence2003A. Bock, Annotation, Validity and Effect of Provision in Contract Against Mechanic’s Lien, 76 A.L.R.2d 1087 , 1089 (1961); see, e.g., Durant Const., Inc. v. Gourley, 336 N.W.2d 856 (Mich. Ct. App. 1983); see also Landvatter Ready Mix, Inc. v. Buckey, 963 S.W.2d 298, 301 (Mo. Ct. App. 1997) (recognizing that “[i]t has long been the rule that a mechanic’s lien claim may be waived”). 10 See, e.g., 770 Ill. | 1 | 1 |
Williams Bros. Construction v. Vaughngreen1 sentence2003Const. v. Vaughn, 631 P.2d 688, 690 (Mont. 1981)). 7 See NRS 108.239(5) (requiring the district court to hear and determine mechanic’s lien claims in a summary way). 8 55 Nev. 134 , 28 P.2d 499 (1934). 9 100 Nev. 185 , 678 P.2d 679 (1984). 10 55 Nev. at 140 , 28 P.2d at 499 . 11 Id. at 142-43 , 28 P.2d at 500 . 12 100 Nev. at 186-87 , 678 P.2d at 680 . 13 Id. at 189-90 , 678 P.2d at 682 . 14 Id. at 190 , 678 P.2d at 682 . 15 Commercial’s argument that, by failing to allow a mechanic’s lien claim for delay-related damages, the district court would permit Amedeo to be unjustly enriched is withou | 1 | 1 |
Durant Construction, Inc v. Gourleygreen1 sentence2003A. Bock, Annotation, Validity and Effect of Provision in Contract Against Mechanic’s Lien, 76 A.L.R.2d 1087 , 1089 (1961); see, e.g., Durant Const., Inc. v. Gourley, 336 N.W.2d 856 (Mich. Ct. App. 1983); see also Landvatter Ready Mix, Inc. v. Buckey, 963 S.W.2d 298, 301 (Mo. Ct. App. 1997) (recognizing that “[i]t has long been the rule that a mechanic’s lien claim may be waived”). 10 See, e.g., 770 Ill. | 1 | 1 |
Capron v. Stroutgreen1 sentence1914See, also, Capron v. Strout, 11 Nev. 304 . | 1 | 1 |
| Case | Negative | Cited |
|---|---|---|
| No negative-treatment citations attached to this issue in Nevada. Read the followed side critically anyway. | ||
| Case | Cited | Years |
|---|---|---|
Ray Heating Products, Inc. v. Miller
green
2 sentences1985In Ray Heating Products v. Miller, supra, we held that a lien claim was not insufficient for failure to state the “terms, time given and conditions of the contract,” explaining that “if there are no special terms, time or conditions given, none can be stated, and in the absence of any such specifications, or proofs to the contrary, the law would presume that none existed, and that the materials were to be paid for on delivery.” 74 Nev. at 126 , 324 P.2d at 238 . 1985In Ray Heating Products v. Miller, supra, we held that a lien claim was not insufficient for failure to state the “terms, time given and conditions of the contract,” explaining that “if there are no special terms, time or conditions given, none can be stated, and in the absence of any such specifications, or proofs to the contrary, the law would presume that none existed, and that the materials were to be paid for on delivery.” 74 Nev. at 126 , 324 P.2d at 238 . | 2 | 1970–1985 |
Milner v. Shuey
green
2 sentences1970Relying on the authority of Porteous Decorative Co. Inc. v. Fee, 29 Nev. 375 , 91 P. 135 (1907), Close makes a multi-pronged attack upon the lien claim, contending it did not comply with NRS 108.060. 4 Porteous was impliedly overruled in Milner v. Shuey, 57 Nev. 159 , 60 P.2d 604 (1936), and in Ray Heating Prods. 1970Relying on the authority of Porteous Decorative Co. Inc. v. Fee, 29 Nev. 375 , 91 P. 135 (1907), Close makes a multi-pronged attack upon the lien claim, contending it did not comply with NRS 108.060. 4 Porteous was impliedly overruled in Milner v. Shuey, 57 Nev. 159 , 60 P.2d 604 (1936), and in Ray Heating Prods. | 2 | 1958–1970 |
Marsh-McLennan Building, Inc. v. Clapp
green
1 sentence2007Ct. 2004) (concluding that the doctrine of substantial compliance does not apply when the timeliness of serving notice is at issue, and thus, the trial court properly struck a mechanics’ lien claim since notice of the claim was not served until one month after the statutory time period allowed for service); American Standard Homes Corp. v. Reinecke, 425 S.E.2d 515, 518 (Va. 1993) (indicating that, unless a lien is perfected within the time outlined by statute, it is lost); Marsh-McLennan Bldg., Inc. v. Clapp, 980 P.2d 311 , 313 n.1 (Wash. Ct. App. 1999) (explaining that an unlawful detainer st | 1 | 2007–2007 |
Hardin v. Jones
green
2 sentences2007Ct. 2004) (concluding that the doctrine of substantial compliance does not apply when the timeliness of serving notice is at issue, and thus, the trial court properly struck a mechanics’ lien claim since notice of the claim was not served until one month after the statutory time period allowed for service); American Standard Homes Corp. v. Reinecke, 425 S.E.2d 515, 518 (Va. 1993) (indicating that, unless a lien is perfected within the time outlined by statute, it is lost); Marsh-McLennan Bldg., Inc. v. Clapp, 980 P.2d 311 , 313 n.1 (Wash. Ct. App. 1999) (explaining that an unlawful detainer st 2007Ct. 2004) (concluding that the doctrine of substantial compliance does not apply when the timeliness of serving notice is at issue, and thus, the trial court properly struck a mechanics’ lien claim since notice of the claim was not served until one month after the statutory time period allowed for service); American Standard Homes Corp. v. Reinecke, 425 S.E.2d 515, 518 (Va. 1993) (indicating that, unless a lien is perfected within the time outlined by statute, it is lost); Marsh-McLennan Bldg., Inc. v. Clapp, 980 P.2d 311 , 313 n.1 (Wash. Ct. App. 1999) (explaining that an unlawful detainer st | 1 | 2007–2007 |
Paterson v. Condos
green
2 sentences2003Const. v. Vaughn, 631 P.2d 688, 690 (Mont. 1981)). 7 See NRS 108.239(5) (requiring the district court to hear and determine mechanic’s lien claims in a summary way). 8 55 Nev. 134 , 28 P.2d 499 (1934). 9 100 Nev. 185 , 678 P.2d 679 (1984). 10 55 Nev. at 140 , 28 P.2d at 499 . 11 Id. at 142-43 , 28 P.2d at 500 . 12 100 Nev. at 186-87 , 678 P.2d at 680 . 13 Id. at 189-90 , 678 P.2d at 682 . 14 Id. at 190 , 678 P.2d at 682 . 15 Commercial’s argument that, by failing to allow a mechanic’s lien claim for delay-related damages, the district court would permit Amedeo to be unjustly enriched is withou 2003Const. v. Vaughn, 631 P.2d 688, 690 (Mont. 1981)). 7 See NRS 108.239(5) (requiring the district court to hear and determine mechanic’s lien claims in a summary way). 8 55 Nev. 134 , 28 P.2d 499 (1934). 9 100 Nev. 185 , 678 P.2d 679 (1984). 10 55 Nev. at 140 , 28 P.2d at 499 . 11 Id. at 142-43 , 28 P.2d at 500 . 12 100 Nev. at 186-87 , 678 P.2d at 680 . 13 Id. at 189-90 , 678 P.2d at 682 . 14 Id. at 190 , 678 P.2d at 682 . 15 Commercial’s argument that, by failing to allow a mechanic’s lien claim for delay-related damages, the district court would permit Amedeo to be unjustly enriched is withou | 1 | 2003–2003 |
Udevco, Inc. v. Wagner
green
2 sentences2003Const. v. Vaughn, 631 P.2d 688, 690 (Mont. 1981)). 7 See NRS 108.239(5) (requiring the district court to hear and determine mechanic’s lien claims in a summary way). 8 55 Nev. 134 , 28 P.2d 499 (1934). 9 100 Nev. 185 , 678 P.2d 679 (1984). 10 55 Nev. at 140 , 28 P.2d at 499 . 11 Id. at 142-43 , 28 P.2d at 500 . 12 100 Nev. at 186-87 , 678 P.2d at 680 . 13 Id. at 189-90 , 678 P.2d at 682 . 14 Id. at 190 , 678 P.2d at 682 . 15 Commercial’s argument that, by failing to allow a mechanic’s lien claim for delay-related damages, the district court would permit Amedeo to be unjustly enriched is withou 2003Const. v. Vaughn, 631 P.2d 688, 690 (Mont. 1981)). 7 See NRS 108.239(5) (requiring the district court to hear and determine mechanic’s lien claims in a summary way). 8 55 Nev. 134 , 28 P.2d 499 (1934). 9 100 Nev. 185 , 678 P.2d 679 (1984). 10 55 Nev. at 140 , 28 P.2d at 499 . 11 Id. at 142-43 , 28 P.2d at 500 . 12 100 Nev. at 186-87 , 678 P.2d at 680 . 13 Id. at 189-90 , 678 P.2d at 682 . 14 Id. at 190 , 678 P.2d at 682 . 15 Commercial’s argument that, by failing to allow a mechanic’s lien claim for delay-related damages, the district court would permit Amedeo to be unjustly enriched is withou | 1 | 2003–2003 |
Burlington Northern Railroad Company v. Department Of Revenue Of The State Of Washington
green
1 sentence2002(Emphasis added; citations omitted.) Burlington Northern v. Department of Revenue, 934 F.2d 1064 , 1069 (9th Cir. 1991); Adriana Intern. | 1 | 2002–2002 |
Hays v. Pigg
green
1 sentence1990In Hayes v. Pigg, 515 P.2d 924 (Or. 1973), the Oregon court held: If the non-lienable charge is extremely small as compared to *713 the total item in which it is included, and if it is inserted without malicious intent, the rule of de minimum non curat lex should apply. | 1 | 1990–1990 |
Porteous Decorative Co. v. Fee
green
1 sentence1970Relying on the authority of Porteous Decorative Co. Inc. v. Fee, 29 Nev. 375 , 91 P. 135 (1907), Close makes a multi-pronged attack upon the lien claim, contending it did not comply with NRS 108.060. 4 Porteous was impliedly overruled in Milner v. Shuey, 57 Nev. 159 , 60 P.2d 604 (1936), and in Ray Heating Prods. | 1 | 1970–1970 |
Lonkey v. Wells
neutral
1 sentence1958Said claimant has duly performed all terms of said contract on its part to be performed, has furnished said labor and materials upon said contract. * * * That the market value of said services due to claimant is the sum of $1487.86, none of which has been paid.” (1) Respondents’ first contention is that this language did not comply with the requirement for a statement of the claimant’s “demand after deducting all just credits and offsets.” The same attack was made against a similar allegation in Milner et al. v. Shuey, 57 Nev. 159 , 60 P.2d 604 , 69 P.2d 771 , but the allegation consisting of | 1 | 1958–1958 |
Warren v. Quade
green
2 sentences1958Said claimant has duly performed all terms of said contract on its part to be performed, has furnished said labor and materials upon said contract. * * * That the market value of said services due to claimant is the sum of $1487.86, none of which has been paid.” (1) Respondents’ first contention is that this language did not comply with the requirement for a statement of the claimant’s “demand after deducting all just credits and offsets.” The same attack was made against a similar allegation in Milner et al. v. Shuey, 57 Nev. 159 , 60 P.2d 604 , 69 P.2d 771 , but the allegation consisting of 1958Said claimant has duly performed all terms of said contract on its part to be performed, has furnished said labor and materials upon said contract. * * * That the market value of said services due to claimant is the sum of $1487.86, none of which has been paid.” (1) Respondents’ first contention is that this language did not comply with the requirement for a statement of the claimant’s “demand after deducting all just credits and offsets.” The same attack was made against a similar allegation in Milner et al. v. Shuey, 57 Nev. 159 , 60 P.2d 604 , 69 P.2d 771 , but the allegation consisting of | 1 | 1958–1958 |
Baird v. Ocequeda
green
2 sentences1949Hooper v. Flood, 1880, 54 Cal. 218 , properly held: Demurrer for misjoinder should have been sustained as to defendant Flood alleged in the complaint and nominated in the lien claim to have been the agent of Irvine, the owner; that the word “cash” does not state terms, time given and conditions of contract, no longer required by 1187, Code of Civil Procedure, Baird v. Ocequeda, 8 Cal.2d 700 , 67 P.2d 1055 ; that statement of intervener “that materials were furnished for Irvine and Lien was claimed on his interest in the land and buildings,” was not a statement of owner or reputed owner. 1949Hooper v. Flood, 1880, 54 Cal. 218 , properly held: Demurrer for misjoinder should have been sustained as to defendant Flood alleged in the complaint and nominated in the lien claim to have been the agent of Irvine, the owner; that the word “cash” does not state terms, time given and conditions of contract, no longer required by 1187, Code of Civil Procedure, Baird v. Ocequeda, 8 Cal.2d 700 , 67 P.2d 1055 ; that statement of intervener “that materials were furnished for Irvine and Lien was claimed on his interest in the land and buildings,” was not a statement of owner or reputed owner. | 1 | 1949–1949 |
Hooper v. Flood
neutral
1 sentence1949Hooper v. Flood, 1880, 54 Cal. 218 , properly held: Demurrer for misjoinder should have been sustained as to defendant Flood alleged in the complaint and nominated in the lien claim to have been the agent of Irvine, the owner; that the word “cash” does not state terms, time given and conditions of contract, no longer required by 1187, Code of Civil Procedure, Baird v. Ocequeda, 8 Cal.2d 700 , 67 P.2d 1055 ; that statement of intervener “that materials were furnished for Irvine and Lien was claimed on his interest in the land and buildings,” was not a statement of owner or reputed owner. | 1 | 1949–1949 |
Norton v. Bedell Engineering Co.
green
2 sentences1949In Norton v. Bedell Engineering Co., 1928, 88 Cal.App. 777 , 264 P. 311 , where neither complaint nor lien claim stated, as required by 1187, C.C.P., kind of materials furnished or work done, objection to evidence was sustained without leave to amend despite 1203, C.C.P., “where complaint stated none of the material matters in the lien claim and did not attach or contain a copy of lien claim.” The court *368 there said it could not be ascertained from the complaint as to contents of lien notice, whether compensation was sought for lumber, hardware, paint, plaster or brick nor whether work perf 1949In Norton v. Bedell Engineering Co., 1928, 88 Cal.App. 777 , 264 P. 311 , where neither complaint nor lien claim stated, as required by 1187, C.C.P., kind of materials furnished or work done, objection to evidence was sustained without leave to amend despite 1203, C.C.P., “where complaint stated none of the material matters in the lien claim and did not attach or contain a copy of lien claim.” The court *368 there said it could not be ascertained from the complaint as to contents of lien notice, whether compensation was sought for lumber, hardware, paint, plaster or brick nor whether work perf | 1 | 1949–1949 |
Hogan v. Bigler
green
2 sentences1949In Hogan v. Bigler, 1908, 8 Cal.App. 71 , 96 P. 97 , strictly interpreting the statute as so many earlier cases did under statutes similar to our own, the court held that required statement, among other things, “the name of the person to whom he furnished the materials,” was not met where lien stated and complaint alleged that lumber was sold to Crawford and evidence without conflict shows sale to one Hambleton, and the lower court so found. 1949In Hogan v. Bigler, 1908, 8 Cal.App. 71 , 96 P. 97 , strictly interpreting the statute as so many earlier cases did under statutes similar to our own, the court held that required statement, among other things, “the name of the person to whom he furnished the materials,” was not met where lien stated and complaint alleged that lumber was sold to Crawford and evidence without conflict shows sale to one Hambleton, and the lower court so found. | 1 | 1949–1949 |
George v. Wentworth
neutral
2 sentences1936The question is governed by our ruling in George et al. v. Wentworth, 56 Nev. 380 , 53 P.2d 1193 , wherein we held that this provision was intended to impose an additional requirement upon an owner in order to exempt his property from the effect of a lien claim. 1936The question is governed by our ruling in George et al. v. Wentworth, 56 Nev. 380 , 53 P.2d 1193 , wherein we held that this provision was intended to impose an additional requirement upon an owner in order to exempt his property from the effect of a lien claim. | 1 | 1936–1936 |
Riverside Fixture Co. v. Quigley
neutral
1 sentence1936This provision relative to amending a lien claim was first incorporated in our lien act in 1911 (Stats. 1911, chap. 160), but notwithstanding this fact, this court, in the case of Riverside Fixture Co. v. Quigley, 35 Nev. 17 , 126 P. 545 , in which the rights of claimant evidently accrued prior to the 1911 amendment, held that where the rights of third parties had not intervened, an amendment would be allowed. | 1 | 1936–1936 |
McClain v. Hutton
green
2 sentences1935J. p. 230; McClain v. Hutton, 131 Cal. 132 , 61 P. 273 , 63 P. 182 , 622; N. C. 1935J. p. 230; McClain v. Hutton, 131 Cal. 132 , 61 P. 273 , 63 P. 182 , 622; N. C. | 1 | 1935–1935 |
Counted by distinct opinions that both name this issue and are annotated to the section; sections every opinion cites regardless of issue are not filtered here, so read the counts against the total above.
Opinions by the citing court's state. A doctrine retained in one state and abandoned in another shows up here as a year span that stalls.